<,FORN'P City Council Staff Report
February 23, 2021
Agenda Item No. 9
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Andy Tran, Senior Civil Engineer, atran@newportbeachca.gov
PHONE: 949-644-3315
TITLE: Cameo Highlands Street Reconstruction — Notice of Completion for
Contract No. 7067-2 (20R21)
ABSTRACT:
On May 26, 2020, the City Council awarded Contract No. 7067-2 for the Cameo Highlands
Street Reconstruction project to All American Asphalt. The work is now complete and staff
requests that the City Council accept and close out the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
FUNDING REQUIREMENTS:
Funds for the construction contract were expended from the following accounts:
Account Description
Account Number
Amount
SB1-RMRA
12601-980000-20R21
$
1,500,000.00
Gas Tax
12101-980000-20R21
$
738,970.51
Water Enterprise
70101-980000-20R09
$
1,449.70
Water Capital
70201-980000-20R09
$
44,260.30
Wastewater Enterprise
71101-980000-20R09
$
36,755.00
Total: $
2,321,435.51
9-1
DISCUSSION:
Cameo Highlands Street Reconstruction - Notice of Completion for
Contract No. 7067-2 (20R21)
February 23, 2021
Page 2
Overall Contract Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$2,425,694.00
$2,321,435.51
10% or less
-4.3%
-6.1%
+1.8%
Allowed Contract Time +
90
Actual Time
12
Approved Extensions (days) =
Under (-) or Over (+)
This project included mobilization, traffic control, survey monument restoration, utility
coordination and verification, removal of existing asphalt concrete (AC) street pavement,
subgrade preparation, construction of new AC street pavement, removal and
reconstruction of deteriorated concrete curb ramps, curbs and gutters, sidewalks, cross
gutters and driveway approaches, minor landscaping and irrigation repairs, utility
adjustments, traffic signage improvements, and pavement striping.
The contracted work has now been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original Bid Amount: $ 2,425,694.00
Actual Cost of Bid Items Constructed: $ 1,297,604.36
Total Change Orders: $ 1,023,831.15
Final Contract Cost: $ 2,321,435.51
The final contract cost was $2,321,435.51, which was approximately 4.3 percent lower
than the original bid amount. This cost decrease was primarily due to a field change in
which the structural pavement section was revised to a full -depth AC section, in lieu of
using geotextile fabric and base material. Revising the pavement section design to
full -depth AC allowed for an overall decrease in pavement thickness, while still providing
the same service life as the original design. Additionally, the full -depth AC section
shortened the construction duration and provided cost savings by eliminating the use of
geotextile fabric and base material as originally proposed.
There were seven contract change orders approved for the project. These change orders
were primarily due to the revised design for the structural pavement section, which
included increased asphalt concrete quantities and the deletion of geotextile fabric and
base material. Overall, a project cost savings was realized as a result of the change
orders.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule
07/06/2020
Actual Start of Construction Per Notice to Proceed
07/27/2020
Extended Contract Completion Date Inclusive of Extra Work
12/03/2020
Actual Substantial Construction Completion Date
11/13/2020
9-2
Cameo Highlands Street Reconstruction - Notice of Completion for
Contract No. 7067-2 (20R21)
February 23, 2021
Page 3
This project was substantially completed ahead of schedule and the contractor was able
to shorten the construction duration, primarily due to the revised, full -depth AC pavement
section design.
ENVIRONMENTAL REVIEW:
On May 26, 2020, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301(b)(c), Class 1,
(maintenance of existing public facilities involving negligible or no expansion of use), of
the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has
no potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT: