City Council Staff Report
July 10, 2018
Agenda Item No. 5
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Peter Tauscher, Senior Civil Engineer
ptauscher@newportbeachca.gov
PHONE: 949-644-3316
TITLE: Notice of Completion for Fire Station No. 6 Apparatus Bay
Replacement — Contract No. 6422 (Project No. 16F11)
ABSTRACT:
On June 13, 2017, City Council awarded Contract No. 6422 for the Fire Station No. 6
Apparatus Bay Replacement Project to Metro Builders & Engineers Group, Ltd. The
required work is now complete and staff requests City Council acceptance and close out
of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project. On June 13, 2017, City Council found this action exempt from the
California Environmental Quality Act (CEQA) pursuant to Section 15302
(Replacement or Reconstruction);
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of the
Civil Code; and
c) Release Faithful Performance Bond one (1) year after acceptance by the City Council.
FUNDING REQUIREMENTS:
Funds for the construction contract were expensed from the following account:
Account Description Account Number
Fire Station 6 — Mariners 53201-980000-16F11
Facilities Maintenance Master Plan 57101-980000-18F02
Fire Station 5 — Corona del Mar 53201-980000-15F12
Total: $
Amount
1,009,089.84
43,050.64
10,400.00
1, 062, 540.48
5-1
Notice of Completion for Fire Station No. 6 Apparatus Bay Replacement —
Contract No. 6422 (Project No. 16F11)
July 10, 2018
Page 2
DISCUSSION:
The existing fire station, constructed in 1957, included an apparatus bay sized to
accommodate equipment used in that era. Since then, fire engines and medical response
rolling equipment have grown in size to the extent that the new fire engine assigned to
this station no longer fit through the existing garage doors. Prior to the completion of this
project, the newest truck was parked under a tent when on station property. This project
concentrated on replacing the undersized apparatus bay as well as building a new
structure that met current building and seismic codes.
Overall Contract Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract
Completion
Allowance
Contract
Directed
Unforeseen
Amount
Change
Change
Change
$977,868.00
$1,062,540.48
10% or less
+8.7%
8.7%
0%
Allowed Contract Time + Approved
170
Actual Time
-5
Extensions days) =
Under (-) or Over (+)
Contract No. 6422, Fire Station No. 6 Apparatus Bay Replacement has been completed
to the satisfaction of the Public Works Department. A summary of this contract's
construction cost is as follows:
Original Bid Amount: $977,868.00
Actual Cost of Bid Items Constructed: $977,868.00
Total Change Orders: $ 84,672.48
Final Contract Cost: $1,062,540.48
The actual cost of contract bid items constructed was awarded bid price of $977,868.00.
Two change orders were issued totaling $84,672.48, an 8.7 percent increase over the
original contract amount, and were within the contingency allowance. The change orders
included removing and replacing the existing roof and rotting wood on the adjacent fire
station residence quarters; making HVAC repairs; changing out signage; and installing
additional concrete that was not included on the drawings. The additional change order
work also included site preparation work for establishing the Corona del Mar temporary
Fire Station #5 across from the Oasis Senior Center. The work at the temporary Fire
Station #5 included connecting water, sewer, and electricity utilities and preparing the
facility for use by fire personnel during the Corona del Mar Fire Station #5/Library
Replacement Project.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule
10/30/2017
Actual Start of Construction Per Notice To Proceed
9/11/2017
Extended Contract Completion Date Inclusive of Extra Work
5/15/2018
Actual Substantial Construction Completion Date
5/9/2018
5-2
Notice of Completion for Fire Station No. 6 Apparatus Bay Replacement —
Contract No. 6422 (Project No. 16F11)
July 10, 2018
Page 3
ENVIRONMENTAL REVIEW:
On June 13, 2017, City Council found this action exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302 (Replacement or
Reconstruction) is a new garage structure that occupies the same space as the existing
garage and will have the same purpose and capacity to house fire station vehicles of the
CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
5-3
N.T.S.
ATTACHMENT A
LEGEND
im/11% � � � � �
FIRE STATION NO. 6
APPARATUS BAY REPLACEMENT
LOCATION MAP
MAR KERS ORNE
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-6422-2 1 06/26/18
5-4