HomeMy WebLinkAbout20210319_Incomplete Letter_4Tmplt. 02/09/11
COMMUNITY DEVELOPMENT DEPARTMENT
PLANNING DIVISION
100 Civic Center Drive, P.O. Box 1768, Newport Beach, CA 92658-8915
949-644-3200 Fax: 949-644-3229
www.newportbeachca.gov
NOTICE OF INCOMPLETE FILING
VIA EMAIL
March 19, 2021
Magellan Architecture
Attn: Eileen Wade
eileen@magellanarchitects.com
Application No. Staff Approval No. SA2020-006 (PA2020-328)
Address 320 Marine Avenue, Unit B
Dear Eileen Wade:
Please be advised that after reviewing the subject application, your submittal has been
deemed incomplete and further information is required before we are able to proceed
with the application process:
1. Existing residential floor plan provided shows conditions that are not code
compliant with current or previous building codes. Please address. If this is a
drafting error, please remove residential plans from the plan set as the proposed
work does not involve this area. If there are changes proposed to the residential
portions, please prepare plans as such for review.
Please review the conditions of approval from Building, Life Safety Services and Public
Works:
Building Division – Tonee Thai, Principal Civil Engineer, 949-718-1867,
tthai@newportbeachca.gov
a. Final washout area design shall ensure that site storm drainage will not be
directed to the washout area drain that is connected to the sewer system.
b. Final design of trash enclosure exterior wall adjacent to the side property line
shall be fire rated construction with no openings per CBC Table 602 & Table
705.8 and not attached to adjacent site wall located on other property.
c. Comply with disable access requirements.
Life Safety Services – Kevin Bass, Fire Marshall, 949-644-3108,
kbass@newportbeachca.gov
a. CFC 304.3.3 and 304.3.4 – trash enclosures within the building or within 5
feet of the building shall be protected with sprinklers.
2. Public Works – David Keely, Senior Civil Engineer, 949-644-3349
dkeely@newportbeachca.gov
a. See attached.
«HearingDATE»
I:\Users\PLN\Shared\PA's\PAs - 2020\PA2020-328\PA2020-328_Incomplete Letter_2.docx
Page 2
3. Electronic Copy. Please provide an electronic copy of the above revised and
requested materials on a CD-ROM upon resubmission.
Upon verification of completion, the application will be processed as a Staff Approval.
Should you have any questions regarding submittal requirements, please contact Patrick
Achis at 949-644-3237 or pachis@newportbeachca.gov.
By:
Attachments: Public Works Conditions of Approval
December 17, 2020
City of Newport Beach PUBLIC WORKS DEPARTMENT
TO: PLANNING DEPARTMENT
FROM: David Keely Senior Civil Engineer
SUBJECT: FINDINGS AND CONDITIONS OF APPROVAL FOR STAFF APPROVAL NO. SA2020-006 (PA2020-328) 320 MARINE AVENUE
CONDITIONS:
1.All improvements shall be constructed as required by Ordinance and the PublicWorks Department.
2.Each unit shall be served by its individual water meter and sewer lateral and
cleanout. Each water meter and sewer cleanout shall be installed with a traffic
grade box and cover.
3.No above ground improvements are permitted within the 5-foot alley setbackarea.
4.An encroachment permit is required for all work activities within the public right
of-way.
5.In case of damage done to public improvements surrounding the developmentsite by the private construction, additional reconstruction within the public rightof-way could be required at the discretion of the Public Works Inspector.