<,FoRN�P City Council Staff Report
November 22, 2016
Agenda Item No. 11
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Peter Tauscher, Civil Engineer
ptauscher@newportbeachca.gov
PHONE: 949-644-3316
TITLE: Newport Theater Arts Center Building Improvements — Notice of
Completion of Contract No. 7022-2 (Project No. 15F02)
ABSTRACT:
On June 28, 2016, City Council awarded Contract No. 7022-2 for the Newport Theater Arts
Center Building Improvements project to Optima RPN (Optima) of Irvine, California. The
total contract award was $188,851.00 plus $29,000.00 allowance for contingencies. The
required work is now complete and staff requests City Council acceptance and close out of
the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for
the project (This project was found exempt from the California Environmental Quality Act
(CEQA) pursuant to Sections 15301(a));
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of the
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
FUNDING REQUIREMENTS:
Funds for the construction contract were expensed from the following account:
Account Description
Facilities Maintenance Master Plan
Account Number
57101-98000-15F02
Amount
$ 191,949.00
Total: $ 191,949.00
DISCUSSION:
Newport Theater Arts Center Building Improvements —
Notice of Completion of Contract,
No. 7022-2 (15F02)
November 22, 2016
Page 2
Overall Contract Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract
Completion
Allowance
Contract
Directed
Unforeseen
Amount
Change
Change
Change
$188,851.00
$191,949.00
15% or less
+1.6%
-4.9%
+6.5%
Allowed Contract Time + Approved
60
Actual Time
3
Extensions days) =
Under (-) or Over (+)
Contract No. 7022-2, Newport Theater Arts Center Building has now been completed to the
satisfaction of the Public Works Department. A summary of this contract's construction cost
is as follows:
Original bid amount: $188,851.00
Actual Cost of Bid Items Constructed: $179,747.00
Total Change Orders: $ 12,202.00
Final contract cost: $191,949.00
The final cost of bid items constructed was $179,747.00, which was $9,104 less than the
original bid amount. During construction, after removal on the existing roofing material, field
inspection determined that more roof sheathing remained in suitable condition then
originally anticipated resulting in the bulk of this bid item savings.
Also during construction two change orders were issued totaling $12,202.00, which was
approximately 6.5 percent of the original contract amount and within the contingency
allowance. The first change order was issued that provided for replacement of two
additional structural beams. A second change order was issued to provide 15 additional
working days beyond the original contract time to allow the contractor to address a building
code requirement that 20% of the contract cost be used for Americans with Disabilities Act
(ADA) related improvements. This ADA effort was included in the Bid item allowance,
however the change order was needed to define the work effort and provide the necessary
time to complete the work to provide greater accessibility to the Newport Theater Arts
Center. Final ADA improvements included restriping ADA parking stalls, upgrading stair
access, and instating a dual height drinking fountain.
A summary of the project schedule is as follows:
Estimated Completion Date per Baseline Schedule November 25, 2016
Project Awarded for Construction June 28, 2016
Notice to Proceed August 10, 2016
Contract Completion Date with Approved Extensions November 7, 2016
Actual Substantial Construction Completion Date November 2, 2016
11-2
Newport Theater Arts Center Building Improvements —
Notice of Completion of Contract,
No. 7022-2 (15F02)
November 22, 2016
Page 3
ENVIRONMENTAL REVIEW:
The Newport Theater Arts Center Building Improvement project was found exempt from the
California Environmental Quality Act (CEQA) pursuant to Section 15301 (Existing Facilities).
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of the
meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
11-3
v
ATTACHMENT A
NEWPORT THEATER ARTS CENTER
BUILDING IMPROVEMENTS
15F02
LOCATION MAP
NOT TO SCALE
PROPERTY LIMITS
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7022-2 1 11/22/16
11-4