Loading...
HomeMy WebLinkAbout05 - Water Transmission Main Valve Replacement — NOC for C-7539-1 (18W12)Q �EwPpRT CITY OF O � z NEWPORT BEACH <,FORN'P City Council Staff Report April 28, 2020 Agenda Item No. 5 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Michael J. Sinacori, Assistant City Engineer, msinacori@newportbeachca.gov PHONE: 949-644-3342 TITLE: Water Transmission Main Valve Replacement — Notice of Completion for Contract No. 7539-1 (18W12) On May 28, 2019, City Council awarded Contract No. 7539-1 for the Water Transmission Main Valve Replacement project to T.E. Roberts, Inc. The work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project. On May 28, 2019, the City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302(c); b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release Faithful Performance Bond one year after acceptance by the City Council. FUNDING REQUIREMENTS: Funds for this construction contract were included within the approved Capital Improvement Program budget and were expended from the following accounts: Account Description Water Capital Distribution & Piping Account Number US .T.Z11d 70201931-980000-18W12 $ 822,898.66 Total: $ 822,898.66 5-1 DISCUSSION: Water Transmission Main Valve Replacement — Notice of Completion Contract No. 7539-1 (18W12) April 28, 2020 Page 2 Overall Contract Cost/Time Summary Awarded Final Cost at Contingency Actual % Due to % Due to Contract Amount Completion Allowance Contract Directed Unforeseen Change Change Change $749,933.00 $822,898.66 10% or less +9.7% 9.7% 0% Allowed Contract Time + 127 Actual Time -15 Approved Extensions (days) = Under (-) or Over (+) The Water Transmission Main Valve Replacement project (Contract No. 7539-1) replaced large diameter valves identified in the Water Master Plan. These were older deteriorated valves located on large diameter transmission mains (16 -inch, 18 -inch & 30 -inch) that were installed in the 1960's and used to isolate sections of the water system for maintenance and operations. This year's project replaced nine valves located on Eastbluff Drive and San Joaquin Hills Road. The contract specifically provided for the removal and disposal of existing 16 -inch, 18 -inch and 30 -inch water transmission main pipe and valves, demolition and disposal of existing valve vaults, construction of 16 -inch, 18 -inch and 30 -inch transmission main pipe and fittings and connections to the existing water system, pavement restoration, traffic control and other appurtenant work as required by the contract. The contracted work has now been completed to the satisfaction of the Public Works Department. A summary of the construction cost is as follows: Original bid amount: Actual Cost of Bid Items Constructed: Total Change Orders: Final Contract Cost: $749,933.00 $749,933.00 $72,965.66 $822,898.66 After award of this contract and during construction, staff determined that a deteriorated 12 -inch and 18 -inch valve also needed replacement at Eastbluff Drive and Mar Vista Drive, as well as a two-inch air/vac assembly on the existing 30 -inch water transmission main located at San Joaquin Hills Road just west of San Miguel Drive to accommodate the project. In addition, the proposed work on the valve and vault located on San Joaquin Hills Road adjacent to Avocado Avenue was deleted due to complications related to bypassing the water system and the ability to keep businesses in and around the Fashion Island loop in service. Staff now plans to maintain that structure in its current configuration to avoid those business impacts. One change order totaling $72,965.66 was approved as part of the project. The change order addressed costs for the abovementioned work including sawcutting, excavation and disposal, traffic control and costs for night work. Also included as part of this change order were costs for additional work efforts for the removal of the existing valve and vault located at San Joaquin Hills Road and Marguerite Avenue that included the replacement of two 8 -inch main line valves, and a 6 -inch hydrant valve. 5-2 Water Transmission Main Valve Replacement — Notice of Completion Contract No. 7539-1 (18W12) April 28, 2020 Page 3 With the completion of the project, the final contract cost is approximately 9.7 percent above the original bid amount. A summary of the project schedule is as follows: Estimated Start of Construction per Annual Baseline Schedule July 8, 2019 Actual Start of Construction Per Notice to Proceed August 14, 2019 Extended Contract Completion Date Inclusive of Extra Work February 20, 2020 Actual Substantial Construction Completion Date January 29, 2020 Public Works staff directed the contractor to stop work in September in order to minimize traffic disruptions related to school drop-off and pick-up times and to comply with the Utilities Department's no work order due to the high-water usage period. In addition, Metropolitan Water District was working on emergency water repairs for their system that were not completed until December. The contractor was unable to re -start work until January 2020, extending the contracted completion date to January 29, 2020 with the water transmission main valve improvements completed to the satisfaction of the Public Works Department. ENVIRONMENTAL REVIEW: On May 28, 2019, City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302(c) Class 2 (reconstruction of existing public facilities involving negligible or no expansion of capacity) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING - The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENT: Attachment A — Location Map 5-3