HomeMy WebLinkAbout11 - Corporation Yard Re -Roofing Project — Award of Contract No. 7880-1Q �EwPpRT CITY OF O � z NEWPORT BEACH <,FORN'P City Council Staff Report November 24, 2020 Agenda Item No. 11 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Tom Sandefur, Assistant City Engineer, tsandefur@newportbeachca.gov PHONE: 949-644-3321 TITLE: Corporation Yard Re -Roofing Project — Award of Contract No. 7880-1 ABSTRACT: The City has a Facilities Maintenance Master Plan (FMMP) to address major capital maintenance needs for various City buildings and facilities. In association with this plan, several building roofs at the City's Corporation Yard were inspected and scheduled for replacement. Staff has received bids for the Corporation Yard Re -Roofing Project and is requesting City Council approval to award the work to Chapman Coast Roof Co., Inc. (Chapman) of Fullerton, CA. RECOMMENDATION: a) Determine this action is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301—Class 1 (rehabilitation of deteriorated facilities) of the CEQA Guidelines, because this action results in no expansion of an existing use; b) Approve the project drawings and specifications; c) Award Contract No. 7880-1 to Chapman for the total bid price of $521,328, and authorize the Mayor and City Clerk to execute the contract; and d) Establish a contingency amount of $53,000 (approximately 10 percent) to cover the cost of unforeseen work not included in the original contract. FUNDING REQUIREMENTS: Sufficient funding is available in the Capital Improvement Program budget for the award of this contract. Funds will be expensed from the Facilities Maintenance Master Plan Account (57101-980000-21F02). Corporation Yard Re -Roofing Project — Award of Contract No. 7880-1 November 24, 2020 Page 2 Proposed fund uses are as follows: Vendor Purpose Amount Chapman Construction Contract $ 521,328 Chapman Construction Contingency $ 53,000 Various Printing and Incidentals $ 5,672 Total: $ 580,000 DISCUSSION: As part of the Facilities Maintenance Master Plan (FMMP), the City's Corporation Yard roofs were inspected. Buildings A, B, C, D and H had roofs identified as needing replacement. Buildings C and D roofs were replaced during a previous project, completed in July 2020. Staff developed the necessary plans to replace the roofs of Buildings A, B, and H and put the project out for public bids. At 10 a.m. on October 14, 2020, the City Clerk opened and read the following bids for this project: The City received eight bids for this project. The base bid amount submitted by the low bidder, Chapman, is approximately 1.8 percent more than the Engineer's Estimate of $512,000. This increase may be accounted for in Addendum No. 1 where the demolition of the Building A roof was switched to Saturday work to minimize the disruption to the City staff working in that building. Chapman possesses a valid and current California State Contractor's License C-39 (Roofing Contractor), as required by the Contract Documents. A check of the Contractor's references indicates satisfactory completion of similar projects for public agencies. The work necessary for the completion of this contract consists of removing existing roof systems, installing new built-up roof systems and replacing vents, scuppers and skylights on Buildings A, B and H at the Corporation Yard located at 592 Superior Avenue. Pursuant to the Contract Documents, the Contractor will have 80 consecutive working days to complete the work. 11-2 Bidder Total Bid Amount LOW Chapman Coast Roof, Inc. $ 521,328 2nd Best Contracting Services, Inc. $ 594,500 3rd ERC Roofing $ 603,229 4th Exbon Development, Inc. $ 617,000 5th Letner Roofing $ 631,097 6th San Marino Roof Co., Inc. $ 644,000 7th Rite -Way Roof Corporation $ 704,880 8th C. I. Services, Inc. $ 720,888 The City received eight bids for this project. The base bid amount submitted by the low bidder, Chapman, is approximately 1.8 percent more than the Engineer's Estimate of $512,000. This increase may be accounted for in Addendum No. 1 where the demolition of the Building A roof was switched to Saturday work to minimize the disruption to the City staff working in that building. Chapman possesses a valid and current California State Contractor's License C-39 (Roofing Contractor), as required by the Contract Documents. A check of the Contractor's references indicates satisfactory completion of similar projects for public agencies. The work necessary for the completion of this contract consists of removing existing roof systems, installing new built-up roof systems and replacing vents, scuppers and skylights on Buildings A, B and H at the Corporation Yard located at 592 Superior Avenue. Pursuant to the Contract Documents, the Contractor will have 80 consecutive working days to complete the work. 11-2 Corporation Yard Re -Roofing Project — Award of Contract No. 7880-1 November 24, 2020 Page 3 The project drawings and specifications will be available upon request at the City Council meeting. ENVIRONMENTAL REVIEW: Staff recommends the City Council find this action is not subject to the California Environmental Quality Act (CEQA) pursuant to Sections 15301 —Class 1 (rehabilitation of deteriorated facilities) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no expansion of an existing use. z[9)t1INIkiLes The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Attachment A — Location Map Attachment B — Building Roofs to be Replaced 11-3 CITY OF COSTA MESA PROJECT LOCATIONS ATTACHMENT A JOHN WAYNE AIRPORT pAC/FSC Cpl\ f VICINITY MAP NOT TO SCALE CORPORATION YARD RE -ROOFING PROJECT LOCATION MAP O,p Cl TY OF IRVINE P� IJNNERSI f Y 13 CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C-7880-1 1 11/24/20 16TH ST WEST ATTACHMENT B DOES TO E REPLACED CITY OF COSTA MESA / CORPORATION YARD (592 SUPERIOR AVE) O CORPORATION YARD RE -ROOFING PROJECT BUILDING 'A', 'B' AND 'H' N 0 NOT TO SCALE CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C-7880-1 1 11/24/20