City Council Staff Report
March 26, 2019
Agenda Item No. 10
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Ben Davis, Associate Civil Engineer, bdavis@newportbeachca.gov
PHONE: 949-644-3317
TITLE: Spyglass Hill Reservoir Mixing System —Award of Contract No. 7428-
1 (19W15)
ABSTRACT:
Construction bids have been received for the Spyglass Hill Reservoir Mixing System
Project to improve water circulation and quality of potable water in the Spyglass Hill
Reservoir. Staff requests City Council's approval to award the construction contract to
Humphrey Constructors of Diamond Bar, California.
RECOMMENDATION:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15302(c) Class 2, (reconstruction of existing facility involving
negligible or no expansion of capacity) of the CEQA Guidelines, because this project
has no potential to have a significant effect on the environment;
b) Approve the project plans and specifications;
c) Award Contract No. 7428-1 to Humphrey Constructors, for the total bid amount of
$165,400.00, and authorize the Mayor and City Clerk to execute the contract;
d) Establish a contingency of $24,810.00 (approximately 15% of total bid) to cover the
cost of unforeseen work not included in the original contract; and
e) Approve Budget Amendment No. 19BA-032 transferring $92,000.00 from savings in
Utilities Yard Spill Control/Tipping Floor project (Account No. 70201932-980000-
18W14) to the Spyglass Hill Reservoir Mixing System project (Account No. 70201932-
980000-19W15).
FUNDING REQUIREMENTS:
Upon approval of the proposed budget amendment, sufficient funding will be available for
the award of this contract. The proposed budget amendment transfers $92,000.00 (Water
Fund) of savings from the Utilities Yard Spill Control/Tipping Floor project into this project,
thus avoiding any impact on the fund balance.
10-1
Spyglass Hill Reservoir Mixing System —Award of Contract No. 7428-1 (19W15)
March 26, 2019
Page 2
The following fund will be expensed:
Account Description Account Number Amount
Water Capital - NMP 70201932-980000-19W15 $ 192,000.00
Total: $ 192,000.00
Staff recommends establishing approximately fifteen (15) percent for contingency
purposes for unforeseen conditions associated with construction.
Proposed fund uses are as follows:
Vendor
Humphrey Constructors
Humphrey Constructors
Various
DISCUSSION:
Purpose
Construction Contract $
Construction Contingency $
Printing & Incidentals $
Total: $
Amount
165,400.00
24,810.00
1,790.00
192,000.00
The Spyglass Hill Reservoir Mixing System project will improve water circulation in the
below ground Spyglass Hill Reservoir. The reservoir is located underneath Spyglass Hill
Reservoir Park and holds approximately 1.5 million gallons of potable water.
The scope of work includes installing underground power and communication lines from
the reservoir to the control building, installing a new mixer control panel, and installing a
submersible mixer in the reservoir. The need for this project is to assist with maintaining
proper water quality as identified by the Utilities Department.
At 10 a.m. on March 5, 2019, the City Clerk opened and read the following electronic bids
for this project:
The City received multiple bids for this project and the low bid is approximately 10 percent
above the Engineer's Estimate of $150,000.00. The low bidder, Humphrey Constructors,
possesses a California State Contractor's License Classification "A" and the
subcontractor, Big Bear Electric, possesses a "C-10" License as required by the project
specifications. A check of the contractor's references indicates satisfactory completion
of similar projects for other public agencies.
Pursuant to the contract documents, the Contractor will have 30 consecutive working
days to complete the work.
10-2
BIDDER
TOTAL BID AMOUNT
Low
Humphrey Constructors
$
165,400.00
2nd
AToM Engineering Construction, Inc.
$
167,398.00
3rd
J.R. Filanc Construction
$
181,370.00
4th
RE Chaffee Construction
$
239,410.00
The City received multiple bids for this project and the low bid is approximately 10 percent
above the Engineer's Estimate of $150,000.00. The low bidder, Humphrey Constructors,
possesses a California State Contractor's License Classification "A" and the
subcontractor, Big Bear Electric, possesses a "C-10" License as required by the project
specifications. A check of the contractor's references indicates satisfactory completion
of similar projects for other public agencies.
Pursuant to the contract documents, the Contractor will have 30 consecutive working
days to complete the work.
10-2
Spyglass Hill Reservoir Mixing System — Award of Contract No. 7428-1 (19W 15)
March 26, 2019
Page 3
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(c) Class 2, (reconstruction
of existing facility involving negligible or no expansion of capacity) of the CEQA
Guidelines, because it has no potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
Attachment B — Budget Amendment
10-3
ATTACHMENT A
SPYGLASS HILL RESERVOIR CITY OF NEWPORT BEACH
MIXING SYSTEM PUBLIC WORKS DEPARTMENT
LOCATION MAP C-7428-1 19W15 3/26/19
10-4
City of Newport Beach
BUDGET AMENDMENT
2018-19
EFFECT ON BUDGETARY FUND BALANCE:
increase Revenue Estimates
Increase Expenditure Appropriations AND
jX Transfer Budget Appropriations
SOURCE:
x from existing budget appropriations
from additional estimated revenues
from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
ATTACHMENT B
NO. BA- 19BA-032
AMOUNT:j $92,000.00
To transfer expenditure appropriations from the Spill Control Valve I Tipping Floor project 18W14) to the Spyglass Hill Reservoir
Mixing System System project (19W15).
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund O_biect Description
REVENUE ESTIMATES
Org Obiect . Project Description
Debit
Amount
EXPENDITURE APPROPRIA TIONS
Org Object Proiect Description
70201932 980000 18W14 Water Cap - Spill Control Valve/ Tipping Floor $92,000.00
70201932 980000 19W15 Water Cap - Spyglass Hill Reservoir Mixing System
Signed:
Signed
FI
Finance Director
City Council Approval: City Clerk
. Automatic System
Credit
$92,000.00
3 -/7 -
Date
Date
10-5
Increase in Budgetary Fund Balance
Decrease in Budgetary Fund Balance
x
No effect on Budgetary Fund Balance
ONE-TIME? '
e
Yes
No
To transfer expenditure appropriations from the Spill Control Valve I Tipping Floor project 18W14) to the Spyglass Hill Reservoir
Mixing System System project (19W15).
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund O_biect Description
REVENUE ESTIMATES
Org Obiect . Project Description
Debit
Amount
EXPENDITURE APPROPRIA TIONS
Org Object Proiect Description
70201932 980000 18W14 Water Cap - Spill Control Valve/ Tipping Floor $92,000.00
70201932 980000 19W15 Water Cap - Spyglass Hill Reservoir Mixing System