RESOLUTION NO. ZA2021-089
A RESOLUTION OF THE ZONING ADMINISTRATOR OF THE
CITY OF NEWPORT BEACH APPROVING COASTAL
DEVELOPMENT PERMIT NO. CD2021-065 TO RAISE AN
EXISTING SEAWALL LOCATED AT 2676 BAY SHORE DRIVE
(PA2021-250)
THE ZONING ADMINISTRATOR OF THE CITY OF NEWPORT BEACH HEREBY FINDS AS
FOLLOWS:
SECTION 1. STATEMENT OF FACTS.
1. An application was filed by Skurman Architects, with respect to property located at 2676
Bayshore Drive, requesting approval of a coastal development permit.
2. The lot at 2676 Bay Shore Drive is legally described as Lot 54 of Tract 907.
3. The applicant proposes to raise an existing concrete seawall to a height of 10.9 feet North
American Vertical Datum of 1988 (NAVD 88). The existing seawall has an elevation that
varies from 7.90 to 8.28 feet NAVD 88. The applicant proposes to remove existing
distressed concrete coping and construct new concrete coping with a concrete stem wall,
which is located within the permit jurisdiction of the City.
4. The subject property is designated Single Unit Residential Detached (RS-D) by the
General Plan Land Use Element and is located within the Single-Unit Residential (R-1)
Zoning District.
5. The subject property is located within the coastal zone. The Coastal Land Use Plan
category is Single Unit Residential Detached (RSD-B) (6.0 – 9.9 DU/AC) and it is located
within the Single-Unit Residential (R-1) Coastal Zone District.
6. A public hearing was held on December 16, 2021, online via Zoom. A notice of time, place
and purpose of the hearing was given in accordance with the Newport Beach Municipal
Code (NBMC). Evidence, both written and oral, was presented to, and considered by,
the Zoning Administrator at this hearing.
SECTION 2. CALIFORNIA ENVIRONMENTAL QUALITY ACT DETERMINATION.
1. This project is categorically exempt pursuant to Title 14 of the California Code of
Regulations Section 15303, Division 6, Chapter 3, Guidelines for Implementation of the
California Environmental Quality Act (CEQA) under Class 3 (New Construction or
Conversion of Small Structures), because it has no potential to have a significant effect
on the environment.
2. Class 3 exempts the construction of accessory structures. The proposed project
consists of the construction of a raised concrete seawall.
Zoning Administrator Resolution No. ZA2021-089
Page 2 of 7
07-02-19
3.The exceptions to this categorical exemption under Section 15300.2 are not applicable.
The project location does not impact an environmental resource of hazardous or critical
concern, does not result in cumulative impacts, does not have a significant effect on the
environment due to unusual circumstances, does not damage scenic resources within
a state scenic highway, is not a hazardous waste site, and is not identified as a historical
resource.
SECTION 3. REQUIRED FINDINGS.
In accordance with Section 21.52.015 (Coastal Development Permits, Findings and Decision)
of the Newport Beach Municipal Code, the following findings and facts in support of such
findings are set forth:
Finding:
A.Conforms to all applicable sections of the certified Local Coastal Program.
Facts in Support of Finding:
1.The proposed improvements comply with applicable residential development standards
including height of accessory structures in the front setback. The proposed raised
seawall is located within the required front setback area abutting the bay, which is 10
feet. The existing concrete seawall has an elevation which varies from 7.9 to 8.28 feet
NAVD 88, is proposed to be raised to 10.9 feet NAVD 88 while being adaptable to a
future height of 14.4 feet NAVD 88. The proposed seawall meets the current City of
Newport Beach standard of 10.9 NAVD 88. All proposed improvements comply with
height requirements for accessory structures in the front setback.
2.The neighborhood is predominantly developed with two- and three-story, single-family
residences with protective shoreline devices. The proposed raised bulkhead is
consistent with the existing neighborhood pattern of development.
3.According to a Coastal Hazards Report and Sea Level Rise Analysis prepared by
Geosoils, Inc. dated July 15, 2021, there is an existing seawall which serves the subject
property. The seawall has an elevation which varies from 7.9 to 8.28 feet (NAVD 88).
The current maximum bay water elevation is 7.7 feet (NAVD 88) and may exceed the
7.90 to 8.28 feet (NAVD 88) top of bulkhead elevation for the seawall during high tide or
storm events. The proposed raising of the seawall to 10.9 feet NAVD 88 is to prevent
flooding into the property. The project includes reinforcing and raising the existing
seawall to 10.9 feet (NAVD 88) with an adaptability elevation of 14.4 feet (NAVD88).
This is above the minimum required 10.9 feet (NAVD 88). Flooding, wave runup, and
erosion will not significantly impact this property over the proposed 75-year economic
life of the development. Flood shields (sandbags and other barriers) can be deployed
across the openings to protect and prevent flooding to the structure. The report
concludes that the proposed project will be reasonably safe from flooding hazards for
the next 75 years.
Zoning Administrator Resolution No. ZA2021-089
Page 3 of 7
07-02-19
4.The property is located in an area known for the potential of seismic activity and
liquefaction. All projects are required to comply with the California Building Code (CBC)
and Building Division standards and policies. Geotechnical investigations specifically
addressing liquefaction are required to be reviewed and approved prior to the issuance of
building permits. Permit issuance is also contingent on the inclusion of design mitigation
identified in the investigations. Construction plans are reviewed for compliance with
approved investigations and CBC prior to building permit issuance.
5.The project site is not located adjacent to a coastal view road, public access way, or
Coastal Viewpoint as identified in the Coastal Land Use Plan. The nearest coastal view
road that is West Coast Highway, which is located approximately 1,200 feet from the
subject property. The project does not contain any unique features that could degrade the
visual quality of the coastal zone.
Finding:
B.Conforms with the public access and public recreation policies of Chapter 3 of the
Coastal Act if the project is located between the nearest public road and the sea or
shoreline of any body of water located within the coastal zone.
Facts in Support of Finding:
1.The project site is located between the nearest public road and the sea or shoreline.
Implementation Plan Section 21.30A.040 requires that the provision of public access bear
a reasonable relationship between the requirement and the project’s impact, and be
proportional to the impact. In this case, the project raises an existing seawall within the
front setback area abutting the bay. Therefore, the project does not involve a change in
land use, density or intensity that will result in increased demand on public access and
recreation opportunities. Furthermore, the project is designed and sited (appropriate
height, setbacks, etc.) so as not to block or impede existing public access opportunities.
2.Lateral access to the bay is available throughout various entrances from West Coast
Highway. The project does not include any features that would obstruct access to the bay.
SECTION 4. DECISION.
NOW, THEREFORE, BE IT RESOLVED:
1.The Zoning Administrator of the City of Newport Beach hereby finds this Project is
categorically exempt from the California Environmental Quality Act (“CEQA”) pursuant to
Section 15303 under Class 3 (New Construction or Conversion of Small Structures) of the
CEQA Guidelines, California Code of Regulations, Title 14, Division 6, Chapter 3, because
it has no potential to have a significant effect on the environment.
2.The Zoning Administrator of the City of Newport Beach hereby approves Coastal
Development Permit No. CD2021-065, subject to the conditions set forth in Exhibit “A,”
which is attached hereto and incorporated by reference.
Zoning Administrator Resolution No. ZA2021-089
Page 4 of 7
07-02-19
3.This action shall become final and effective 14 days following the date this Resolution
was adopted unless within such time an appeal or call for review is filed with the
Community Development Director in accordance with the provisions of Title 21 Local
Coastal Implementation Plan, of the Newport Beach Municipal Code. Final action taken
by the City may be appealed to the Coastal Commission in compliance with Section
21.64.035 of the City’s certified LCP and Title 14 California Code of Regulations,
Sections 13111 through 13120, and Section 30603 of the Coastal Act.
PASSED, APPROVED, AND ADOPTED THIS 16TH DAY OF DECEMBER, 2021.
Zoning Administrator Resolution No. ZA2021-089
Page 5 of 7
07-02-19
EXHIBIT “A”
CONDITIONS OF APPROVAL
1.The development shall be in substantial conformance with the approved site plan stamped
and dated with the date of this approval (except as modified by applicable conditions of
approval).
2.The existing seawall shall be reinforced and capped to 10.9 feet (NAVD 88) minimum in
accordance with the recommendations provided in the report prepared by Geosoils, Inc.
on July 15, 2021 and as identified in the approved plans.
3.The alterations to the seawall shall allow for a future increase in height without further
seaward encroachment.
4.Prior to final building permit inspection, an agreement in a form approved by the City
Attorney between the property owner and the City shall be executed and recorded
waiving rights to the construction of future shoreline protection devices including the
repair and maintenance, enhancement, reinforcement, or any other activity affecting the
bulkhead, that results in any encroachment seaward of the authorized footprint of the
bulkhead or other shoreline protective device. The agreement shall be binding against
the property owners and successors and assigns.
5.Prior to the issuance of a building permit, the property owner shall submit a notarized
signed letter acknowledging all hazards present at the site, assuming the risk of injury
or damage from such hazards, unconditionally waiving any claims of damage against
the City from such hazards, and to indemnify and hold harmless City, its City Council, its
boards and commissions, officials, officers, employees, and agents from and against any
and all claims, demands, obligations, damages, actions, causes of action, suits, losses,
judgments, fines, penalties, liabilities, costs and expenses (including without limitation,
attorney’s fees, disbursements and court costs) of every kind and nature whatsoever which
may arise from or in any manner relate (directly or indirectly) to City’s approval of
development. This letter shall be scanned into the plan set prior to building permit issuance.
6.No demolition or construction materials, equipment debris, or waste, shall be placed or
stored in a location that would enter sensitive habitat, receiving waters, or a storm drain
or result in impacts to environmentally sensitive habitat areas, streams, the beach,
wetlands or their buffers. No demolition or construction materials shall be stored on
public property.
7.Demolition beyond the approved scope of work requires planning division approval prior
to commencement of work. Approval of revisions to project plans are not guaranteed. Any
changes in the current scope of work may require the entire structure to be demolished
and redeveloped in conformance with the current Zoning Code Development Standards.
8.The applicant is responsible for compliance with the Migratory Bird Treaty Act (MBTA).
In compliance with the MBTA, grading, brush removal, building demolition, tree
trimming, and similar construction activities shall occur between August 16 and January
Zoning Administrator Resolution No. ZA2021-089
Page 6 of 7
07-02-19
31, outside of the peak nesting period. If such activities must occur inside the peak
nesting season from February 1 to August 15, compliance with the following is required
to prevent the taking of native birds pursuant to MBTA:
A.The construction area shall be inspected for active nests. If birds are observed flying
from a nest or sitting on a nest, it can be assumed that the nest is active. Construction
activity within 300 feet of an active nest shall be delayed until the nest is no longer
active. Continue to observe the nest until the chicks have left the nest and activity is no
longer observed. When the nest is no longer active, construction activity can continue
in the nest area.
B.It is a violation of state and federal law to kill or harm a native bird. To ensure
compliance, consider hiring a biologist to assist with the survey for nesting birds, and
to determine when it is safe to commence construction activities. If an active nest is
found, one or two short follow-up surveys will be necessary to check on the nest and
determine when the nest is no longer active.
9.Best Management Practices (BMPs) and Good Housekeeping Practices (GHPs) shall
be implemented prior to and throughout the duration of construction activity as
designated in the Construction Erosion Control Plan.
10.The discharge of any hazardous materials into storm sewer systems or receiving waters
shall be prohibited. Machinery and equipment shall be maintained and washed in
confined areas specifically designed to control runoff. A designated fueling and vehicle
maintenance area with appropriate berms and protection to prevent spillage shall be
provided as far away from storm drain systems or receiving waters as possible.
11.Debris from demolition shall be removed from work areas each day and removed from
the project site within 24 hours of the completion of the project. Stock piles and
construction materials shall be covered, enclosed on all sites, not stored in contact with
the soil, and located as far away as possible from drain inlets and any waterway.
12.Trash and debris shall be disposed in proper trash and recycling receptacles at the end
of each construction day. Solid waste, including excess concrete, shall be disposed in
adequate disposal facilities at a legal disposal site or recycled at a recycling facility.
13.Revisions to the approved plans may require an amendment to this Coastal
Development Permit or the processing of a new coastal development permit.
14.This approval does not authorize any new or existing improvements (including
landscaping) on State tidelands, public beaches, or the public right-of-way.
15.This Coastal Development Permit does not authorize any development seaward of the
private property.
16.The project is subject to all applicable City ordinances, policies, and standards, unless
specifically waived or modified by the conditions of approval.
Zoning Administrator Resolution No. ZA2021-089
Page 7 of 7
07-02-19
17.The applicant shall comply with all federal, state, and local laws. Material violation of
any of those laws in connection with the use may be cause for revocation of this Coastal
Development Permit.
18.This Coastal Development Permit may be modified or revoked by the Zoning
Administrator if determined that the proposed uses or conditions under which it is being
operated or maintained is detrimental to the public health, welfare or materially injurious
to property or improvements in the vicinity or if the property is operated or maintained
so as to constitute a public nuisance.
19.Prior to issuance of a building permit, a copy of the Resolution, including conditions of
approval Exhibit “A” shall be incorporated into the Building Division and field sets of
plans.
20.Prior to the issuance of building permit, the applicant shall pay any unpaid administrative
costs associated with the processing of this application to the Planning Division.
21.Should the property be sold or otherwise come under different ownership, any future
owners or assignees shall be notified of the conditions of this approval by the current
property owner or agent.
22.This Coastal Development Permit No. CD2021-065 shall expire unless exercised within 24
months from the date of approval as specified in Section 21.54.060 (Time Limits and
Extensions) of the Newport Beach Municipal Code, unless an extension is otherwise
granted.
23.To the fullest extent permitted by law, applicant shall indemnify, defend and hold harmless
City, its City Council, its boards and commissions, officials, officers, employees, and agents
from and against any and all claims, demands, obligations, damages, actions, causes of
action, suits, losses, judgments, fines, penalties, liabilities, costs and expenses (including
without limitation, attorney’s fees, disbursements and court costs) of every kind and nature
whatsoever which may arise from or in any manner relate (directly or indirectly) to City’s
approval of 2676 Bay Shore Drive Seawall including, but not limited to, Coastal
Development Permit No. CD2021-065 (PA2021-250). This indemnification shall include,
but not be limited to, damages awarded against the City, if any, costs of suit, attorneys'
fees, and other expenses incurred in connection with such claim, action, causes of action,
suit or proceeding whether incurred by applicant, City, and/or the parties initiating or
bringing such proceeding. The applicant shall indemnify the City for all of City's costs,
attorneys' fees, and damages, which City incurs in enforcing the indemnification provisions
set forth in this condition. The applicant shall pay to the City upon demand any amount
owed to the City pursuant to the indemnification requirements prescribed in this condition.