HomeMy WebLinkAbout09 - City Bridge Deck Maintenance Project — Award of Contract No. 7679-2 (21R13)Q SEW Pp�T
CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
September 13, 2022
Agenda Item No. 9
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, P.E., Assistant City Engineer
tandefur@newportbeachca.gov
PHONE: 949-644-3321
TITLE: City Bridge Deck Maintenance Project — Award of Contract
No. 7679-2 (21 R13)
ABSTRACT:
City of Newport Beach (City) staff received construction bids for the City Bridge Deck
Maintenance Project and requests City Council approval to award the construction
contract to Peterson -Chase General Engineering Construction, Inc. of Irvine, California
(Peterson -Chase). The project performs deck maintenance work to bridges throughout
the City consisting of sealing decks with high molecular weight methacrylate, installing
deck joints, and striping.
RECOMMENDATION:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15301 (c) (repair and maintenance of existing street with no
expansion of use) of the CEQA Guidelines, because this project has no potential to
have a significant effect on the environment;
b) Approve the project drawings and specifications;
c) Award Contract No. 7679-2 to Peterson -Chase General Engineering Construction,
Inc. for the base bid price of $270,800, and authorize the Mayor and City Clerk to
execute the contract; and
d) Establish a contingency of $40,620 (15 percent of total bid) to cover the cost of
unforeseen work not included in the original contract.
9-1
City Bridge Deck Maintenance Project — Award of Contract No. 7679-2 (21 R13)
September 13, 2022
Page 2
DISCUSSION:
Caltrans and City staff conduct periodic inspections of City maintained bridges. Based on
these inspections, a repair strategy is conceived to keep the bridges structurally sound
and extend the useful life of each. One of the strategies for maintaining the concrete
bridge decks is to seal the minor surface cracking to prevent water and corrosive deposits
from entering the bridge deck and damaging the reinforcing steel. This project proposes
to coat the decks of the Newport Island Bridge, the Jamboree Road Bridges, Bison
Avenue Bridge, and Bonita Canyon Bridge. In addition, the asphalt laid over the bridge
joints on Balboa Island Bridge has begun to crack due to the normal movement and
flexing of the bridge. The proposed project will cut a series of joints into the asphalt to
relieve the stress and protect the asphalt.
At 10 a.m. on August 3, 2022, the City Clerk opened and read the following bids for this
project:
411919102-1
TOTAL BID AMOUNT
Low Peterson -Chase General Engineering, Inc. $ 270,800
2nd Beador Construction Company, Inc. $ 282,300
3rd Truesdell Corporation of California, Inc. $ 295,295
4th Applied Restoration, Inc. $ 455,500
The low bid amount is approximately 20 percent lower than the Engineer's Estimate of
$335,500. This lower than anticipated cost is due to the lower cost proposed for the deck
sealant.
The apparent low bidder, Peterson -Chase, Inc., possesses a California state contractor's
license classification "A" as required by the project Special Provisions. The contractor is
registered with the California Department of Industrial Relations as required by California
law to work and bid on public contracts. A check of the contractor's references indicates
satisfactory completion of similar projects for other local public agencies.
Pursuant to the contract documents, the contractor will have 30 consecutive working days
to complete the project.
The project plans and specifications will be available for review at the September 13,
2022 City Council meeting or upon request.
FISCAL IMPACT:
The FY 2022-23 adopted Capital Improvement Program (CIP) budget includes sufficient
funding for the award of this contract. Project funding will be expensed from the following
account:
9-2
City Bridge Deck Maintenance Project — Award of Contract No. 7679-2 (21 R13)
September 13, 2022
Page 3
Account Description Account Number Amount
Gas Tax 12101-980000-21R13 $ 313,000
Proposed fund uses are as follows:
\/Pnrinr
Peterson -Chase, Inc.
Peterson -Chase, Inc.
Various
Total: $
Purpose
Construction Contract
Contingency
Incidentals, Printing
313,000
Amount
$
270,800
$
40,620
$
1,158
Total: $
312,578
Staff recommends establishing $40,620 (15 percent of total bid) for contingency purposes
and unforeseen conditions associated with construction.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301 (c) (repair and
maintenance of existing street with no expansion of use) of the CEQA Guidelines,
California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a
significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Maps
9-3
ATTACHMENT A
a
BAYSIDE DR
� O
R
Z
_ m
m
LEGEND
Ll
BRIDGE
N07 TG SCALE
CITY BRIDGE DECK MAINTENANCE PROJECT
BALBOA ISLAND BRIDGE
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7679-2 1 09/13/22
m,
J
� � SoN PEE
a
o LEGEND
G
BRIDGE
NOT TO SCALE
CITY BRIDGE DECK MAINTENANCE PROJECT CITY OF NEWPORT BEACH
BISON AVE BRIDGE PUBLIC WORKS DEPARTMENT
LOCATION MAP C-7679-2 09/13/22
9-5
O
o
® v a
o � �
Q
0
d
o
o �
o
a
r7 BO,yirg 0 � o
mr giyy0"o
o
R
z
d
FORD RD
LEGEND
d BRIDGE
NOT TO SCALE
CITY BRIDGE DECK MAINTENANCE PROJECT
BONITA CANYON BRIDGE
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7679-2 1 09/13/22
CITY BRIDGE DECK MAINTENANCE PROJECT I CITY OF NEWPORT BEACH
JAMBOREE ROAD BRIDGE PUBLIC WORKS DEPARTMENT
LOCATION MAP I C-7679-2 1 09i1-3i22
9-7
N07 70 SCALr
CITY BRIDGE DECK MAINTENANCE PROJECT CITY OF NEWPORT BEACH
38TH STREET BRIDGE PUBLIC WORKS DEPARTMENT
LOCATION MAP I C-7679-2 1 09i1-3i22
ON