November 16, 2021
Agenda Item No. 14
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer,
tsandefur@newportbeachca.gov
PHONE: 949-644-3321
TITLE: FY2019-20 Streetlight Improvements (Eastbluff) — Notice of
Completion for Contract No. 7661-2 (20V02)
On September 8, 2020, the City Council awarded Contract No. 7661-2, FY 2019-20
Streetlight Improvements (Eastbluff) to International Line Builders, Inc. (ILB) of Corona,
California. The work is now complete and staff requests City Council acceptance and
close out of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$723,858.00
$756,478.30
10% or less
+4.5%
-1.0%
+5.5%
Allowed Contract Time +
135
Actual Time
0
Approved Extensions (days) =
Under (-) or Over (+)
14-1
FY2019-20 Streetlight Improvements (Eastbluff) — Notice of Completion for Contract No.
7661-2 (20V02)
November 16, 2021
Page 2
The project removed and replaced old conduits, wires, pull boxes and streetlight heads.
The project also installed new pull boxes, LED streetlight lamps, and five new service
cabinets. Finally, the circuits along Vista del Oro between Vista del Sol and Eastbluff
Drive, and the residential streets enveloped by Eastbluff Drive and Jamboree Road, were
converted from high-voltage to medium -voltage.
The contracted work has now been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original Bid Amount:
$
723,858.00
Actual Cost of Bid Items Constructed:
$
702,323.14
Total Change Orders:
$
54,155.16
Final Contract Cost:
$
756,478.30
The final contract cost at $756,478.30 is approximately 4.5%higher than the original bid
amount. Almost $19,000 of the additional cost was required for temporary power to the
streetlights due to Southern California Edison (SCE) scheduling delays. ILB provided
temporary light towers and generators to power the streetlights in the Eastbluff
neighborhoods. Additionally, ILB encountered more damaged conduits and tree root
blockages than staff expected, resulting in costs totaling approximately 14% of the
change order amount. The remainder of the extra costs were incurred due to the City
providing direction to the contractor to conduct additional streetlighting work in order to
take advantage of ILB's competitive pricing and quality work.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule March 15, 2021
Actual Start of Construction Per Notice to Proceed March 11, 2021
Extended Contract Completion Date Inclusive of Extra Work September 20, 2021
Actual Substantial Construction Completion Date September 20, 2021
Additional time was added to the contract for the SCE scheduling delays related to the
five new service cabinets.
FISCAL IMPACT:
Funds for the construction contract were expended from the following accounts:
Account Description
Neighborhood Enhancement
General Fund
Account Number
53601-980000-20V02
01201927-980000-17V02
Total:
Amount
$ 733,246.31
$ 23,231.99
$ 756,478.30
14-2
FY2019-20 Streetlight Improvements (Eastbluff) — Notice of Completion for Contract No.
7661-2 (20V02)
November 16, 2021
Page 3
ENVIRONMENTAL REVIEW:
On September 8, 2020, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(c) (replacement of existing
facilities involving negligible expansion of capacity) of the CEQA Guidelines, California
Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant
effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
14-3
Q
C
17TI
)TH S
CITY OF COSTA
MESA
PROJECT LOCATIONS
JOHN WAYNE
AIRPORT
PgC//C-/C
CCF -4/V
VICINITY MAP
NOT TO SCALE
FY 2019-20 STREETLIGHT
IMPROVEMENT PROJECT (EASTBLUFF)
LOCATION MAP
- O�p
CITY OF
IRVINE
P�
UNIVERSITY
Attachment P
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7661-2 1 11/16/21
14-4