HomeMy WebLinkAboutPRR_PW_2Please Distribute to:
(-, (~
p·ROJECT REVIEW REQUEST
COMMUNITY DEVELOPMENT DEPARTMENT
Planning Division
Public Works -Brine/Keely/Almendralo/Cooke
Date: 5-23-2019
Please return PRR and Plans to Staff Planner
Liane Schuller, Consultant Planner
949-644-3200, lschuller@newportbeachca.gov
Applicant: TSG-Parcel 1, LLC Contact: Tom Bitney, John Santry
949-417 -1396
Project Name Uptown Newport NP
Address: 4311 Uptown Newport Drive
(PA2019-067) NP2019-003
Tentative Parcel Map to subdivide 2.06 ac parcel into two parcels for conveyance purposes
(Resubmittal)
REPORT REQUESTED BY: June 7, 2019
Check all that apply: Notes:
□ No comments on the project
as presented.
□ Application of Standard Code
requirements are not
expected to alter the project
design. ~ Recommended conditions of
approval are attached.
□ Application of Standard Code
requirements or the attached
conditions of approval will
substantially impact or alter
the design of the project.
□ I contacted the applicant on
□ To schedule an appt. for ~/ ~/1/;1 Code review ~ □ To discuss the following
(see notes) Signature Ext. Date
Please indicate the approximate time spent on reviewing this project: II~_;'
Tm pit: 10/10/12
June 7, 2019
TO: Planning
FROM: David Keely
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
Senior Civil Engineer
SUBJECT: FINDINGS AND CONDITIONS OF APPROVAL FOR
TENTATIVE PARCEL MAP NO. NP2019-003 (PA2019-067)
4311 UPTOWN NEWPORT DRIVE
FINDINGS:
1. That the design of the development will not conflict with any easements acquired
by the public at large for access through or use of property within the proposed
development.
2. That public improvements will be required of the Applicant per the Municipal
Code and the Subdivision Map Act.
CONDITIONS:
1. A parcel Map shall be recorded. The Map shall be prepared on the California
coordinate system (NAD83). Prior to recordation of the Map, the
surveyor/engineer preparing the Map shall submit to the County Surveyor and
the City of Newport Beach a digital-graphic file of said map in a manner
described in Section 7-9-330 and 7-9-337 of the Orange County Subdivision
Code and Orange County Subdivision Manual, Subarticle 18. The Map to be
submitted to the City of Newport Beach shall comply with the City's CADD
Standards. Scanned images will not be accepted.
2. Prior to recordation of the parcel map, the surveyor/engineer preparing the map
shall tie the boundary of the map into the Horizontal Control System established
by the County Surveyor in a manner described in Section s 7-9-330 and 7-9-337
of the Orange County Subdivision Code and Orange County Subdivision Manual,
Subarticle 18. Monuments (one inch iron pipe with tag) shall be set On Each Lot
Corner unless otherwise approved by the Subdivision Engineer. Monuments
shall be protected in place if installed prior to completion of construction project.
3. The existing cul-de-sac configuration of Capitan Court shall be maintained until
such time the Phase 2 roadway configuration is complete.