HomeMy WebLinkAbout07 - Police Station Gun Range Remodel — Award of Contract No. 7080-1 (19F12)Q �EwPpRT CITY OF O � z NEWPORT BEACH <,FORN'P City Council Staff Report February 25, 2020 Agenda Item No. 7 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Peter Tauscher, Senior Civil Engineer PHONE: 949-644-3316 TITLE: Police Station Gun Range Remodel — Award of Contract No. 7080-1 (19F12) Staff has received construction bids for the Police Station Gun Range Remodel project and requests City Council approval to award the construction contract to Optima RPM, Inc. This project will replace and update the existing indoor police firing range located at 870 Santa Barbara Drive. RECOMMENDATION: a) Find this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 (Existing Facilities) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because this project has no potential to have a significant effect on the environment; b) Approve the project drawings and specifications; c) Award Contract No. 7080-1 to Optima RPM, Inc. (Optima RPM) for the total bid price of $691,000.00, and authorize the Mayor and City Clerk to execute the contract; and d) Establish $70,000.00 (approximately 10 percent) contingency to cover the cost of unforeseen work not included in the original contract. FUNDING REQUIREMENTS: Sufficient funding is available in the Capital Improvement Program budget for the award of this contract. The following funds will be expensed: Account Description Account Number Amount Environmental Liability 16001-980000-19F12 $ 765,000.00 Total: $ 765,000.00 7-1 Police Station Gun Range Remodel — Award of Contract No. 7080-1 (19F12) February 25, 2020 Page 2 Proposed uses are as follows: \/Pnrinr Optima RPM, Inc. Optima RPM, Inc. Various Purpose Amount Construction Contract $ 691,000.00 Construction Contingency $ 70,000.00 Incidentals $ 4,000.00 Total: $ 765,000.00 Staff recommends establishing $70,000.00 (approximately 10 percent of total bid) for contingency purposes and unforeseen conditions associated with construction. BACKGROUND: The existing Police Department station was constructed in 1973. The building has received various updates through the years, including a significant interior remodel in 1985 and a remodel of several offices and rooms in 2018. This remodel effort focuses on a complete overhaul and upgrade of the indoor shooting range (Attachment A). Originally constructed in 1976, the current setup consists of a rubber backstop, four designated shooting lanes with target rails, a suspended acoustical ceiling system, overhead baffles and an HVAC system. DISCUSSION: Police Department staff met with Public Works in order to provide a suitable design and layout, increasing range safety, making more efficient use of space, and providing easier access for cleaning the bullet trap. The existing rubber trap and all hazardous waste will be removed. Five new vertical funnel -type bullet traps will be installed, which, when coupled with non -lead frangible ammunition, will provide for an easier to clean method of capture. A new HVAC system will improve ventilation and capture of airborne particles. New ceiling and wall plates will improve ballistic protection, and new acoustical panels will improve sound mitigation. Lastly, an automated turning target system and improved, energy-efficient LED lighting system will provide better training conditions for staff. On February 4, 2020, at 2:00 p.m. the City Clerk opened and read the following electronic bids for this project: 7-2 BIDDER TOTAL BID AMOUNT Low Optima RPM, Inc. $ 691,000.00 2nd Dalke & Sons Construction, Inc. $ 710,480.00 3rd The Stone Collector $ 732,000.00 4th Gilman Builders, Inc. $ 733,000.00 5th H2M Construction, Inc. $ 746,000.00 6th Thomco Construction, Inc. $ 766,425.00 7th Horizons Construction Company Int'I, Inc. $ 816,000.00 8th Mar'ani Builders, Inc. $ 899,000.00 9th Fast -Track Construction $ 932,830.00 10th MTM Builders, Inc. $ 937,000.00 11th RenewAge Energy Solutions, Inc. $ 1,307,000.00 7-2 Police Station Gun Range Remodel — Award of Contract No. 7080-1 (19F12) February 25, 2020 Page 3 After the bid opening, staff received a bid protest letter from the third lowest bidder (Attachment B), The Stone Collector, claiming that the low bidder's bid was non-responsive. The low bidder then submitted a response to the bid protest (Attachment C). Staff reviewed the low bidder's response and determined the low bidder complies with the bidding specifications for this project. Staff recommends the City Council declare Optima RPM as the lowest responsive bidder. The bid amount submitted by Optima RPM is 7.9% below the Engineer's Estimate of $750,000.00. Optima RPM possesses a valid California State General Building "B" Contractors License as required by the project specifications and has satisfactorily completed facility projects for the City and other local agencies. Pursuant to the contract specifications, Optima RPM is allotted 60 consecutive working days to complete the work. Liquidated damages in the amount of $1,000.00 per calendar day will be assessed in case of tardy completion. ENVIRONMENTAL REVIEW: Staff recommends the City Council find this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 (Existing Facilities) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because this project has no potential to have a significant effect on the environment. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Attachment A — Location Map Attachment B — The Stone Collector Bid Protest Letter Attachment C — Optima RPM, Inc. Response Letter 7-3 ATTACHMENT A NEWPORT BEACH POLICE DEPARTMENT REMODEL • _ •► 1 A_9 NOT TO SCALE CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C-7080-1 2/25/2020 ATTACHMENT B 70. The Stone Collector TO: City of Newport Beach Attn: Peter Tauscher DATE: 02/05/2020 PROJECT: Police Station Gun Range Remodel RE: Bid Protest The Stone Collector protest the above mentioned project against Optima RPM Inc. and Dalke & sons construction Inc. and request both bidders to be deemed unresponsive and to be disqualified based on the information below: 1- Optima RPM Inc. On page 17 of the submitted bid the license number listed as 761714 belongs to W &C Ingram Landscape not Optima RPM Inc. 2- Dalke & sons construction Inc. There is no title of the person signing on page 5 of the submitted bid. According to City of Newport Beach Instruction to Bidders item #13 states: All documents shall bear signatures and titles of persons authorized to sign on behalf of the bidder. M. Alsayed, Owner The Stone Collector 2220 Skyline Drive. Fullerton, CA 92831 1714-797-4610 1 malsayed@sbcglobal.net 7-5 ATTACHMENT C a pum Reengineering BPio/"ect Management February 6, 2020 Mr. Peter Tauscher City of Newport Beach Public Works Department ptauscher@neweportbeachca.gov RE: Police Station Gun Range Bid Date: 2/4/2020 Bid Protest Good afternoon Mr. Tauscher, 17945 Sky Park Circle, Suite D Irvine, CA 92614 O. 949.724.1399 1 F. 949.724.1851 We are in receipt of the bid protest submitted by The Stone Collector and offer the following; Our license number is 961714 as stated on pages 5 and 9 of our submitted bid proposal. The license number was inadvertently mistyped on page 17. In light of the above our bid stands firm and we look forward to the Board's approval and the commencement of the project. Thank you. Maykel Hanna Vice President 17945 Sky Park Circle, Suite D, Irvine, CA 92614 10. 949.724.1399 1 F. 949.724.1851 www.optimarpm.com 7-6