September 12, 2017
Agenda Item No. 7
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Bob Stein, Assistant City Engineer, rstein@newportbeachca.gov
PHONE: 949-644-3322
TITLE: Big Canyon Restoration and Water Quality Improvement Project -
Notice of Completion for Contract No. 8111-1 (Project No. 15X12)
ABSTRACT:
On September 13, 2016, City Council awarded Contract No. 8111 to construct features
to improve water quality in Big Canyon Creek and replace invasive plants with native
vegetation on the six -acre site. The work is now substantially complete and staff
requests City Council acceptance and close out of the contract.
RECOMMENDATIONS:
a) Accept the completed work and authorize the City Clerk to file a Notice of
Completion for the project. On May 10, 2016, the City Council adopted Resolution
No. 2016-58 adopting Mitigated Negative Declaration No. ND2016-001 (SCH#
2016031011), pursuant to the California Environmental Quality Act (CEQA) and City
Council Policy K-3;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
the Civil Code; and
c) Release Faithful Performance Bond one (1) year after acceptance by the City
Council.
FUNDING REQUIREMENTS:
Funds for the construction contract were expensed from the following accounts:
7-1
Big Canyon Restoration and Water Quality Improvement Project —
Notice of Completion for Contract No. 8111-1 (Project No. 15X12)
September 12, 2017
Page 2
Account Description
Measure M Competitive
Contributions
OCSD Reimbursement
General Fund
DISCUSSION:
Account Number
1230052-980000-15X 12
13501-980000-15X12
01201928-980000-15X 12
01201926-980000-17011
Total
Overall Contract Cost/Time Summary
Amount
$1,432,780.00
443,947.07
21,472.00
33,947.04
$1,932,146.11
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$1,782,230.00
$1,932,146.11
10% or less
+8.4%
+5.8%
+2.6%
Allowed Contract Time +
155+48
Actual Time
42
Approved Extensions (days) =
Under (-) or Over (+)
The work necessary to complete this contract included constructing a storm water
drainage piping and structures to capture storm flows from Jamboree Road and direct
flows to a bio -retention cell infiltration system, constructing a bypass system for Big
Canyon creek to isolate groundwater flows under Jamboree Road, diverting
groundwater flows with high selenium concentration to the sanitary sewer, creating a
trail system, installing an improved access road from Jamboree Road, providing an
irrigation system for the six -acre site and planting native plants. The contracted work
has now been completed to the satisfaction of the Public Works Department.
A summary of the construction cost is as follows:
Original Bid Amount:
Actual Cost of Bid Items Constructed:
Total Change Orders:
Final Contract Cost:
$1,782,230.00
$1,790,723.02
$ 141,423.09
$1,932,146.11
The actual cost of bid items constructed was $8,493 more than the original bid amount
due to actual amount of sediment removed.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule
9/13/16
Actual Start of Construction Per Notice To Proceed
9/29/16
Extended Contract Completion Date Inclusive of Extra Work
5/8/17
Actual Substantial Construction Completion Date
6/19/17
7-2
Big Canyon Restoration and Water Quality Improvement Project —
Notice of Completion for Contract No. 8111-1 (Project No. 15X12)
September 12, 2017
Page 3
The project was substantially complete, including planting, as of June 19, 2017. The
contractor will complete its 120 -day plant establishment and maintenance requirements
on October 19, 2017.
ENVIRONMENTAL REVIEW:
On May 10, 2016, City Council adopted Resolution No. 2016-58, A Resolution of the
City Council of the City of Newport Beach adopting Mitigated Negative Declaration No.
ND2016-001 (SCH# 2016031011) for the Big Canyon Habitat Restoration & Water
Quality Improvement Project (PA2016-046), Attachment C, pursuant to California
Environmental Quality Act, State CEQA Guidelines and City Council Policy K-3).
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
7-3
Attachment A
Project Ea-�, carp - .. Lltit
4 ria
i ys:
Big Canyon Habitat Restoration and
Water Quality Improvements
Location Map
lost
r,
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
Project 15X12 5/10/16