HomeMy WebLinkAbout09 - Balboa Village Streetscape ImprovementsTO:
FROM:
CITY OF
NEWPORT BEACH
City Council Staff Report
November 13, 2018
Agenda Item No. 9
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Patrick Arciniega, Senior Civil Engineer
parciniega(a-)_newportbeachca.gov
PHONE: 949-644-3347
TITLE: Balboa Village Streetscape Improvements — Award of Contract
No. 7489-1 (17R11)
ABSTRACT:
Staff has received acceptable construction bids for the Balboa Village Streetscape
Improvements project to restore or install new plants, trees, planters, trash receptacles
and benches, as well as remove and replace existing damaged sidewalk and curb & gutter
in Balboa Village. Staff requests City Council's approval to award the construction
contract to Optima RPM.
RECOMMENDATIONS:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15302(c) (reconstruction of existing facility involving negligible or
no expansion of capacity) of the CEQA Guidelines, California Code of Regulations,
Title 14, Chapter 3, because it has no potential to have a significant effect on the
environment;
b) Approve the project drawings and specifications;
c) Award Contract No. 7489-1 to Optima RPM for the total bid price of $672,880.72, and
authorize the Mayor and City Clerk to execute the contract;
d) Approve Budget Amendment No. 19BA-016 appropriating $181,000.00 from the
unappropriated Balboa Village Parking Management fund balance to Account
No. 53501-980000-17R11 and $230,000.00 from the unappropriated Measure M Fair
Share fund balance to Account No.12201-980000-17R11 for the Balboa Village
Streetscape Improvements project; and
e) Establish $33,000.00 (approximately 5 percent) contingency amount to cover the cost
of unforeseen work not included in the original contract.
9-1
Balboa Village Streetscape Improvements — Award of Contract No. 7489-1 (17R11)
November 13, 2018
Page 2
FUNDING REQUIREMENTS:
Upon approval of the budget amendment, sufficient funding is available for this project.
The following funds will be expensed:
Account Description
Account Number
Amount
Balboa Village Parking Mgmt
53501-980000-17R11
$
477,000.00
Measure M Fair Share
12201-980000-17R11
230,000.00
Total:
$
707,000.00
Proposed fund uses are as follows:
Vendor
Purpose
Amount
Optima RPM
Construction Contract
$
672,880.72
Optima RPM
Construction Contingency
$
33,000.00
Various
Printing & Incidentals
$
1,119.28
Total:
$
707,000.00
Staff recommends establishing approximately a five (5) percent contingency for
unforeseen conditions associated with construction.
DISCUSSION:
The Balboa Village Advisory Committee (BVAC) was established by the City Council in
September 2012 to oversee the timely implementation of the Balboa Village Master Plan.
Proposed improvement plans for Balboa Village include an update to the Balboa Village
Design Guidelines, development of a Wayfinding Sign Program to better direct motorists
to parking facilities and pedestrians to surrounding attractions, and a streetscape
improvement plan to refresh the public realm within the Village.
The existing streetscape and public rights-of-way in Balboa Village are generally in good
condition, but there is room for improvement. Since 2000, the City has invested over
$12 million in the area, including new decorative sidewalks, street trees, and planters.
This Streetscape Improvement Plan recognizes the public improvements already made
in the area, but includes direction for an enhanced landscape/streetscape design plan
which serves as the overarching theme for the area. The sidewalks and circulation
system are already appropriate for the area, so current improvement efforts focus on
landscaping, furniture, and lighting maintenance and replacement.
The focus of this project will be to refurbish and restore the existing streetscape
improvements originally installed between 2002 and 2004. Specifically, this project will
replace all the large aging terra cotta planter pots with new matching planter pots in dark
navy color, re -finish existing navy color planters in place, re -powder coat brackets of
hanging planters, replace seasonal faux plants in the terra cotta hanging planters with
new navy color pots and plants, enlarge palm tree wells where palms are out -growing
and uplifting the lithocrete sidewalk, as well as install new trash receptacles and benches.
9-2
Balboa Village Streetscape Improvements — Award of Contract No. 7489-1 (17R11)
November 13, 2018
Page 3
As part of the project, additional repairs to the existing village lithocrete hardscape are
recommended. Several sections of lithocrete are currently uplifted due to adjacent
landscaping, and are tripping hazards. Other areas have been cut into over the years
for utilities and patched back with concrete. Since landscaping and irrigation
maintenance is included in this rehabilitation plan, it was suggested to remove some of
the lithocrete on Washington Street to allow more room for the growing palm trees, allow
for additional landscaping and reduce the amount of lithocrete in the area without
impacting the design theme. Additional lithocrete sidewalk repairs total approximately
1,600 square feet, which equates to $230,170 of the total project cost. Staff is
recommending proceeding with streetscape improvement as noted above, including the
additional lithocrete sidewalk repairs work. Funding will come from available BVAC
parking revenues as well as Measure M funds.
At 11 a.m. on October 11, 2018, the City Clerk opened and read the following electronic
bids for this project:
The low bid amount is 9.1 percent above the Engineer's Estimate of $616,500.00. The
low bidder, Optima RPM, possesses a California State Contractors License Classification
"A" and its subcontractor, Inland Empire Landscape, Inc., possesses a "C-27" as required
by the project specifications. A check of the contractor's references indicates satisfactory
completion of projects for the City of Newport Beach and other public agencies.
Pursuant to the Contract Specifications, the Contractor will have 90 consecutive working
days to complete the work. Public notices and construction work is expected to begin
with a soft start in December with the approval of the construction contract. Construction
completion is scheduled for Spring 2019.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(c) (reconstruction of
existing facility involving negligible or no expansion of capacity) of the CEQA Guidelines,
California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a
significant effect on the environment.
9-3
BIDDER
TOTAL BID AMOUNT
Low
Optima RPM
$672,880.72
2nd
United GLI
$685,316.00
3rd
Mariposa Landscapes, Inc.
$703,600.89
4t"
Marina Landscape, Inc.
$790,190.00
5t"
Environmental Construction, Inc.
$825,353.18
6t"
Aramexx Construction
$898,125.00
7t"
Yakar
$971,835.00
The low bid amount is 9.1 percent above the Engineer's Estimate of $616,500.00. The
low bidder, Optima RPM, possesses a California State Contractors License Classification
"A" and its subcontractor, Inland Empire Landscape, Inc., possesses a "C-27" as required
by the project specifications. A check of the contractor's references indicates satisfactory
completion of projects for the City of Newport Beach and other public agencies.
Pursuant to the Contract Specifications, the Contractor will have 90 consecutive working
days to complete the work. Public notices and construction work is expected to begin
with a soft start in December with the approval of the construction contract. Construction
completion is scheduled for Spring 2019.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(c) (reconstruction of
existing facility involving negligible or no expansion of capacity) of the CEQA Guidelines,
California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a
significant effect on the environment.
9-3
Balboa Village Streetscape Improvements — Award of Contract No. 7489-1 (17R11)
November 13, 2018
Page 4
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
Attachment B — Budget Amendment
NE
ATTACHMENT A
6 LIMITS OF WORK ®®
NTS
BALBOA VILLAGE
LANDSCAPING IMPROVEMENTS
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7489-1 1/13/18
9-5
ATTACHMENT B City of Newport Beach
BUDGET AMENDMENT
2018-19
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates
X Increase Expenditure Appropriations
Transfer Budget Appropriations
SOURCE:
from existing budget appropriations
from additional estimated revenues
X from unappropriated fund balance
EXPLANATION:
NO. BA- 19BA-016
AMOUNT:j $411,000.00
This budget amendment is requested to provide for the following:
To increase expenditure appropriations from the Balboa Village Parking Management unappropriated fund balance
and the Measure M Fair Share unappropriated fund balance for the Balboa Village Streetscapes Improvements
project.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Obiect
535 300000
122 300001
REVENUE ESTIMATES
Org Object Project
EXPENDITURE APPROPRIATIONS
Org Object Project
53501 980000 17R11
12201 980000 17R11
Description
BV Parking Mgmt - Fund Balance
Measure M - Fund Balance
Description
Description
BV Parking Mgmt - Balboa Village St
17R11 -Construct -535 -Unassigned
Measure M - Balbao Village St.
17R11 -Construct -122 -Unassigned
Signed: ( �, lr4
„( { Financial Approval: Finance Director
Signed:
Signed:
AdminKtrp(lve Approval: City Manager
City Council Approval: City Clerk
Amount
Debit Credit
$181,000.00
$230,000.00
. Automatic System
$181,000.00
$230,000.00
// - 7 - LA
Date
Date
Date
Increase in Budgetary Fund Balance
ANDX
Decrease in Budgetary Fund Balance
No effect on Budgetary Fund Balance
ONE-TIME?
F']
Yes
No
This budget amendment is requested to provide for the following:
To increase expenditure appropriations from the Balboa Village Parking Management unappropriated fund balance
and the Measure M Fair Share unappropriated fund balance for the Balboa Village Streetscapes Improvements
project.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Obiect
535 300000
122 300001
REVENUE ESTIMATES
Org Object Project
EXPENDITURE APPROPRIATIONS
Org Object Project
53501 980000 17R11
12201 980000 17R11
Description
BV Parking Mgmt - Fund Balance
Measure M - Fund Balance
Description
Description
BV Parking Mgmt - Balboa Village St
17R11 -Construct -535 -Unassigned
Measure M - Balbao Village St.
17R11 -Construct -122 -Unassigned
Signed: ( �, lr4
„( { Financial Approval: Finance Director
Signed:
Signed:
AdminKtrp(lve Approval: City Manager
City Council Approval: City Clerk
Amount
Debit Credit
$181,000.00
$230,000.00
. Automatic System
$181,000.00
$230,000.00
// - 7 - LA
Date
Date
Date