Eligibility Checklist for Expedited
Solar Photovoltaic Permitting for
One- and Two -Family Dwellings
GENERAL REQUIREMENTS
A.
System size is 10 kW AC CEC rating or less
,PT'Y
❑ N
B.
The solar array is roof -mounted on one- or two-family dwelling or accessory structure
,g'Y
❑ N
C.
The solar panel/module arrays will not exceed the maximum legal building height
Y
❑ N
D.
Solar system is utility interactive and without battery storage
O'Y
❑ N
E.
Permit application is completed and attached
W'
❑ N
ELECTRICAL REQUIREMENTS
120/220 Vac with a bus bar rating of 225 A or less
A.
No more than four photovoltaic module strings are connected to each Maximum Power
Point Tracking (MPPT) input where source circuit fusing is included in the inverter
!?l❑ N
1) No more than two strings per MPPT input where source circuit fusing is not included
Y ❑ N
2) Fuses (if needed) are rated to the series fuse rating of the PV module
DAY ❑ N
3) No more than one non inverter -integrated DC combiner is utilized per inverter
ErY ❑ N
B.
For central inverter systems: No more than two inverters are utilized
0-Y ❑ N
C.
The PV system is interconnected to a single-phase AC service panel of nominal
120/220 Vac with a bus bar rating of 225 A or less
Z( 11N
D.
The PV system is connected to the load side of the utility distribution equipment
❑ N
E.
A Solar PV Standard Plan and supporting documentation is completed and attached
Y O N
STRUCTURAL REQUIREMENTS
A.
A completed Structural Criteria and supporting documentation is attached (if required)
!( Y ❑ N
FIRE SAFETY REQUIREMENTS
A.
Clear access pathways provided/1
13N
B.
Fire classification solar system is provided
rd Y ❑ N
C.
All required markings and labels are provided
RiY ❑ N
D.
A diagram of the roof layout of all panels, modules, clear access pathways and
approximate locations of electrical disconnecting means and roof access points
is completed and attached
/Y O N
Notes:
1. These criteria are intended for expedited solar permitting process.
2. If any items are checked NO, revise design to fit within Eligibility Checklist otherwise permit application
may go through standard process.
CITY OF NEWPORT BEACH
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING DIVISION
100 Civic Center Drive I P.O. Box 1768 1 Newport Beach, CA 92658-8915
www.newportbeachea.gov 1 (949) 644-3200
SOLAR CONTRACTOR DECLARATION
Keep with Inspection card.
This form is for the Inspector to take at time of final inspection
PART 1: To be completed BEFORE PERMIT' ISSUANCE
JOBSITE ADDRESS:
SU I �'Wvrs& ave-
CONTRACTOR
veCONTRACTOR NAME: CONTRACTOR STATE LICENSE #:
AiA-Gt,v,, So Ian 160r9 &3 c.- P F/
PANEL MAKE #: PANEL MODEL #:
�cz �-7 LG3-7o aiC —v5
I, �0 \ `p Ltd
`fA� N �1 �� declare that the PV module make and model
(PRIAT N )
number, quantity, and location are installed as per the approved plans. Module
manufacturer, make, model and number, fire classifications of modules, and
brackets match the improved plans for the project located at the above
within the ity port Beach.
I �n 1�°
rl�k
(DATE)
CITY OF NEWPORT BEACH
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING DIVISION
100 Civic Center Drive 1 P.O. Box 1768 1 Newport Beach, CA 92658-8915
www.newportbeachca.gov 1 (949) 644-3200
SMOKE DETECTOR AND CARBON MONOXIDE
SELF -CERTIFICATION
(this certification is to be filled out by the permittee or homeowner)
Project Address:
Permit Number:
Property Owner:
Licensed Contra
The State of California now requires that smoke and carbon monoxide detectors must be
installed in all residential buildings
California Residential Code (CRC) Section R314.1, CRC R315.2 states in part that
existing dwellings be "retrofitted with smoke detectors and carbon monoxide detectors.
CRC Section R314.3, CRC R315.3 defines required locations.
Both boxes below must be checked.
❑ Carbon Monoxide Alarm: On the ceiling or wall outside of each separate
sleeping area in the immediate vicinity of bedrooms or in each hallway outside of
the rooms, and each level of the dwelling. Detectors are also required in
bedrooms with gas fired appliances
K
Smoke Alarms: Installed in each room used for sleeping purposes, outside
h sleeping area, and on each level of the dwelling unit.
Retrofitted detectors may be battery operated for buildings where no alterations are
performed on the interior. Multiple -purpose alarms (carbon monoxide and smoke alarms)
shall comply with all applicable standards and must be approved by the State Fire
Marshall. The devices must be installed per manufacturer's specifications.
I, the undersigned, here ce t a e permittee or homeowner of the
project. I further cern that s ke alarms a d carbon monoxide alarms are
present and tes a unction 'n all the wing locations:
Signature: Date: 11 Olt
NOTE: This self-ce ifi n is only for projects to the exterior of the structure w ere access to the
interior of the dwellin b the City of Newport Beach Building Inspector is not achieved during the course of
construction.
Forms\SmokeDetectomndCarbonMonoxideSelfCert08/12/16