Seimone Jurjis, Community Development
Department Director
Tonee Thai, Acting Chief Building Official
,�
March 8, 2022
Item No. 11
_ ,V,W PO\
cc\ FO V7%
Background
Ordinance No. 2019-8, sets a three-year time limit to
complete construction of one -unit and two -unit family
dwellings.
Approximately 165 building permits are expected to be
subject to the three-year time limit in June 2022.
After June, it is estimated that an average of 25 projects
per month would be subject to the three-year time limit
for completion.
Current Workflow
Ordinance No. 2010-2
3 -YEAR TIME
EXTENSION
NEEDED
HEARING OFFICER
Hear 1St & 2nd extension
request. May grant up to 180
days extension.
CITY COUNCIL HEAR
ANY ADDITIONAL
EXTENSION
What Happened?
COV/D-79 disrupted the construction industry
Impacts and Delays:
• General Building Materials: OK
• Specialized Orders: 1— 2 Months
• Door / Windows: 5 - 7 Months
• Appliances: 10 —14 Months
• Skilled Labor: Very Limited (many left the industry)
Number of Permits by Age
80 75
70
N
a -j
E 50
L
o 40 36
32
= 30
z
20
12
10 5 3
0
M
3 4 5 6 7 8 9
Age of Permits in Years
Proposed Workflow
HEARING OFFICER
Hear 2nd & 3rd extension
3 -YEAR TIME request. May grant up to 180
EXTENSION days extension.
NEEDED
BUILDING OFFICIAL
Ministerially grant 15t extension
request up to 365 days.
CITY COUNCIL HEAR
ANY ADDITIONAL
EXTENSION
Questions and Discussion
City Council Meeting
March 08, 2022
Tonee Thai, Acting Chief Building Official
Email: tthai@newportbeachca.gov
Phone: 949-718-1867