HomeMy WebLinkAbout11 - Newport Beach Sand Replenishment MaintenanceTO: FROM: CITY OF NEWPORT BEACH City Council Staff Report PREPARED BY: PHONE: TITLE: ABSTRACT: August 14, 2018 Agenda Item No. 11 HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov Michael J. Sinacori, P.E., Assistant City Engineer 949-644-3342, Msinacori(a)_newportbeachca.gov Newport Beach Sand Replenishment Maintenance — Notice of Completion for Contract No. 8309-1 (17H04) On February 28, 2017, City Council awarded Contract No. 8309-1 (17H04) for Newport Beach Sand Replenishment Maintenance, to GCI Construction, Inc., in concert with the Lower Santa Ana River Sand Management project by the County of Orange. The required work is now complete and staff requests City Council's acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project. The County of Orange processed Addendum IP -15-359 as part of Environmental Impact Report No. 583 for the necessary environmental clearances and regulatory permitting for the project-, b) Authorize City Clerk to release Labor & Materials Bond 65 days after Notice of Completion has been recorded in accordance with applicable portions of the Civil Code-, and c) Release Faithful Performance Bond one (1) year after acceptance by the City Council. FUNDING REQUIREMENTS: Funds for the construction contract were expensed from the following account: Account Description Account Number Amount Tidelands Maintenance 10001-980000-17H04 $329,691.16 General Fund 01201928-980000-17H04 $414,000.00 General Fund 01201938-980000-19H04 $ 65,525.00 Environmental Contributions 13801-980000-17H04 $ 9,783.84 $819,000.00 Newport Beach Sand Replenishment Maintenance — Notice of Completion No. 8309-1 (171-104) August 14, 2018 Page 2 DISCUSSION: In the 2017/18 fiscal year, the County of Orange was dredging approximately 800,000 cubic yards (CY) from the lower Santa Ana River and placing this material within the near shore area along West Newport Beaches. As part of their project, the County also agreed to provide and stockpile up to 50,000 CY of beach sand for the City as part of the September 27, 2016 Council Approved Cooperative Agreement with the County. This contract also allowed for approximately 25,000 CY of sand to be placed on Balboa Island and China Cove. In addition, this effort included minor maintenance activities within West Newport and Balboa Peninsula for moving accumulated beach sands to areas where sand has been lost during this past year's winter storms. Between 2016's EI Nino's storms (heavy winds and sea currents) and rain events, significant oceanfront erosion has been realized. This contract took full advantage of the County's effort to manage the sand buildup in the lower Santa Ana River to maximize the City's effort to address the erosion and sand displacement areas along the City beach area. In addition to working with the County on lower Santa Ana River large sand management project, staff also coordinated with the County maintenance staff during last year's normal river mouth sand maintenance effort and again used GCI to further place this river mouth sand in areas of need on the Peninsula. The original plan allowed the contractor to have 45 consecutive working days to complete the work prior to Memorial Day 2017. However, the County of Orange was unable to remove all the necessary sand near the Santa Ana River Mouth prior to summer and arranged for their contractor or maintenance staff to return the following fall to complete the work. GCI agreed to hold their bid prices and was mobilized two additional times to complete our city sand maintenance as part of this contract, while adjusting to the County's changing operation. No additional mobilization charges or increases to the bid prices occurred with the extended contract efforts. With the opportunity to receive additional high quality sand and the increased need for city beach sand management, additional work was completed within the bid quantities resulting in an 8.7% increase in the final contract cost. Overall Contract Cost/Time Summary Awarded Final Cost Contingency Actual %Due to %Due to Contract at Allowance Contract Directed Unforeseen Amount Completion Change Change Change $753,475.00 $819,000.00 10% 8.7% 8.7% 0% Allowed Contract Time + Actual Time Under (-) or Approved Extensions N/A Over (+) N/A da s = Contract No. 8309-1, Newport Beach Sand Replenishment Maintenance, has now been completed to the satisfaction of the Public Works Department. A summary of this contract's construction cost is as follows: 11-2 Newport Beach Sand Replenishment Maintenance — Notice of Completion No. 8309-1 (17H04) August 14, 2018 Page 3 Original Bid Amount: $753,475.00 Actual Cost of Bid Items Constructed: $819,000.00 Total Change Orders: $ 0.00 Final Contract Cost: $819,000.00 ENVIRONMENTAL REVIEW: The County of Orange processed Addendum IP -15-359 to its 1989 Environmental Impact Report No. 583 related to this project which was recorded April 29, 2016. The addendum also addressed the City of Newport, San Clemente and Huntington Beach utilizing portions of the LSR sand for beach nourishment in needed city areas. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENT: Attachment A — Location Map 11-3 ATTACHMENT A JOHN WAYNE AIRPORT PROJECT LOCATIONS 1 - BALBOA ISLAND 2 - CHINA COVE NTS NEWPORT BEACH CITY OF NEWPORT BEACH SAND REPLENISHMENT PUBLIC WORKS DEPARTMENT MAINTENANCE C-8309-1 LOCATION MAP PROJECT 17H04 814/18