CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
May 12, 2020
Agenda Item No. 12
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer,
tsandefur@newportbeachca.gov
PHONE: 949-644-3321
TITLE: Community Room Audio -Visual Improvements — Award of Contract
No. 7817-1 (19F02)
ABSTRACT:
Staff received construction bids for the Community Room Audio -Visual Improvements
Project and requests City Council approval to award the construction contract to VMI,
Inc.
RECOMMENDATION:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15301 (a) (Interior or exterior alteration involving electrical
conveyances) of the CEQA Guidelines, because this project results in negligible or no
expansion of existing capacity;
b) Approve the project drawings and specifications;
c) Award Contract No. 7817-1 to VMI Inc. for the total base bid amount of $122,492.21,
and authorize the Mayor and City Clerk to execute the associated construction
contract;
d) Establish $12,250.00, (approximately 10 percent) contingency to cover unforeseen
conditions, extra work and/or material quantities; and
e) Approve Budget Amendment No. 20-045 appropriating $118,842.21 in increased
expenditures from unappropriated General Fund, PEG Fee Reserve fund balance to
Account No. 01201925-980000-19F02.
12-1
Community Room Audio -Visual Improvements — Award of Contract No. 7817-1 (19F02)
May 12, 2020
Page 2
FUNDING REQUIREMENTS:
Upon approval of the proposed budget amendment, sufficient funding is available within
the current Capital Improvement Program budget for the award of this contract. The
recommended Budget Amendment appropriates $118,842.21 of increased expenditures
from the General Fund, PEG Fee Reserve fund balance to Account No. 01201925-
980000-19F02. Public Education and Government (PEG) funds are designated for
projects that improve communication between the City and the public.
The following funds will be expensed:
Account Description Account Number
Facilities Maintenance Master Plan 01201925-980000-19F02 $
Proposed expenditures are as follows:
Vendor
VMI, Inc.
VMI, Inc.
Various
DISCUSSION:
Purpose
Construction Contract
Construction Contingency
Printing & Incidentals
Total:
Amount
136,742.21
$ 122,492.21
$ 12,250.00
$ 2,000.00
$ 136,742.21
The Civic Center Community Room hosts events, classes, forums, and serves as
overflow seating for City Council meetings. In the current environment, where we are
following social distancing requirements in response to the COVID-19 Pandemic, the
room provides the venue for public attendance and comment at City Council meetings.
The audio-visual (A/V) system currently consists of a roll down screen and a projector
mounted on the ceiling. The system suffers when the room is brightly lit or the sun
shines through the glass curtain wall and washes out the video screen. This project
replaces the video projection with a video wall consisting of nine linked video monitors
that create a single screen measuring approximately 165 -inches across.
The project also updates the control panels and boxes and provides for a power
supply backup to the server rack in the room.
At 10 a.m. on April 7, 2020, the City Clerk opened and read the following bids for this
project:
Bidder Total Bid Amount
Low VMI, Inc. $ 122,492.21
2nd Digital Networks Group $ 129,146.05
3rd EIDIM Group, Inc. dba EIDIM AV Technology $ 135,186.11
12-2
Community Room Audio -Visual Improvements — Award of Contract No. 7817-1 (19F02)
May 12, 2020
Page 3
The low bid amount is 18 percent below the Engineer's Estimate of $150,000. The low
bidder, VMI, Inc., possesses a California state contractor's license classification "C-7" as
required by the project specifications. The contractor is registered with the California
Department of Industrial Relations as required by California law to work and bid on public
contracts. A check of the contractor's references indicates satisfactory completion of
similar projects for other local public agencies.
The work necessary for the completion of this contract consists of installing a video wall
display and all related wiring and audio-visual equipment; installing structural mounting
system for installation of the video wall; and modifying the existing fabric panels for the
mounting of the video wall. The contract also includes the acquisition of any required
Building Permit and any plans required for the acquisition of the permit.
Pursuant to the Contract Specifications, the Contractor will have 15 consecutive working
days to complete the work.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (" CEQA") pursuant to Section 15301 (a) (Interior or exterior
alteration involving electrical conveyances) of the CEQA Guidelines, California Code of
Regulations, Title 14, Chapter 3, because the replacement or reconstruction of existing
structures and facilities will have substantially the same purpose and capacity as the
structure replaced.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Budget Amendment
12-3
City of Newport
Beach
BUDGET AMENDMENT
Department: Public Works
Requestor: Angela Crespi
0 CITY MANAGER'S APPROVAL ONLY
2 COUNCIL APPROVAL REQUIRED
ONE TIME: F] Yes E No
Approvals
ATTACHMENT A
BA#: 20-045
Prepared by: Walid Harding
Finance Director: Date
Citv Clerk: Date
EXPLANATION FOR REQUEST:
To increase expenditure appropriations to be used for an agreement with VMI Inc. for the Community Room 0 from existing budget appropriations
Audio Visual upgrade. El from additional estimated revenues
El from unappropriated fund balance
REVENUES
Fund # Or Object Project
012 01299 691010
Description
I Interfund Transfers - Transfer In General Fund
Increase or (Decrease) $
$118,842.21
Subtotal �$—
118,842.21
EXPENDITURES
Fund # Or Object
012 01201925980000
010 01099 991012
Project
119F02
Description Increase or (Decrease) $
:Facilities - CIP Expenditures For GL i....... .. $118,842.21
'General Fund Interfund Transfr -Transfer Out CIP Fund
+
--- -------
- ----
f
--------- - -- -----------i I - - -----
Subtotal $
237,684 42
FUND BALANCE
Fund # Object_ Description
---------
Increase or
(Decrease) $
1010jGeneral Fund
- PEG Reserve
t
$118,84221;!
----
...........
......
J
......... .............___. _._..._ __...._..--_--.___+---------
Subtotah$
(118,842.21)J
Fund Balance Change Required
12-4