City Council Staff Report
May 22, 2018
Agenda Item No. 11
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: John Kappeler, Senior Civil Engineer,
jkappeler@newportbeachca.gov
PHONE: 949-644-3218
TITLE: Bayview Heights Drainage Project — Award of Contract No. 7109-1
(15X11)
ABSTRACT:
Staff has received construction bids for Bayview Heights Drainage Project and requests
City Council approval to award the construction contract to Jeremy Harris Construction,
Inc. (Jeremy Harris Construction) of Riverside, California.
RECOMMENDATIONS:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15333 (Small Habitat Restoration Projects) and Section 15304
(Class 4 Minor Alterations to Land) of the CEQA Guidelines, because it has no
potential to have a significant effect on the environment;
b) Approve the project drawings and specifications;
c) Award Contract No. 7109-1 to Jeremy Harris Construction for the total bid amount of
$313,874.70, and authorize the Mayor and City Clerk to execute the contract;
d) Establish a contingency of $31,300.00 (approximately 10% of Total Bid) to cover the
cost of unforeseen work not included in the original contract; and
e) Approve Budget Amendment No. 18BA-038 transferring $77,000.00 from project
savings from Account No. 10001-980000-15H19 (Tidegate Retrofit Project) to
Account No. 10001-980000-15X11 for the Bayview Heights Drainage Project.
FUNDING REQUIREMENTS:
Upon approval of the proposed budget amendment, sufficient funding is available for the
award of this contract. Project funding will be expensed from the following accounts:
Bayview Heights Drainage Project — Award of Contract No. 7109-1
May 22, 2018
Page 2
Account Description Account Number Amount
Measure M Competitive 1230052-980000-15X11 $ 274,921.94
General Fund 01201928-980000-15X11 $ 5,837.06
Tidelands Maintenance 10001-980000-15X11 $ 81,080.00
Total: $ 361,839.00
Proposed uses are as follows:
Account Description
Jeremy Harris Construction
Jeremy Harris Construction
On -Call Geotechnical
On-call Professional
Various
DISCUSSION:
Purpose Amount
Construction Contract $ 313,874.70
Contingency $ 31,300.00
Professional/Technical Services $ 5,300.00
Environmental/Biological Services $ 10,000.00
Printing/Incidentals $ 1,364.30
Total: $ 361,839.00
At 11:00 a.m. on April 24, 2018, the City Clerk opened and read the following bids for this
project:
The bid amount submitted by Jeremy Harris Construction is two percent below the
Engineer's Estimate of $320,000. Jeremy Harris Construction possesses a California
State General Building "A" Contractors License and one of its Subcontractors, possess a
"Class C-27" License, as required by the project specifications, and has satisfactorily
completed similar grading and pipeline projects for other local agencies.
Pursuant to the contract specifications, Jeremy Harris Construction is allotted 120
Calendar days to complete the work. Liquidated damages in the amount of $500.00 per
calendar day will be assessed in case of tardy completion.
This project includes installation of 520 linear feet of 24 -inch reinforced concrete pipe from
Mesa Drive to a vegetated basin designed for energy dissipation and to improve water
quality. Eroded areas will be filled and the hillside slope revegetated to provide erosion
protection. Proposed improvements at the upper end of the project will be constructed
within easements that have been granted by the owners on two residential properties
(2600 and 2612 Mesa Drive) with the improvements on the lower end of the project
constructed on property owned by County of Orange and State of California. Staff is
working with the County of Orange and State of California to finalize easements.
11-2
BIDDER
TOTAL BID AMOUNT
Low
Jeremy Harris Construction
$313,874.70
2nd
Aramexx Construction
$338,294.50
3rd
Wright Construction Engineering Corp.
$377,000.00
4th
GMC Engineering Inc.
$397,000.00
5th
KASA Construction
$419,980.50
6th
GRFCO, Inc.
$469,013.50
7th
Excel Paving
$473,546.00
8th
Beador Construction Company Inc.
$533,700.00
9th
GCI Construction Inc.
$621,372.00
The bid amount submitted by Jeremy Harris Construction is two percent below the
Engineer's Estimate of $320,000. Jeremy Harris Construction possesses a California
State General Building "A" Contractors License and one of its Subcontractors, possess a
"Class C-27" License, as required by the project specifications, and has satisfactorily
completed similar grading and pipeline projects for other local agencies.
Pursuant to the contract specifications, Jeremy Harris Construction is allotted 120
Calendar days to complete the work. Liquidated damages in the amount of $500.00 per
calendar day will be assessed in case of tardy completion.
This project includes installation of 520 linear feet of 24 -inch reinforced concrete pipe from
Mesa Drive to a vegetated basin designed for energy dissipation and to improve water
quality. Eroded areas will be filled and the hillside slope revegetated to provide erosion
protection. Proposed improvements at the upper end of the project will be constructed
within easements that have been granted by the owners on two residential properties
(2600 and 2612 Mesa Drive) with the improvements on the lower end of the project
constructed on property owned by County of Orange and State of California. Staff is
working with the County of Orange and State of California to finalize easements.
11-2
Bayview Heights Drainage Project — Award of Contract No. 7109-1
May 22, 2018
Page 3
Regulatory agencies have issued permits for the project including approval of the Coastal
Development Permit by the California Coastal Commission on July 13, 2017. At that time,
the Coastal Commission also reaffirmed the CEQA finding for the project. Construction
is expected to start this summer and be substantially complete in the Fall. Staff is
expecting to work closely with the regulatory agencies during the construction and
anticipates the need for professional biological monitoring which will be performed under
a separate agreement.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15333 (Small Habitat Restoration
Projects) and Section 15304 (Class 4 Minor Alterations to Land) of the CEQA Guidelines,
because it has no potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
Attachment B — Budget Amendment
11-3
4r�
✓f F - - `Tr --07
PROJECT
k ITE
0114
7ff"q
Ink
NEWPORT BACK BAY
?"w
Bayview Heights Drainage Project
Location Map
Attachment A
f
4 J'
I,
{
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-8046-1 1 10/10/17
City of Newport Beach
BUDGET AMENDMENT
2017-18
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates
Increase Expenditure Appropriations AND
X Transfer Budget Appropriations
SOURCE:
X from existing budget appropriations
from additional estimated revenues
from unappropriated fund balance
EXPLANATION:
ATTACHMENT B
NO. BA- 18BA-038
$77,000.00
Increase in Budgetary Fund Balance
Decrease in Budgetary Fund Balance
X No effect on Budgetary Fund Balance
ONE-TIME?
B Yes
No
This budget amendment is requested to provide for the following:
To transfer expenditure appropriations from the Tidegate Retrofit project to the Bayview Heights Drainage project.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Object
REVENUE ESTIMATES
0 r Object
EXPENDITURE APPROPRIATIONS
Org Object Project
10001 980000 15H19
10001 980000 15X11
Signed: /',b
Signed
Signed
Financial 7Cooroval: -Finance
Description
Description
Amount
Debit Credit
Description
Tidegate Retrofit Project $77,000.00
151 -119 -CONSTRUCT -UNASSIGNED
Bayview Heights Drainage Project $77,000.00