SOLAR VOLTAIC
ELECTRICAL PLAN REVIEW COMMENTS
RESIDENTIAL
Project Description: SFR SOLAR PV SYSTEM. 4.08 KW. 12 MODULES
Project Address: 1412 NOTTINGHAM RD Plan Check No.: 1434-2021
Permit App. Date:
Applicant/Contact:
Plan Check Engineer: Dan Kennedy
D Ken nedv(a)NewportBeachCA.gov
let Review: 6/24/21 ❑ 2nd Review:
F71Italic comments
Plan Check Expires:
1:10sMT-31
Phone: 949-644-3279
1-1 3rd Review:
The code section references are from the 2019 California Building Code and 2019 California
Electrical Code, unless otherwise stated.
• TO EXPEDITE PROJECT APPROVAL: Please provide a written response indicating how and where
each comment was resolved on the plans.
• Resubmit all previously reviewed plans, updated plans and supporting documents with each
subsequent review.
• AFTER 2nd PLAN REVIEW: Please call the plan check engineer listed above to schedule a plan review
appointment, to expedite project approval.
• Plan review status is available online at www.newportbeachca.00v Project status is also available
using the interactive voice response system at 949-644-3255, or by speaking with a permit technician
at 949-644-3288 during business hours.
ELECTRICAL
1. Provide AC disconnect or other equipment's manufacturer's specification sheets within the
construction plans.
2. Provide an exterior elevation indicating all equipment and their required labels. Clearly identify the
specific location and height of each label on the exterior elevation and clearly identify the complete
information required on each label at the MSP, Inverter, disconnect etc.
3. Provide and illustrate minimum 3 feet working clearances in front of all solar – voltaic equipment.
This correction does not pertain to Planning minimum side yard setback, it pertains to working
clearances.