HomeMy WebLinkAbout08 - Tidegate Improvement Project - NOC of Contract No. 6270 (Project No. 15H19)December 13, 2016 Agenda Item No. 8 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Peter Tauscher, Civil Engineer ptauscher@newportbeachea.gov PHONE: 949-644-3316 TITLE: Tidegate Improvement Project - Notice of Completion of Contract No. 6270 (Project No. 15H19) ABSTRACT: On March 8, 2016, City Council awarded Contract No. 6270 for the Tidegate Improvement Project to Paulus Engineering, Inc. (Paulus). The total contract award was $168,710.00 plus $17,290.00 allowance for contingencies. The required work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project (On March 8, 2016, City Council found this project as exempt from the California Environmental Quality Act (CEQA) pursuant to Sections 15302(c)); b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release Faithful Performance Bond one year after acceptance by the City Council. FUNDING REQUIREMENTS: Funds for the construction contract were expensed from the following account: Account Description Account Number Amount Tidelands Maintenance 10001-980000-15H19 $ 170,402.49 Total: $ 170,402.49 8-1 DISCUSSION: Tidegate Improvement Project — Notice of Completion of Contract, No. 6270 (15H19) December 13, 2016 Page 2 Overall Contract Cost/Time Summary Awarded Final Cost at Contingency Actual % Due to % Due to Contract Completion Allowance Contract Directed Unforeseen Amount Change Change Change $168,710.00 $171,152.49 10% or less +1.4% 0.2% +1.2% Allowed Contract Time + Approved 117 Actual Time 6 Extensions days) = Under (-) or Over (+) Contract No. 6270, Tidegate Improvement Project has now been completed to the satisfaction of the Public Works Department. A summary of this contract's construction cost is as follows: Original bid amount: Actual Cost of Bid Items Constructed: Total Change Orders: Final contract cost: $168,710.00 $169,210.00 $ 1,942.49 $171,152.49 The actual cost of bid items constructed was $169,210.00 which was slightly more than the original bid amount due to increasing the quantity of manhole steps needed to complete the project. There was one change order totaling $1,942.00, which amounted to 1.2 percent of the original contract amount and within the contingency allowance. The change order included substituting cast iron hardware for stainless steel and adding a double seal on all three actuators. This change will provide increased corrosion resistance for the submerged equipment. A summary of the project schedule is as follows: Estimated Completion Date per Baseline Schedule November 11, 2016 Project Awarded for Construction March 8, 2016 Notice to Proceed April 19, 2016 Contract Completion Date with Approved Extensions October 12, 2016 Actual Substantial Construction Completion Date October 4, 2016 The project was substantially complete as of October 4, 2016. Some miscellaneous punch list items, operation & maintenance turnover, and post -substantial completion will be finalized prior to the Notice of Completion action. Tidegate Improvement Project — Notice of Completion of Contract, No -6270051-119) December 13, 2016 Page 3 ENVIRONMENTAL REVIEW: On March 8, 2016, City Council found this Environmental Quality Act (CEQA) pursuant t reconstructing of existing utility system and/or expansion of capacity). NOTICING: action exempt from the California o Section 15302(c) (Replacing or facility involving negligible or no The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Attachment A - Location Map CITY OF COSTA MESA VICTORIA ST R JOHN WAYNE AIRPORT PROJECT LOCATIONS CITY OF IRVINE ATTACHMENT A 01 NTS 2015-2016 TIDEGATE CITY OF NEWPORT BEACH IMPROVEMENT PROJECT PUBLIC WORKS DEPARTMENT 151-119 C-6270 12/13/16 LOCATION MAP 8-4