Loading...
HomeMy WebLinkAbout09 - Bison Avenue, San Joaquin Hills Road and San Nicolas Drive Pavement Rehabilitation — NOCQ �EwPpRT CITY OF O � z NEWPORT BEACH <,FORN'P City Council Staff Report August 25, 2020 Agenda Item No. 9 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Andy Tran, Senior Civil Engineer, atran@newportbeachca.gov PHONE: 949-644-3315 TITLE: Bison Avenue, San Joaquin Hills Road and San Nicolas Drive Pavement Rehabilitation — Notice of Completion for Contract No. 7433-2 (19R21) On November 19, 2019, City Council awarded Contract No. 7433-2 for the Bison Avenue, San Joaquin Hills Road and San Nicolas Drive Pavement Rehabilitation project to R.J. Noble Company, Inc. The work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project; b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release the Faithful Performance Bond one year after acceptance by the City Council. FUNDING REQUIREMENTS: The adopted budget included sufficient funding for this contract. The construction contract was expensed from the following accounts within the budget: Account Description Measure M Fair Share SB 1 RMRA CalRecycle Grant Account Number 12201-980000-19R21 12601-980000-19R21 13501-980000-19R02 Amount $ 1,112,317.66 $ 1,414,600.00 $ 71,690.00 Total: $ 2,598,607.66 9-1 Bison Avenue, San Joaquin Hills Road and San Nicolas Drive Pavement Rehabilitation — Notice of Completion for Contract No. 7433-2 (19R21) August 25, 2020 Page 2 The City was also successful in obtaining grant funding to pay for a portion of the paving material under the CalRecycle Rubberized Pavement Grant Program (Program). This Program promotes the use of rubberized asphalt concrete made from recycled waste tires generated in California. The Program aims to decrease the adverse environmental impacts created by disposing and stockpiling waste tires. Through the Program, the City will be reimbursed $10/ton of rubberized asphalt concrete used on this project. The total amount of grant funding from this Program is $71,690.00 for this contract. DISCUSSION: Overall Contract Cost/Time Summary Awarded Final Cost at Contingency Actual % Due to % Due to Contract Amount Completion Allowance Contract Directed Unforeseen Change Change Change $2,681,325.00 $2,598,607.66 10% or less -3.1% -3.8% +0.7% Allowed Contract Time + 120 Actual Time +7 Approved Extensions (days) = Under (-) or Over (+) This project included mobilization, traffic control, survey monument restoration, utility coordination and verification, clearing and grubbing, removal of existing areas of failed roadway pavement, subgrade preparation, cold milling, grinding of existing asphalt pavement, construction of asphalt concrete pavement, asphalt rubberized hot mix pavement, concrete driveway approaches, concrete cross gutter, concrete curb ramps, concrete curb and gutters, concrete median curbs, minor landscaping and irrigation repairs, utility adjustments, traffic signage improvements, pavement striping and minor traffic signal improvements. The contracted work has now been completed to the satisfaction of the Public Works Department. A summary of the construction cost is as follows: Original Bid Amount: $ 2,681,325.00 Actual Cost of Bid Items Constructed: $ 2,493.381.57 Total Change Orders: $ 105,226.09 Final Contract Cost: $ 2,598,607.66 The final contract cost was $2,598,607.66, which was approximately 3.1 percent lower than the original bid amount. The project savings was primarily attributed to the field measured asphalt concrete quantities being lower than estimated. The change orders for the project included reconstruction of additional concrete sidewalk and curb and gutter to address damaged concrete along Bison Avenue and San Joaquin Hills Road. Additionally, staff identified traffic signal infrastructure within the project limits that needed to be replaced prior to completing the final pavement restoration. 9-2 Bison Avenue, San Joaquin Hills Road and San Nicolas Drive Pavement Rehabilitation — Notice of Completion for Contract No. 7433-2 (19R21) August 25, 2020 Page 3 A summary of the project schedule milestones is as follows: Estimated Start of Construction per Annual Baseline Schedule 1/6/2020 Actual Start of Construction Per Notice to Proceed 1/13/2020 Extended Contract Completion Date Inclusive of Extra Work 7/10/2020 Actual Substantial Construction Completion Date 7/17/2020 The concrete improvements and asphalt paving operation was completed on April 8, 2020. However, the contract time was extended to account for manufacturing delays for signal equipment caused by the COVID 19 pandemic. Upon receiving the parts in July, traffic signal modifications were completed in a timely and expeditious manner. ENVIRONMENTAL REVIEW: On November 19, 2019, the City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301(c), Class 1, (maintenance of existing public facilities involving negligible or no expansion of use), of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENT: Attachment A — Location Map 9-3 pli ATTACHMENT A Mom Ivry♦ bar` n LIMITS OF WORK IIIIIIIII�� ••••• ������ �••viiiii! iiiii iii�••••pp OHIO --- III, BISON AVE, SJHR AND SAN NICOLAS DR CITY OF NEWPORT BEACH PAVEMENT REHABILITATION PUBLIC WORKS DEPARTMENT LOCATION MAP C-7433-1 19R21 8/25/20 =I