HomeMy WebLinkAboutB9906933 - Soils13 r4
FEB 2 3 2002
LAWGIBB
GROUP
FINAL REPORT
GEOTECHNICAL INSPECTION SERVICES
EAST PARKING STRUCTURE
HOAG MEMORIAL HOSPITAL PRESBYTERIAN
301 NEWPORT BOULEVARD
NEWPORT BEACH, CALIFORNIA
Prepared for:
HOAG MEMORIAL HOSPITAL PRESBYTERIAN
Newport Beach, California
February 22,2002
Project 70144-0-0057
LAW Crandall
LAWGIBB Group Member A
February 22, 2002
Mr. James Easley, Project Manager
Facilities Design and Construction
Hoag Memorial Hospital Presbyterian
One Hoag Drive/P.O. Box 6100
Newport Beach, California 92658-6100
Subject:
Final Report of Geotechnical Inspection Services
East Parking Structure
Hoag Memorial Hospital Presbyterian
301 Newport Boulevard
Newport Beach, California
Hoag Project No. 1253.08
Law/Crandall Project 70144-0-0057
Dear Mr. Easley:
SUMMARY
We have completed geotechnical inspection services at the site of the subject project. This final
report provides:
• Verification of our observation and approval of the shoring installation at
the subject site.
• A formal record of our observation and testing of the compacted fill placed
to grade the site.
• Confirmation of our observation and approval of the foundation
excavations.
• A formal record of our observation and testing of the compacted asphalt
paving placed in areas to be paved.
The observation work was performed between June 23, 2000 and February 14, 2002. The location of
the site is shown in relation to adjacent streets on the attached Plot Plan. We performed a
geotechnical investigation of the site and submitted our recommendations in a report dated
September 10, 1999 (our Job No. 70131-9-0330.0002).
A Division of LAW Engineering and Environmental Services. Inc.
200 Citadel Drive • Los Angeles, CA 90040-1554
323-889-5300 • Fax: 323-721-6700
Hoag Memorial Hospital Presbyterian - Geotechnical Inspection Services Febniaiy 22, 2002
Law/Crandall Project 70144-0-0057
This final report is limited to the earthwork performed through February 14, 2002, the date of our last
observation and/or testing of the soil -related and asphalt paving work for the project. Based on our
observations, we are satisfied that the shoring system was installed in general accordance with the
shoring plans and project requirements. The fill and asphalt paving, at the locations and elevations we
tested, were compacted to at least the specified degree of compaction. Also, the foundation
excavations extended into satisfactory soils.
Our professional services have been performed using that degree of care and skill ordinarily
exercised, under similar circumstances, by reputable geotechnical engineers practicing in this or
similar localities. No other warranty, expressed or implied, is made as to the professional opinions
included in this report. The scope of our services did not include surveying or the responsibility for
job safety. The soil -related and asphalt paving work was performed to the limits and at the locations
indicated by stakes and hubs set by others.
4'
OBSERVATION OF SHORING
Prior to mass excavation to the lower building level, shoring was installed around the perimeter of the
site where there was not sufficient space for sloped embankments. The shoring consisted of soldier
piles tied back with friction anchors. The soldier piles were installed at the design locations indicated
on shoring drawing prepared by Cefali and Associates, Inc. Our field technician observed the drilling
of the soldier pile excavations to verify that the soils were consistent with those encountered during
our previous investigation of the site. He also measured the soldier pile shafts to confirm that they
were excavated to at least design dimensions.
INSTALLATION OF TIE -BACK ANCHORS
After installation of the soldier piles and excavation to the first bench, the tie -back anchors were
installed at the design locations and elevations indicated on the shoring plan. The shafts for the tie-
back anchors were observed for soil conditions and excavation to design dimensions.
Hoag Memorial Hospital Presbyterian - Geotechnical Inspection Services February 22, 2002
Lax; Crandall Project 70144-0-0057
ANCHOR TESTING
Following installation of the tie -back anchors and curing of the concrete, each anchor was tested to
150% or to 200% of the design load, in accordance with the project plans. Selected anchors were
tested to 200% to meet the criteria for 30-minute and 24-hour anchor load testing. After testing and
approval, each anchor was locked -off near the design load and mass excavation continued until the
final excavation level for parking structure construction was reached. The data for the soldier pile and
anchor installation and subsequent anchor testing are retained in our files should further reference be
required.
OBSERVATION AND TESTING OF COMPACTED FILL
This section describes our observation and testing of compacted fill placed as part of the project
earthwork.
LOCATIONS
The earthwork for the project consisted of placing compacted fill to grade the site and provide
support for floor slab, as well as subgrade support for adjacent walks and slabs, roadways and
driveways, curbs and gutters, and for parking lot paving. The grading work included placing
compacted soils as backfill against walls below grade, around footings, around the electric vault,
around the catch basin, around the elevator pit, and in trenches for water, storm drain, sewer, fire
protection sprinkler, and electrical line installations. Also, base course was placed and compacted in
parking lot, driveway, and roadway paving areas.
SOIL TYPES
The soils used for the required filling consisted of on -site silty sand with clay, well graded sand, silty
sand, and itnported crushed miscellaneous base material. Pea gravel was also placed and consolidated
as backfill behind the exterior walls of the parking structure.
Hoag Memorial Hospital Presbyterian - Geotechnical Inspection Services February 13, 2002
Law/Crandall Project 70144-0-D057
INSTALLATION OF TIE -BACK ANCHORS
After installation of the soldier piles and excavation to the first bench, the tie -back anchors were
installed at the design locations and elevations indicated on the shoring plan. The shafts for the tie-
back anchors were observed for soil conditions and excavation to design dimensions.
ANCHOR TESTING
Following installation of the tie -back anchors and curing of the concrete, each anchor was tested to
150% or to 200% of the design load, in accordance with the project plans. Selected anchors were
tested to 200% to meet the criteria for 30-minute and 24-hour anchor load testing. After testing and
approval each anchor was locked -off near the design load and mass excavation continued until the
final excavation level for parking structure construction was reached. The data for the soldier pile and
anchor installation and subsequent anchor testing are retained in our files should further reference be
required.
OBSERVATION AND TESTING OF COMPACTED FILL
This section describes our observation and testing of compacted fill placed as part of the project
earthwork.
LOCATIONS
The earthwork for the project consisted of placing compacted fill to grade the site and provide
support for floor slab, as well as subgrade support for adjacent walks and slabs, roadways and
driveways, curbs and gutters, and for parking lot paving. The grading work included placing
compacted soils as backfill against walls below grade, around footings, around the electric vault,
around the catch basin, around the elevator pit, and in trenches for water, storm drain, sewer, fire
protection sprinkler, and electrical line installations. Also, base course was placed and compacted in
parking lot, driveway, and roadway paving areas.
3
Hoag Memorial Hospital Presbyterian - Geotechnica! Inspection Services Fehrua y 22, 2002
Law/Crandall Project 70144-0-0057
COMPACTION SPECIFICATIONS
The specifications required that the fill and backfill be compacted to at least 90% of the maximum
dry density obtainable by the ASTM Designation D1557-91 (equivalent to UBC 70-1) method of
compaction. In accordance with Instruction Bulletin No. 333 dated October 10, 2001 by Taylor and
Associates, the upper four feet of backfill in planter areas adjacent to the north retaining wall were to
be compacted to at least 80% of the maximum dry density. The base course was to be compacted to at
least 95% of the maximum density.
Compaction tests were performed on representative samples of the soils to establish the maximum
dry densities. The tests were performed in general accordance with the specified ASTM Designation
D1557-91 (equivalent to UBC 70-1) method of compaction, which uses a 1/30-cubic-foot mold in
which each of five layers of soil is compacted by 25 blows of a 10-pound hammer falling 18 inches.
The results of the compaction tests were used in establishing the degree of compaction achieved
during the placement of the fill.
The soil type, maximum dry density, and optimum moisture content of the fill are given in the
attached Table 1, Soil Classification and Compaction Data.
PLACEMENT AND COMPACTION OF FILL
After installation of shoring, the site was stripped and cleared, existing fill and disturbed natural soils
were excavated from the parking structure area to the desired level for construction. Next, the
exposed natural soils were scarified to a depth of 6 inches, brought to near -optimum moisture
content, and rolled with heavy compaction equipment. In the parking lot and hardscape areas, the
uppermost subgrade soils were reworked. Where soft and wet soils were encountered during grading,
these soils were excavated and replaced with pea gravel, and consolidated. The required fill materials
were then placed in loose lifts approximately 8 inches in thickness, brought to near -optimum
moisture content. The loose lifts were compacted using a loader, a hand -guided impact compactor, a
sheepsfoot roller, a vibratory plate compactor, and a wheel compactor attached to a backhoe.
4
Hoag Memorial Hospital Presbyterian - Georechnical Inspection Services February 22, 2002
Law/Crandall Project 70144-0-0057
Areas to receive backfill were first cleared of construction debris and loose soils; the required backfill
soils were then placed in loose lifts approximately 8 to 18 inches in thickness, brought to near -
optimum moisture content. The soils were compacted using a vibratory sheepsfoot roller, a vibratory
plate compactor, and hand -guided impact compactors.
FIELD DENSITY TESTING
Sand -cone field density tests were performed to establish the degree of compaction achieved during
the placement of the fill. The tests were performed in general accordance with the ASTM
Designation D1556 (equivalent to UBC 70-2) for sand -cone field density testing. Where a test
indicated less than the required compaction, the soils were reworked and retested until at least the
specified degree of compaction resulted. The results of the field density tests are presented in the
attached table, Test Results; the approximate locations of the tests are shown on the Plot Plan, except
Test 328. This test was performed on an off -site electric trench backfill located on Hoag Drive, west
of James Irvine Surgery Center.
As requested, our field technician also observed installation of a subdrain system at the base of the
parking structure perimeter walls and the north retaining walls. The subdrain system consisted of
perforated pipes surrounded with crushed rock and geo-fabric filter.
OBSERVATION OF FOUNDATION EXCAVATIONS
The following foundation design recommendations were presented in our geotechnical investigation
report:
Spread footings carried at least 1 foot into the stiff and dense natural soils, and at
least 3 feet below the lowest adjacent floor level, may be designed to impose a net
dead -plus -live load pressure of 6,000 pounds per square foot. A one-third increase
in the bearing value may be used when considering wind or seismic loads....
Footings for minor structures (including retaining walls, free-standing walls, and
elevator pit walls) established in properly compacted fill and/or the undisturbed
natural soils, may be designed to impose a net dead -plus -live load pressure of 1,500
pounds per square foot. Footings should extend at least 1 %z feet below the adjacent
final grade or floor level.
5
Hoag Memorial Hospital Presbyterian - Geotechnical Inspection Services February 22, 2002
Law/Crandall Project 70144-0-0057
Excavations were made for spread footings to support the parking structure. Excavations were also
made for retaining walls and planter walls. Our field technician observed and probed the footing
excavations to confirm that the soils were undisturbed natural materials or properly compacted fills
recommended for foundation support. After observations indicated satisfactory conditions, written
notice of our approval was left at the job site for the information of responsible parties.
OBSERVATION AND TESTING OF ASPHALT PAVING
As requested, our field technician observed the asphalt paving placed in the parking lot roadway, and
driveway areas and performed ASTM Designation D2922-81 (equivalent to UBC 70-5) nuclear gage
in -place density tests to establish the degree of compaction achieved. The asphalt paving was to be
compacted to at least 95% of the maximum density.
The asphalt concrete consisted of1/2-inch and %-inch aggregate using AR4000 asphalt cement. At the
time of delivery, the temperature of the asphalt ranged from 290° to 310° Fahrenheit. Values of 147
and 151 pounds per cubic foot were used for the asphalt maximum density.
The nuclear gage in -place density test results are given in the attached Table 2; the approximate
locations of the tests are shown on the Plot Plan, except Tests 329 and 330. These tests were
performed on the off -site asphalt patch placed along Hoag Drive, west of James Irvine Surgery
Center.
In providing professional geotechnical observations and testing services associated with the
development of the project, we have employed accepted engineering and testing procedures. We also
made a reasonable effort to evaluate that the soil -related work was carried out in general compliance
with the project specifications, our recommendations, and the City of Newport Beach Municipal
Code, and is suitable for the intended use. Although our observation did not reveal obvious
deficiencies, we do not guarantee the contractor's work, nor do the services performed by our firm
6
Hoag Memorial Hospital Presbyterian- Geotechnical Inspection Services Februmy 22, 2002
Law/Crandall Project 70144-11-0057
relieve the contractor of responsibility in the event of subsequently discovered defects in the
contractor's work.
Respectfully submitted,
LAW/CRANDALL
A Division of Law Engineering and Environmental Services. Inc.
SI-
by with permission
fley c.
so i e Manager
Marshall Lew, Ph.D.
Senior Principal
Vice President
G-I Project70144 proejct,2000-project100057100057rpt
Attachments (3)
(3 copies submitted)
cc: (2) City of Newport Beach
Building Department
(1) The Keith Companies
7
CITY OF NEWPORT BEACH
P.O. BOX 1768, NEWPORT BEACH, CA 92658-8915
(1/C Project 70144-0-0057)
MISCELLANEOUS GRADING CERTIFICATE
Project Address: 301 Newport Boulevard,_ Newport Beach, California
Grading Permit No.: 2131 G-98
Owner: Hoag Memorial Hospital Presbyterian
• Type of Project: Single Family
Multi -family
Non-residential
• The following grading work was performed after the preparation of the Rough
Grading Report and was not included as part of the Rough Grading Report:
Trench backfill Retaining wall backfill
Subgrade compaction Foundation for
for hardscape retaining walls
Other (describe)
• Did you perform the required inspections and testing for each of the checked
items? N/A
Yes No
• Specify the compaction test locations and results and the tested foundation
bearing pressure (if applicable).
See our final report dated February 22, 2002 for details.
• I certify that the grading work was done in compliance with the Soils Report for
this project and the work complies with City grading regulations.
Geotechnical Engineer's Name Mrthall LEW, Pn.D. License No. 522 (exp 3/31/03)
Address 200 Citadel Drive, IDS Ang California 90=-1554
Signature
3300 Newport Boulevard, Newport B
Table 1: Compaction Test Data
Soil Type
Optimum
Moisture Maximum Dry
Content (%) Density (pcf)
Silty sand with clay 9.0 129
Silty sand 9.0 133
Well graded sand 15.5 110
Silty sand 9.0 129
Note: Test Method ASTM D1557-91
70144-0-0057-2n2i2oo2
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
1 66% 7.4 123 129 95
2 68 12.8 116 129 90
3 70 12.0 119 129 92
4 72% 10.2 121 129 94
5 74% 10.9 125 129 97
6 74% 10.1 122 129 95
7 73 9.3 120 129 93
8 74 9.8 121 129 94
9 75 9.7 125 129 97
10 74 8.7 124 133 93
11 74'% 7.8 124 133 93
12 75 8.9 125 133 94
13 74'% 8.8 125 133 94
14 76 6.4 122 133 92
15 75 8.7 129 133 97
16 75'% 6.4 123 133 92
17 76 10.0 128 133 96
18 74 9.2 129 133 97
19 75'% 8.2 126 133 95
20 76'% 8.1 132 133 99
21 73 8.7 130 133 98
22 74 8.0 123 133 92
23 75 7.9 120 133 90
24 75% 6.2 127 133 95
25 72% 10.5 110 133 83 A 26
26 72% 10.5 128 133 96
27 73% 10.3 120 133 90
28 72 7.4 114 133 86 A 35
29 72% 10.1 120 133 90
30 74% 9.6 124 133 93
31 77'% 8.6 126 133 95
32 76'% 8.9 123 133 92
33 71'% 14.0 105 110 95
34 75 9.5 122 133 92
35 72 8.6 123 133 92
36 78 CMB 150 154 97 AA
37 78 CMS 147 150 98 AA
38 78 CMB 154 156 99 AA
39 78% CMS 153 156 98 AA
40N 78 AC 142 147 97 AA
00057tb1/kz 2/22/2002 Pagel
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
41N 78 AC 143 147 97 AA
42N 78 AC 148 147 101 A4
43N 78 AC 144 147 98 M
44N 78 AC 144 147 98 AA
45 76 11.6 121 133 91
46 69 10.9 114 129 88 A 47
47 69 10.8 116 129 90
48 72% 8.3 118 129 91
49 65 10.6 124 133 93
50 61 9.7 123 133 92
51 63 10.0 124 133 93
52 59% 14.3 105 110 95
53 60% 14.0 106 110 96
54 62 16.3 104 110 95
55 63 15.2 101 110 92
56 61 14.8 103 110 94
57 59% 13.9 106 110 96
58 59% 16.1 108 110 98
59 61 17.2 104 110 95
60 56% 10.9 116 129 90
61 55% 9.6 119 129 92
62 57 8.6 117 129 91
63 59 9.4 118 129 91
64 56 14.5 101 110 92
65 55'% 15.0 103 110 94
66 58 10.0 120 129 93
67 59 8.9 121 129 94
68 52 14.2 102 110 93
69 53% 11.0 116 129 90
70 60'/z 9.0 118 129 91
71 62 15.1 102 110 93
72 56 15.7 105 110 95
73 591,4 13.9 104 110 95
74 58 10.4 122 129 95
75 59% 10.7 120 129 93
76 61 9.5 124 129 96
77 55% 10.3 107 110 97
78 56 9.3 117 129 91
79 61 12.4 104 110 95
80 62 13.3 103 110 94
00057th0kz 2/22/2002
Page 2
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
81 64 13.1 106 110 96
82 58 12.4 103 110 94
83 61 14.5 104 110 95
84 59 10.6 119 129 92
85 61'/z 10.2 121 129 94
86 61 11.1 119 129 92
87 62% 13.1 120 129 93
88 55 10.1 120 129 93
89 54 11.0 118 129 91
90 60 9.5 119 129 92
91 58 9.3 116 129 90
92 6314 9.7 119 129 92
93 63% 8.7 118 129 91
94 6314 8.4 119 129 92
95 621A 8.3 117 129 91
96 6214 8.9 117 129 91
97 61 8.7 117 129 91
98 62 8.9 117 129 91
99 60 10.2 116 129 90
100 61 9.5 119 129 92
101 77 12.0 121 133 91
102 58 12.5 102 110 93
103 58 13.5 101 110 92
104 57 13.0 100 110 91
105 58 10.5 117 129 91
106 58 10.2 116 129 90
107 58 10.4 119 129 92
108 58 13.2 101 110 92
109 58 13.3 101 110 92
110 58 12.8 100 110 91
111 58 13.8 104 110 95
112 58 13.6 104 110 95
113 58 12.9 102 110 93
114 5714 9.3 118 129 91
115 58 10.8 116 129 90
116 58 11.0 117 129 91
117 60 11.1 120 129 93
118 631A 10.9 122 129 95
119 60'/ 9.8 118 129 91
120 621A 10.6 111 129 86 A 121
00057tb1&z 2/22/2002 Page 3
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (lbs/cu. ft.) Compaction Number
121 62% 10.8 117 129 91
122 63% 11.3 118 129 91
123 64 11.1 125 129 97
124 66 10.5 122 129 95
125 65% 9.9 124 129 96
126 64 10.5 117 129 91
127 62 9.9 123 129 95
128 64 9.0 116 129 90
129 65 11.5 120 129 93
130 67 11.6 121 129 94
131 65% 10.4 121 129 94
132 66% 10.1 124 129 96
133 68 8.8 122 129 95
134 69 10.2 119 129 92
135 73^% 12.8 106 129 82 A 136
136 731,4 10.5 116 129 90
137 711,4 9.7 119 129 92
138 73 6.3 116 129 90
139 71 8.7 115 129 89 A 140
140 71 7.8 117 129 91
141 70'% 11.8 116 129 90
142 73% 11.7 118 129 91
143 67 11.0 121 129 94
144 71'/z 11.8 117 129 91
145 67 10.8 120 129 93
146 71% 11.3 117 129 91
147 74% 9.9 122 129 95
148 76 10.6 119 129 92
149 76 9.1 127 133 95
150 77% 11.7 122 133 92
151 72 10.1 124 133 93
152 78% 9.8 126 133 95
153 75% 10.3 122 129 95
154 75 9.8 119 129 92
155 73% 10.0 119 129 92
156 74 9.6 119 129 92
157 46 14.5 104 110 95
158 55 14.3 104 110 95
159 50 15.9 99 110 90
160 54% 15.7 101 110 92
00057t61/kz 2/22/2002 Page4
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
161 58 14.9 104 110 95
162 60 13.3 105 110 95
163 77 11.3 119 129 92
164 75% 10.8 122 129 95
165 68 14.4 103 110 94
166 61 15.5 102 110 93
167 74 6.3 116 129 90
168 77^/ 7.6 118 129 91
169 73 11.1 121 129 94
170 69% 10.2 116 129 90
171 71'/2 10.0 117 129 91
172 73'/z 10.0 119 129 92
173 75% 9.8 122 129 95
174 74 9.3 116 129 90
175 75'% 9.8 116 129 90
176 70 10.2 125 129 97
177 72 10.0 121 129 94
178 75 9.3 119 129 92
179 74 9.7 120 129 93
180 75^/ 9.5 119 129 92
181 71 11.1 117 129 91
182 73 10.1 116 129 90
183 73 10.5 116 129 90
184 75 10.8 118 129 91
185 72% 9.9 117 129 91
186 74% 10.2 118 129 91
187 73 10.3 124 129 96
188 75 10.0 121 129 94
189 74 10.5 122 129 95
190 76 9.6 121 129 94
191 78 9.6 117 129 91
192 80 9.4 117 129 91
193 78'% 9.1 118 129 91
194 80^% 8.9 119 129 92
195 78% 10.5 117 129 91
196 79'/ 10.4 116 129 90
197 71 ^% 9.2 120 129 93
198 73% 9.3 121 129 94
199 75% 9.1 119 129 92
200 75 9.0 118 129 91
n0057tb1/kz 2/22/2002
Page 5
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
201 66'% 8.1 117 129 91
202 72'% 9.7 116 129 90
203 7414 10.0 118 129 91
204 68% 9.5 119 129 92
205 74 10.8 118 129 91
206 74'% 11.1 120 129 93
207 79 8.5 118 129 91
208 78% 8.7 120 129 93
209 78 8.0 116 129 90
210 70 10.6 117 129 91
211 78'% 9.0 118 129 91
212 72 9.0 119 129 92
213 7414 10.0 118 129 91
214 75 9.9 119 129 92
215 7714 9.5 119 129 92
216 78'/ 9.8 117 129 91
217 74 10.2 121 129 94
218 76 9.6 120 129 93
219 76 9.5 119 129 92
220 72 10.5 120 129 93
221 75 10.2 118 129 91
222 79 9.5 119 129 92
223 80 9.7 118 129 91
224 75 8.7 122 129 95
225 80 8.7 117 129 91
226 79 8.5 117 129 91
227 7714 CMB 131 138 95 AA
228 7414 9.5 117 129 91
229 76 9.9 121 129 94
230 7714 9.0 118 129 91
231 7514 9.3 119 129 92
232 78 9.8 119 129 92
233 76'/% 10.2 122 129 95
234 79 CMB 138 141 98 AA
235 7814 CMB 140 143 98 AA
236 7914 CMB 130 137 95 AA
237 80 CMB 139 142 98 AA
238 79 CMB 140 143 98 AA
239 7914 CMB 134 138 97 AA
240 75 9.7 119 129 92
00057tb1/ z 2/22/2002
Page 6
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
241 74 9.9 120 129 93
242 77 9.5 119 129 92
243 78 CMB 144 147 98 AA
244 77% CMB 130 137 95 AA
245 78 11.1 119 129 92
246 74% CMB 133 137 97 AA
247 76% CMB 131 136 96 AA
248 76' CMB 132 137 96 AA
249 76% CMB 132 138 96 AA
250 76% CMB 135 141 96 AA
251 77 CMB 132 135 98 AA
252 52 10.3 118 129 91
253 56% 10.5 118 129 91
254N 79% AC 142 147 97 AA
255N 78% AC 139 147 95 AA
256N 781,4 AC 141 147 96 AA
257N 79% AC 140 147 95 AA
258N 79% AC 141 147 96 AA
259N 81 AC 139 147 95 AA
260N 80 AC 139 147 95 AA
261N 77 AC 139 147 95 AA
262N 78'% AC 142 147 97 AA
263N 78 AC 144 147 98 AA
264N 78 AC 142 147 97 AA
265N 79 AC 139 147 95 AA
266N 78 AC 139 147 95 AA
267N 79 AC 139 147 95 AA
268N 78% AC 142 147 97 AA
269N 76 AC 139 147 95 AA
270N 76 AC 143 147 97 AA
271N 76% AC 139 147 95 AA
272N 77 AC 140 147 95 AA
273N 75 AC 141 147 96 AA
274 56% 13.0 102 110 93
275 50 12.5 102 110 93
276 78% 9.8 121 129 94
277 77% 8.9 120 129 93
278 78 9.2 121 129 94
279 78% 8.7 119 129 92
280 79 7.0 116 129 90
00057tbl/kz J22/2002
Page 7
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (lbs/cu. ft.) (Ibs/cu. ft.) Compaction Number
321 65 9.0 118 129 91
322 67 10.7 121 129 94
323 69% 10.8 115 129 89 *
324 71% 10.4 112 129 87 *
325 75 10.3 109 129 84 *
326 65 11.1 109 129 84 *
327 58% 11.1 110 129 85 *
328 80 9.5 122 129 95
329N 79% AC 143 151 95 AA
330N 79% AC 143 151 95 AA
331 60'/z 9.5 116 129 90
332 62'% 11.1 116 129 90 *
333 64'% 9.9 116 129 90 *
334 57'% 10.5 119 129 92
335 59'% 11.1 124 129 96
336 62 11.6 119 129 92
337 64 11.0 119 129 92
338 61 % 10.9 119 129 92
339 66 11.4 120 129 93
340 68 10.0 116 129 90
341 70 10.2 116 129 90
342 72 9.9 121 129 94
343 74 9.1 126 129 98
344 63'% 10.3 121 129 94
345 65% 11.6 112 129 87 *
346 67% 10.4 113 129 88 *
347 55 11.1 116 129 90
348 501A 10.6 119 129 92
349 58'% 10.8 117 129 91
350 54 11-0 116 129 90
351 67'% 9.6 118 129 91
352 57% 9.0 117 129 91
353 59'% 9.0 116 129 90
354 61'% 8.9 116 129 90
355 63% 11.1 124 129 96
356 64'% 11.0 124 129 96
357 61% 10.5 117 129 91
00057!b1,xls/kz 2/22/02
Page 9
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
281 79 7.9 119 129 92
282 77% 9.0 119 129 92
283 79 9.2 116 129 90
284 78% 11.1 122 129 95
285 78 8.7 117 129 91
286 76% 9.0 119 129 92
287 78 9.3 117 129 91
288 80 9.3 116 129 90
289 77 7.0 116 129 90
290 75 8.9 116 129 90
291 49% 11.0 122 129 95
292 50% 10.9 121 129 94
293 51'/ 15.1 102 110 93
294 51% 11.0 116 129 90
295 52% 10.7 116 129 90
296 53'/% 9.1 116 129 90
297 54% 9.8 118 129 91
298 61 10.3 117 129 91
299 53 10.0 117 129 91
300 55'/z 11.1 116 129 90
301 56% 10.2 125 129 97
302 65 9.6 116 129 90
303 71 10.0 117 129 91
304 50% 9.0 122 129 95
305 52% 8.8 118 129 91
306 49% 9.5 122 129 95
307 51% 9.3 120 129 93
308 53% 9.6 120 129 93
309 55'% 10.8 119 129 92
310 57 11.0 124 129 96
311 59 10.5 120 129 93
312 58 11.1 114 129 88 *
313 60 10.0 115 129 89 *
314 73'/ 10.3 120 129 93
315 75% 10.1 122 129 95
316 61 7.5 116 129 90
317 63 7.7 117 129 91
318 65 11.1 109 129 84 *
319 67 11.0 113 129 88 *
320 63 9.3 121 129 94
00057t 1/kz 2/22/2002 Page 8
Table 2: Field Density Test Results
Moisture Dry Maximum
Test Elevation Content Density Dry Density Percent Retest
Number (ft.) (% of Dry Wt.) (Ibs/cu. ft.) (Ibs/cu. ft.) Compaction Number
358 63 10.3 116 129 90
Notes:
Elevations refer to job datum.
A Indicates area reworked and retested.
AA Indicates 95% compaction required.
CMB Indicates crushed miscellaneous base material;
wet density values used in calculations.
AC Indicates asphalt concrete.
N Indicates nuclear gage density test.
* Indicates 80% compaction required.
00057tb1/kz 2/22/2002 Page 10
H0SPITA
...NAM VD.,ORAN
PS. i*,, en ruin•
diuw wou asiAV Snt 4G?IOG ewou'u LIST
n.va pew c[ a'v OF i¢.M-s:• ve.r IOC/ .._::
•x.aKO rel.x cnzavic« suu te..-, I
COSErcac aJo ru¢'-cxc. aimzmmacron- _
w �m
0
cc
w
0 o
m
cr
e
W
2
4
IA,
•
SLa.Y3 'ws..
°`mIM fM0".`,...., (,.1t.
:L- — .,..ram..
tGUAaitR1-WMtQ,Y
Pam r:
m c nark
.._..— Pea Wan N� Ed,