City Council Staff Report
July 24, 2018
Agenda Item No. 4
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Brad Sommers, Principal Civil Engineer
bsommers@newportbeachca.gov
PHONE: 949-644-3326
TITLE: Balboa Peninsula Pedestrian Crossing Improvement Project— Notice
of Completion for Contract No. 7288-1 (18T03)
ABSTRACT:
On March 27, 2018, City Council awarded Contract No. 7288-1, for the first phase of the
Balboa Peninsula Pedestrian Crossing Improvement Project to Excel Paving (Excel). The
work is now complete and staff requests City Council acceptance and close out of the
contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project. On March 27, 2018, the City Council found this project exempt from
the California Environmental Quality Act (CEQA) pursuant to Class 1 Section
15301(c);
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
FUNDING REQUIREMENTS:
The construction contract was expensed from the following account:
Account Description
General Fund (18T03)
Account Number
01201927-980000-18T03
Amount
$ 408,752.04
$ 408,752.04
4-1
Balboa Peninsula Pedestrian Crossing Improvement Project —
Notice of Completion for Contract No. 7288-1 (18T03)
July 24, 2018
Page 2
DISCUSSION:
The completed (Phase 1) Balboa Crossing Improvement project included signing, striping
and pavement enhancements at 45 crosswalk locations along the Balboa Peninsula.
(Phase 2 is being planned for this current fiscal year.)
Overall Contract Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$386,307.00
$408,752.04
10% or less
+5.8%
+5.8%
+0.0%
Allowed Contract Time +
40
Actual Time
2
Approved Extensions (days) =
Under (-) or Over (+)
The contracted work has now been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original bid amount:
Actual Cost of Bid Items Constructed:
Total Change Orders:
Final Contract Cost:
$386,607.00
$404,577.38
$4,174.66
$408,752.04
The final contract cost of $408,627.43 is 5.8 percent higher than the original bid amount.
This cost increase was primarily due to roadway paving added to repair damaged
pavement adjacent to the crosswalk locations.
This project included three change orders for a total amount of $4,174.66, which is
approximately 1 percent of the original bid amount. Change orders were issued to revise
the thermoplastic striping mixture to increase slip resistance and retroreflectivity of the
crosswalk striping and to replace additional deteriorated signage within the project area.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule
3/12/18
Actual Start of Construction Per Notice to Proceed
4/16/18
Extended Contract Completion Date Inclusive of Extra Work
6/11/18
Actual Substantial Construction Completion Date
6/7/18
4-2
Balboa Peninsula Pedestrian Crossing Improvement Project —
Notice of Completion for Contract No. 7288-1 (18T03)
July 24, 2018
Page 3
ENVIRONMENTAL REVIEW:
On March 27, 2018, the City Council found this project to be exempt from the California
Environmental Quality Act (CEQA) pursuant to Sections 15301 Class 1 (c) (maintenance
of existing public facilities involving negligible or no expansion of use) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
4-3
�9\
1-0
09
BALBOA BLVD.
BALBOA BLVD.
•
44TH
ST.
•
18TH ST.
•
42ND
ST.
•
17TH ST.
•
40TH
ST.
•
16TH ST.
•
38TH
ST.
•
14TH ST.
•
36TH
ST.
•
13TH ST.
•
35TH
ST.
•
12TH ST.
•
34TH
ST.
•
11TH ST.
•
32ND
ST.
•
10TH ST.
•
31ST
ST.
•
9TH ST.
•
30TH
ST.
•
8TH ST.
•
28TH
ST.
•
7TH ST.
•
26TH
ST.
•
6TH ST.
•
23RD
ST.
•
ISLAND AVE.
•
22ND
ST.
•
MEDINA WY.
•
21ST
ST.
•
CORONADO ST.
•
20TH
ST.
•
N/0 CYPRESS
•
19TH
ST.
•
ADAMS ST.
BALBOA BLVD.
ST.
• PALM ST.
• WASHINGTON
• MAIN ST.
• E ST.
• G ST.
• 1 ST.
• W/O SERRANO AVE.
ATTACHMENT A
NEWPORT BLVD.
• 23RD ST.
ST. • 26TH ST.
• 28TH ST.
• 30TH ST.
BALBOA PENINSULA CROSSWALK
IMPROVEMENT PROJECT
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
7/24/2018