Loading...
HomeMy WebLinkAbout09 - Central and Mariners Libraries Restrooms Rehabilitation Project — NOCP0 m CITY OF z NEWPORT BEACH City Council Staff Report September 12, 2017 Agenda Item No. 9 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Fong Tse, Assistant City Engineer ftse@newportbeachca.gov PHONE: 949-644-3321 TITLE: Central and Mariners Libraries Restrooms Rehabilitation Project — Notice of Completion — Contract No. 8135-1 (Project No. 15F02) ABSTRACT: On November 22, 2016, City Council awarded the Central and Mariners Libraries Restrooms Rehabilitation Project (Contract No. 8135-1) to New Dynasty Construction Company for a base $429,810.00 contract plus a $43,190.00 contingency amount for unforeseen work. The work is now complete and staff requests City Council project acceptance and contract close out. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project. On November 22, 2016, the City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301(a); b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release Faithful Performance Bond one (1) year after acceptance by the City Council. FUNDING REQUIREMENTS: Funds for the construction contract were expensed from the following account: Account Description Account Number Amount Facilities Maintenance Master Plan 57101-980000-15F02 $463,928.70 Total: $463,928.70 9-1 Central and Mariners Libraries Restrooms Rehabilitation Project — Notice of Completion — Contract No. 8135-1 (Project No. 15F02) September 12, 2017 Page 2 DISCUSSION: The Central Library and the Mariners Branch Library were constructed more than twenty and ten years ago, respectively. The public restrooms in these two buildings are heavily used and have not been renovated since they first entered service. In addition to the aesthetics, the Facilities Maintenance Master Plan identified a number of items such as partitions, sinks, flooring, countertops, lighting and fixtures that need to be either updated or replaced. Accordingly, this project removed all of the original improvements and completely remodeled these facilities from bare walls and floors. Upon construction, the project team discovered numerous pre-existing issues that were not apparent during the design nor building permit plan check. A summary change order was issued to cover the extra cost and work days of these unforeseen repairs. They included (in the Central Library) the pip lining of a disjointed and poorly functioning sewer line below the existing post -tensioned concrete floor; the replacement of a clogged drain line behind the walls in one of the public restrooms; the repair of several metal studs where their lower sections were completely corroded between wet walls; the installation of a large water supply shutoff valve for each of restrooms so that the water can be turned off for restroom areas and the rehabilitation work to proceed; the installation of an automatic door opener per building inspection. In the Mariners Library, the complete reconstruction of the concrete restroom floors and the installation of moisture barriers to contain the recurrent migration of moisture from the ground, and the installation of water supply shutoff valves. This unforeseen repair work accounted for two-thirds of the total $34,118.70 change order amount. The remaining one-third of the total change order amount was staff -directed items modifications including the addition of baby changing stations; wall mosaic coverings to discourage markings; and the sealing of floor tiles to provide enhanced public service and to reduce future maintenance and serviceability costs on items. Overall Contract Cost/Time Summary Awarded Final Cost at Contingency Actual % Due to % Due to Contract Completion Allowance Contract Directed Unforeseen Amount Change Change Change $429,810.00 $463,928.70 10% or less 1 +7.94% 1 +2.78% +5.16% Allowed Contract Time + Approved 130 Actual Time -7 Extensions days) = Under (-) or Over (+) This Project has now been completed to the satisfaction of the Public Works Department. A summary of this contract's construction cost is as follows: Original Bid Amount: Actual Cost of Bid Items Constructed: Total Change Orders: Final Contract Cost: $429,810.00 $429,810.00 $ 34,118.70 $463,928.70 9-2 Central and Mariners Libraries Restrooms Rehabilitation Project — Notice of Completion — Contract No. 8135-1 (Project No. 151`02) September 12, 2017 Page 3 A summary of the project schedule milestones is as follows: Estimated Start of Construction per Annual Baseline Schedule 11/22/16 Actual Start of Construction Per Notice To Proceed 1/2/17 Extended Contract Completion Date Inclusive of Extra Work 8/18/2017 Actual Substantial Construction Completion Date 8/9/2017 ENVIRONMENTAL REVIEW: On November 22, 2016, City Council found this action exempt from the California Environmental Quality Act (CEQA) pursuant to 15301(a) of the CEQA Guidelines for Existing Facilities because the in-kind and in-place rehabilitation of the existing interior restrooms will not result in a physical change to the environment, directly or indirectly. NOTICING: This agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENT: Attachment A — Location Map 9-3 Sj OCG\ MARINERS PARK MARINERS LIBRARY LEGEND PROJECT LOCATION CENTRAL / MARINERS LIBRARIES RESTROOMS REHABILITATION (15F02) LOCATION MAP Attachment A N.T.S. CENTRAL ^\ LIBRARY, \ CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C-8135-1 1 09/12/17 9-4