HomeMy WebLinkAbout08_Annual Review of Uptown Newport Development Agreement_PA2014-039 CITY OF NEWPORT BEACH ZONING ADMINISTRATOR STAFF REPORT October 15, 2020 Agenda Item No. 8 SUBJECT: Annual Review of Uptown Newport Development Agreement (PA2014-039) ▪ Development Agreement No. DA2012-003 SITE LOCATION: 4311-4321 Jamboree Road APPLICANT/OWNER: Uptown Newport, LP (TSG-Parcel 1, LLC) PLANNER: Chelsea Crager, Associate Planner 949-644-3227, ccrager@newportbeachca.gov ZONING DISTRICT/GENERAL PLAN • General Plan: MU-H2 (Mixed-Use Horizontal 2) • Zoning District: PC 58 (Uptown Newport) PROJECT SUMMARY An annual review of Development Agreement No. DA2012-003 (DA) for Uptown Newport Planned Community, pursuant to Section 15.45.080 of the Newport Beach Municipal Code and Section 65865.1 of the California Government Code . RECOMMENDATION 1) Conduct a public hearing; 2) Find the annual review is exempt from the California Environmental Quality Act (“CEQA”) pursuant to Section 15321, Class 21 (Enforcement Actions by Regulatory Agencies) of the CEQA Guidelines, California Code of Regulations, Title 14, Division 6, Chapter 3, because it has no potential to have a significant effect on the environment; 3) Find that the applicant has demonstrated good faith compliance with the terms of Development Agreement No. DA2012-003; and 4) Receive and file the Annual Report of Development Agreement for Uptown Newport Planned Community (Attachment No. ZA 2). 1 Annual Review of Uptown Newport Development Agreement (PA2014-039) Zoning Administrator, October 15, 2020 Page 2 Tmplt: 01/12/18 BACKGROUND On March 12, 2013, the City Council adopted Ordinance No. 2013-6, approving the DA for the development of a 25-acre, mixed-use residential project consisting of 1,244 residential units, two 1-acre public parks, and 11,500 square feet of retail uses. The DA became effective on April 22, 2013. The term of the DA is 15 years, and has two 5-year extension options. The earliest expiration could be in 2028. On April 28, 2015, the City Council approved the First Amendment to the DA that delayed the timing of payment of public benefit fees and park in-lieu fees. The DA and its First Amendment are available online at: http://www.newportbeachca.gov/developmentagreements. On September 5, 2013, the Planning Commission approved Master Site Development Review (MSDR) No. SD2013-002 (PA2013-129) for the Uptown Newport project. The Planning Commission also approved prototypical architectural building elevations, master landscape plan and plant palette, preliminary public parks and paseo plans, preliminary master wall/fence plans, master signage plans, and preliminary site improvement plans for the entire 25-acre planned development. The purpose of this approval is to ensure that the project will be developed in a cohesive manner in phases consistent with the Planned Community Development Plan, Development Agreement, environmental mitigation measures required by the Environmental Impact Report (EIR), and applicable City codes and standards. On October 1, 2013, the Parks, Beaches & Recreation Commission reviewed and approved park amenities on the two public park concepts for the Uptown Newport project. On January 24, 2016, the Community Development Director approved Minor Site Development Review No. SD2015-004 (PA2015-141) for the construction of 455 residential apartment units in two separate buildings, approximately 10,700 square feet of retail use, and a 50-foot-wide paseo within Phase 1 proposed by the Picerne Group. The South Building was approved to provide 222 apartment units with approximately 10,700 square feet of commercial space on the ground floor. The North Building was approved to provide 233 units. A 50-foot-wide paseo will be developed on an easement area between the two buildings, and it will provide public access from Jamboree Road through to the internal street. These two buildings include 92 units for very-low income households. On September 2, 2016, the Community Development Director approved Staff Approval No. SA2016-010 (PA2016-125), an amendment to Condition of Approval No. 34 of Uptown Newport Tentative Tract Map No. NT2012 -002 (TTM No. 17763), to delay completion of the public sidewalk reconstruction along the Jamboree Road frontage of the Uptown Newport Planned Community until occupancy of the Picerne Group’s first residential building or July 31, 2018, whichever comes first. 2 Annual Review of Uptown Newport Development Agreement (PA2014-039) Zoning Administrator, October 15, 2020 Page 3 Tmplt: 01/12/18 On January 24, 2017, the City Council approved the issuance of up to $192,000,000 of multi-family housing bonds by the California Statewide Communities Development Authority (CSCDA) to finance the project. The City does not incur any liability for the CSCDA financing. On March 23, 2017, the Planning Commission approved Major Site Development Review No. SD2017-001 (PA2017-031), an amendment to the previously approved Master Site Development Review application, to allow alternative locations and phasing of the commercial component (up to 11,500 square feet). Specifically, the amendment allows Lot 3 (the Picerne Group’s South Building) to be developed without commercial uses while Lot 2, located at the intersection of Jamboree Road and Fairchild Road, to be developed with commercial uses rather than residential uses. The preliminary plans proposed an approximately 6,500 square feet o f retail use on Lot 2. Additional commercial uses will be developed on other lots within the Uptown Newport Planned Community. On March 24, 2017, the Community Development Director approved Minor Site Development Review No. SD2017-002 (PA2017-040), amending Minor Site Development Review No. SD2015-004, to eliminate the 10,700-square-foot commercial component and associated parking from the South Building. The area formerly planned for commercial use was permitted to be developed with seven additional residential units for a total of 229 units within the South Building. With the approval of the proposed amendment, a total of 462 apartment units would be developed, inclusive of the 92 low - income units. On April 11, 2017, the City Council approved park in-lieu fee credits consistent with the General Plan and Municipal Code. The park in-lieu fee payment for Phase 1 was set in the amount of $2,895,686.54. On July 13, 2018, the Community Development Director approved Minor Site Development Review No. SD2018-002 (PA2018-107) for the construction of Phase 1’s 1-acre neighborhood park. The park’s construction began late December 2018 and is nearly complete. At the last annual review on May 16, 2019, the Zoning Administrator found that Uptown Newport demonstrated good faith compliance with the terms of the DA and its First Amendment. DISCUSSION Section 15.45.080 of the Municipal Code requires the City to periodically review development agreements to determine if the applicant has complied with the terms of the agreement. This review should be conducted at least once every 12 months. 3 Annual Review of Uptown Newport Development Agreement (PA2014-039) Zoning Administrator, October 15, 2020 Page 4 Tmplt: 01/12/18 The applicant is required to demonstrate good faith compliance with the terms of the agreement, and should the Zoning Administrator find that the applicant has not complied in good faith with the terms of the agreement; the Zoning Administrator should refer the matter to City Council. Annual Review The annual review covers the period of May 2019 to September 2020. A summary of construction-related activities within Phase 1 performed by the property owner, its agents and affiliates during the past year are listed below: 1. Building permits for the construction of the Picerne Group’s (One Uptown Newport) apartment project in Phase 1 were issued on May 18, 2017. A total payment of $18,985,299, which includes a park fee of $2,895,687, was submitted consistent with the terms of the DA and its First Amendment. The South Building was completed in July 2019, and the North Building was completed in November 2019. Certificates of Occupancy were issued in December 2019. Due to the COVID-19 global pandemic, the affordable housing implementation process was temporarily delayed. The interest list for affordable housing selection was open from July 30 to August 31, 2020. The first occupancy of the affordable apartments is anticipated by the end of October 2020. It is anticipated that 46 affordable units will be leased by the end of 2020. 2. The DA provides a statement where the City and the landowner may cooperate in the undergrounding of the 66KV high voltage power line along Jamboree Road. A CFD (Community Facilities District) for the financing of the power line undergrounding was formed on March 12, 2019. The first phase, which included the installation of the underground vaults and ducts, was completed in December 2018. It is anticipated that the completion of the line extension will take place near the end of 2020 with removal of the power poles and line in early 2021. 3. Phase 1 site improvements, on-site and Jamboree Road median landscaping, on- site street lights, and traffic signal modifications at main entry, are completed. 4. Construction of the 1-acre park is substantially complete, with park signage remaining to be installed. This is expected to be completed by the end of 2020. 5. An EIR Addendum was prepared for the enclosure of the existing ammonia tank serving the TowerJazz Semiconductor operation. TowerJazz is currently located where future development of Phase 2 is to take place, which is to be implemented after 2027. The EIR Addendum was adopted in July 2020 and construction is anticipated to be completed in October 2020. 4 Annual Review of Uptown Newport Development Agreement (PA2014-039) Zoning Administrator, October 15, 2020 Page 5 Tmplt: 01/12/18 The applicant has prepared a report with a complete list of accomplishments within the past year (Attachment No. ZA 2). After reviewing the attached annual report and applicable documents, staff finds the applicant to be in good faith compliance with the terms and conditions of the DA and its First Amendment. As to the remaining construction of Phase 1 development, the applicant has expressed interests in two condominium residential developments for the remaining portion of Lot 1 (located to the east and north of Phase 1 Park). City approval has not been granted for either of the projects at this time. Lot 2 is anticipated to be developed with an upper scale restaurant and coffee shop; however, plans have been suspended due to the COVID -19 global pandemic. The following table identifies the Phase 1 residential development summary as to-date. Phase 1 Residential Development Implemented Remaining Total Number of Units: 680 458 222 Park Area: 1.03 acre 1.03 N/A The development of Phase 2 will be initiated after TowerJazz Semiconductor’s lease concludes either in 2022 or 2027. This phase consists of a 1-acre park, the remaining 564 residential units, and any remaining unbuilt commercial square footage from Phase 1. ENVIRONMENTAL REVIEW This annual review is exempt from the California Environmental Quality Act (“CEQA”) pursuant to Section 15321, Class 21 (Enforcement Actions by Regulatory Agencies) of the CEQA Guidelines, California Code of Regulations, Title 14, Division 6, Chapter 3, because it has no potential to have a significant effect on the environment. This section exempts actions by regulatory agencies to enforce or revoke a lease, permit, license, certificate, or other entitlement for use issued, adopted, or prescribed by the regulatory agency or enforcement of a law, general rule, standard, or objective, administered or adopted by the regulatory agency. PUBLIC NOTICE Notice of this review was published in the Daily Pilot, mailed to all owners of property within 300 feet of the boundaries of the site (excluding intervening rights -of-way and waterways), including the applicant, and posted on the subject property at least 10 days before the scheduled hearing, consistent with the provisions of the Municipal Code. 5 Annual Review of Uptown Newport Development Agreement (PA2014-039) Zoning Administrator, October 15, 2020 Page 6 Tmplt: 01/12/18 Additionally, the item appeared on the agenda for this meeting, which was posted at City Hall and on the City website. APPEAL PERIOD: An appeal or call for review may be filed with the Director of Community Development within 14 days following the date of action. For additional information on filing an appeal, contact the Planning Division at 949-644-3200. Prepared by: RU/cc Attachments: ZA 1 Vicinity Map ZA 2 Uptown Newport Development Agreement Annual Report 6 Attachment No. ZA 1 Vicinity Map 7 VICINITY MAP Annual Review of Uptown Newport Development Agreement No. DA2012-003 (PA2014-039) 4311-4321 Jamboree Road Subject Property 8 Attachment No. ZA 2 Uptown Newport Development Agreement Annual Report 9 September 30, 2020 Ms. Chelsea Crager City of Newport Beach Planning Department 100 Civic Center Drive Newport Beach, California 92660 RE: 2019 Annual Report for Uptown Newport Development Agreement No. DA2012-003 Dear Ms. Crager, This Annual Report for the Uptown Newport Development Agreement DA2012-003 (the “Agreement”) is being provided to the City pursuant to Section 7 of the Agreement, and is intended to satisfy the annual reporting requirement for Development Agreements under section 65865.1 of the Government Code. Uptown Newport is a mixed use development consisting of: 1,244 residential units, 11,500 square feet of retail uses, and two 1-acre public parks on approximately 25.05 acres of real property located at 4311-4321 Jamboree Road, Newport Beach, California. On March 23, 2013 (the “Agreement Date”), the City Council adopted Ordinance No. 2013-6 (the “Adopting Ordinance”), finding the Agreement to be consistent with the City of Newport Beach General Plan, and approving the Agreement. Because the Agreement was approved by Ordinance as required under Government Code section 65867.5, and no appeals or lawsuits challenging the validity of the Adopting Ordinance were filed, the Agreement became effective thirty days after the Agreement Date, or April 22, 2013. The Uptown Newport project is continuing with development of Phase I of the Uptown Newport Planned Community, with site development completed. The current plan for Phase I is to develop approximately 458 apartment units in two buildings on the Lots 3 and 4 that front along Jamboree Road; for-sale condominiums on Lot 1 that surrounds the Phase I Park, and; approximately 6,500 square foot of retail /commercial on Lot 2 at the Jamboree/Uptown Newport Drive entry. The number of for-sale units will be 30 units on the east half of lot 1 and approximately 66 units on the west half of lot 1. A Preliminary Development review plan was submitted to the city mid-year 2019 for Lot 1. Comments and recommendations provided by the city staff have been being addressed at the design level. The apartment buildings include approximately 92 affordable apartment units that will be incorporated into the same apartment buildings as the market rate apartments. 10 1. The first phase of the 66KV undergrounding on Jamboree Road fronting the Uptown Newport project was completed in December 2018. This included the installation of the underground vaults and ducts. Due to some local effects of a power shutdown on adjacent properties, we have been working with the city staff and SCE to find alternate solutions to avoid or minimize power interruptions. With the collaborative efforts of SCE and the city engineering staff we have arrived at a solution that will be beneficial to the affected business where-in, a power shutdown can be avoided with an extension of the line undergrounding. It is anticipated that the completion of the line extension will take place the near the end of 2020 with the removal of the power poles and line later in early 2021. 2. Construction of the two apartment buildings began May 2017. The two building were completed in July 2019 (south building) and November 2019 (north building). Certificates of occupancy was issued in December 2019. 3. Phase I site improvements are completed. The project landscape is complete. The city has since accepted the Jamboree median. 4. Construction of the 1 acre public park is substantially complete with the park signage remaining to be installed. This will be completed in the next 45-60 days. 5. Plans are currently in design to construct five condominium buildings on a portion of lot 1. City review is anticipated to be completed by October 2020 with permits issued late 2020 early 2021. 6. Plans were in design to construct two commercial/retail buildings on Lot 2. It is anticipated that the site will include an upper scale restaurant and a boutique coffee shop. Plans to construct have been temporarily suspended due to the Covid-19 Pandemic 7. The ammonia tank relocation on Tower Jazz site has taken a slightly different direction. While being a condition of the project mitigations measures to relocate the ammonia tank, new discussions with city staff and city fire department have found an alternate way to satisfy the condition by enclosing the existing ammonia tank facility. This revision will be processed as an EIR addendum and will meet the mitigation requirements. This is anticipated to be completed by October 2020. 11 8. One Uptown Affordable Leasing Plan: In mid-August, the ”Notice of Intent to Lease Affordable Units” was sent to the City of Newport Beach, providing for a list of affordable apartments and their respective rent limits in accordance with the regulatory agreement. The Interest List for affordable housing at One Uptown Newport was opened on July 30, 2020 and closed on August 31, 2020. Over 700+ multi-city subscribers joined the interest list. The Picerne Group has engaged Affordable Housing Consultants, LLC. (AHC) to initiate the qualifying and leasing process. Currently, AHS is contacting the interest list applicants and conducting the tenant file screening process. We anticipate the first Occupancy of the affordable apartments to be by month-end in October, and we will lease and occupy the 46 affordable units in the South building by the end of 2020. TSG-Parcel 1, LLC, as the Assignee of Uptown Newport, LP, and has complied in good faith with the terms and conditions of the Agreement. We look forward to continuing our development efforts for Uptown Newport, and appreciate the City’s cooperation in our efforts. Please contact me at (949) 417-1867 or at brupp@shopoff.com. Should you have any questions or require additional information. Sincerely, Brian Rupp Executive Vice President – Development Cc: Gregory Powers, Jackson Tidus 12