NOTICE OF INCOMPLETE FILING
March 12, 2020
John Tseheridis
Bechtel Infrastructure and Power
16808 Armstrong Avenue, Suite 225
Irvine, CA 92606
jtseheri@bechtel.com
Application No. Minor Use Permit No. UP2019-037 (PA2019-128)
Address Public right-of-way adjacent to 690 [CS] Newport Center Drive
(SLC5637)
Please be advised that after reviewing the subject application, your resubmittal has been
deemed incomplete and further information is required before we are able to proceed with
the application process.
The following documentation is required to complete the application:
1. Agreement.
a. Please note, a bond is required prior to construction.
b. Please note, a master license agreement amendment is required prior to
construction in order to identify the specific site locations approved under
the agreement.
c. Please note, an encroachment permit is required prior to construction.
2. SCE Letter. Provide a letter from Southern California Edison authorizing the power
supply for this site location. Provide the SCE power location and approved
drawings from SCE as well. Please refer to the attached City issued Meter
Pedestal Denial Letter needed.
3. Project Plans. See the attached comments and plans from Public Works, Utilities,
and Real Property for redlined comments. Please provide one full size (24” by 36”)
set of plans and four reduced (11” x 17”) sets of plans that are revised to reflect
the requested information.
4. Traffic Control Plan.
a. Traffic Control Plans shall be signed by a registered engineer.
b. Provide tentative schedule; 30 days for streetlight replacement is
excessive.
c. Please revise Traffic Control Plan per redlines.
\\cnb.lcl\data\Users\PLN\Shared\PA's\PAs - 2019\PA2019-128\PA2019-128 Incomplete
Ltr_03122020.docx
Page 2
5. Electronic copy. All of the above submittal items are required to be submitted in
electronic format (i.e., CD-ROM or PDF via email).
Upon verification of completion, the application will be processed and scheduled for a
Zoning Administrator Hearing. Should you have any questions regarding submittal
requirements, please contact me at 949-644-3253 or bzdeba@newportbeachca.gov.
Benjamin M. Zdeba, AICP
Senior Planner
Attachments:
Meter Pedestal Denial Letter
Comments and redline plan sets
c:
City of Newport Beach
Lauren Wooding, Real Property Administrator
Community Development Department
100 Civic Center Drive, Bay 1D
Newport Beach, CA 92660
lwooding@newportbeachca.gov
Stacey Brown, Project Manager
ATT mobility
1452 Edinger Avenue
Tustin, CA 92780
Sb676b@att.com
F:\Users\PLN\Shared\Staff_Dir\Nova\Project Files\Telecom\Meter Pedestal Denial Letters\Batch 3\Meter
Pedestal Denial Letter-NO SLC5637.docx
Tmplt. 02/09/11
COMMUNITY DEVELOPMENT DEPARTMENT
PLANNING DIVISION
100 Civic Center Drive, P.O. Box 1768, Newport Beach, CA 92658-8915
949-644-3200 Fax: 949-644-3229
www.newportbeachca.gov
May 1, 2019
John Tseheridis
Bechtel Infrastructure & Power Corporation
16808 Armstrong Ave., Suite 225
Irvine, CA 92606
RE: WIRELESS FACILITIES IN THE PUBLIC RIGHT-OF-WAY
Address Public right-of-way adjacent to 690 (CS) Newport Center Drive
(Pole ID SLC5637)
Dear Mr. Tseheridis,
The City of Newport Beach has been notified that AT&T plans to submit applications for
small cell equipment at several SCE utility poles within the City’s public right-of-way as
noted above. The City of Newport Beach must always be mindful of preserving the
attractive aesthetic our City boasts.
As part of our review, we wanted to let you know that the City of Newport Beach will not
permit an above-grade meter pedestal, meter socket, or AC panel to be installed as part
of the Small Cell deployment AT&T, or any other company, is proposing. The City will
require a minimization of impacts for aesthetic and public right-of-way access reasons as
follows:
1. Section 20.49.050 (General Development and Design Standards), Subsection
F(6)(b) (Support Equipment, Installations in a Public Right-of-Way) requires
support equipment to be placed or mounted in the least visually obtrusive location
practicable. This section states that support equipment in the right-of-way shall be
placed underground if required by other provisions of the Municipal Code in flush -
to-grade underground vault enclosures, including flush-to-grade vents, or vents
that extend no more than twenty-four inches above the finished grade and are
screened from public view.
2. Section 13.20.030 (City Policies Regarding Use of the PROW), Subsection B
(Limits on Above-Ground Facilities) limits the number and controls the location of
above ground facilities used in conjunction with underground facilities consistent
with the technical requirements for providing high quality utility service. Companies
shall place all newly installed facilities underground or flush mounted vaults,
whenever feasible. Companies shall coordinate with all affected property owners
F:\Users\PLN\Shared\Staff_Dir\Nova\Project Files\Telecom\Meter Pedestal Denial Letters\Batch
3\Meter Pedestal Denial Letter-NO SLC5637.docx
Page 2
to locate all newly installed AGF to minimize inconvenience and disruption to
residents.
Please note, issuance of this letter does not guarantee automatic approval of the
antennas as proposed.
Thank you for your consideration. Please contact me at 949-644-3249 or
mnova@newportbeachca.gov with any questions.
Sincerely,
Cc:
David Keely, Senior Civil Engineer, Public Works
Lauren Wooding, Real Property Administrator, Community Development