Residential Tract Plan Check Corrections
It is the responsibility of the applicant to satisfy the requirements (clearances) of each of the departments listed in this document.
Normally, each section will stamp your plans indicating their approval.
To view your plan check status and the latest correction list on the Internet, please visit: http://pdsd.oc.ca.gov and click on 'Plan
Check Status' Link
Project Number:RT040709
Submittal Date:Nov 17, 2004
CBC Edition: 2001
Plan Check Date: 12/1/2004 10:15 AM
Description:Single Family Residence
-Nautilus-build
out-tract 16407
Job Address
90 ARCHIPELAGO DR
NEWPORT COAST, CA
Owner Address
John Laing Luxury Homes
3121 Michelson Drive, Suite
200
Irvine CA92612
1st Plan Check 7/22/04 Current - 1st Recheck
Architect of Record
Robert Hidey Architects
7585 Irvine Center Drive
Ste. 200
Irvine CA92618
949-655-1550
Plan Checked By
Elie Nasr
Elie.Nasr@pdsd.ocgov.com
714-834-3473
714-796-8252 FAX
Contact Address
Bill Patterson
3 Hughes
Irvine CA92606
949-458-5429
949-465-1129 FAX
bpatterson@hunsaker.com
Building Name Construction Type Occupancy Stories Area Fire Requirement
Tract Home U-1,R-3 0 0 Automatic Fire Sprinkler
Page 1 of 5
RT040709
OBTAIN CLEARANCES (approval) from:
Current Planning/Zoning (714) 834-2626
DPC Station 1
Grading
Plan Check Review: (714) 834-5534
Inspection Div. (Rough Grade) (949) 472-7979
Fire Authority (714) 573-6100 (714)368-8843
1 Fire Authority Rd., Bldg. A, Irvine California 92606 (Jamboree@Tustin Ranch Rd.) OK
Acoustical Review (714) 834-2978
GENERAL INFORMATION
This correction list covers plan check of residential occupancies (R-1, R-3) and garage/carports only. Recreational
buildings, sales offices, retaining walls, etc. will require separate plan submittals to Commercial/Industrial
Plan Check Section for approval.
Application for which no permit is issued within 180 days following the date of application shall expire by limitation.
An extension of 180 days may be granted upon written request showing circumstances beyond the control of the applicant
have prevented action being taken. In order to renew action for an application after expiration, the applicant
shall resubmit plans and pay a new plan check fee. Sec. 107.4.
At building permit issuance, one (1) additional set of plans consisting of summary or title sheet, plot plan, floor
plans and elevations shall be required for the Assessor´s Office.
INFORMATION
ROUGH GRADING approval are required. NOTE: Building permit will not be issued until "Rough Grading" approval is
obtained from the grading inspector. Contact Grading Section for additional information.
Valid Worker´s Compensation Certificate or Owner-Builder Verification is required prior to issuance of building
permits.
Recheck by appointment only. Call your Plan Checker for recheck appointment. The correction list is available on
the Internet at http://pdsd.oc.ca.gov (Click on the services tab, then the Plan Check Processing link).
Provide will serve letters from the utility company for water and sewer service for tracts of single-family dwellings.
The applicant must submit three sets of plans to the Orange County Fire Authority directly. OCFA approval is required
on 3 sets of plans before any building permits can be issued.
The following residential projects require approval of the Orange County Fire Authority:
All apartments and condominiums.
All tracts of single-family dwellings.
Single Family dwellings with a floor area including the garage exceeding the 3,600 square feet or more than 50
feet from the street.
Projects with new fire sprinkler systems or with alterations to existing fire sprinkler systems.
Projects with new fire alarm systems or with alterations to existing fire alarm systems.
Page 2 of 5 12/1/2004 10:15 AM
RT040709
NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) NOTES
Notes must be shown as worded, on the title sheet of the plan
1. In the case of emergency, call___________________at Work Phone #___________________or Home Phone #_________
__________.
2. Sediment from areas disturbed by construction shall be retained on site using structural controls to the maximum
extent practicable.
3. Stockpiles of soil shall be properly contained to minimize sediment transport from the site to streets, drainage
facilities or adjacent properties via runoff, vehicle tacking, or wind.
4. Appropriate BMP's for construction-related materials, wastes, spills shall be implemented to minimize transport
from the site to streets, drainage facilities, or adjoining properties by wind or runoff.
5. Runoff from equipment and vehicle washing shall be contained at construction sites unless treated to reduce
or remove sediment and other pollutants.
6. All construction contractor and subcontractor personnel are to be made aware or the required best management
practices and good housekeeping measures for the project site and any associated construction staging areas.
7. At the end of each day of construction activity all construction debris and waste materials shall be collected
and properly disposed in trash or recycle bins.
8. Construction sites shall be maintained in such a condition that an anticipated storm does not carry wastes or
pollutants off the site. Discharges of material other than stormwater only when necessary for performance and
completion of construction practices and where they do not: cause or contribute to a violation of any water quality
standard; cause or threaten to cause pollution, contamination, or nuisance; or contain a hazardous substance in
a quantity reportable under Federal Regulations 40 CFR Parts 117 and 302.
9. Potential pollutants include but are not limited to: solid or liquid chemical spills; wastes from paints, stains,
sealants, glues, limes, pesticides, herbicides, wood preservatives and solvents; asbestos fibers, paint flakes
or stucco fragments; fuels, oils, lubricants, and hydraulic, radiator or battery fluids; fertilizers, vehicle/equipment
wash water and concrete wash water; concrete, detergent or floatable wastes; wastes from any engine/equipment
steam cleaning or chemical degreasing and superchlorinated potable water line flushing.
During construction, permittee shall dispose of such materials in a specified and controlled temporary area on
-site, physically separated from potential stormwater runoff, with ultimate disposal in accordance with local,
state and federal requirements.
10. Dewatering of contaminated groundwater, or discharging contaminated soils via surface erosion is prohibited.
Dewatering of non-contaminated groundwater requires a National Pollutant Discharge Elimination System Permit from
the respective State Regional Water Quality Control Board.
11. Graded areas on the permitted area perimeter must drain away from the face of slopes at the conclusion of each
working day. Drainage is to be directed toward desilting facilities.
12. The permittee and contractor shall be responsible and shall take necessary precautions to prevent public trespass
onto areas where impounded water creates a hazardous condition.
13. The permittee and contractor shall inspect the erosion control work and insure that the work is in accordance
with the approved plans.
14. The permittee shall notify all general contractors, subcontractors, material suppliers, lessees, and property
owners: that dumping of chemicals into the storm drain system or the watershed is prohibited.
15. Equipment and workers for emergency work shall be made available at all times during the rainy season. Necessary
materials shall be available on site and stockpiled at convenient locations to facilitate rapid construction of
temporary devices when rain is imminent.
16. All removable erosion protective devices shall be in place at the end of each working day when the 5-Day Rain
Probability Forecast exceeds 40%.
Page 3 of 5 12/1/2004 10:15 AM
RT040709
17. Sediments from areas disturbed by construction shall be retained on site using an effective combination of
erosion and sediment controls to the maximum extent practicable, and stockpiles of soil shall be properly containted
to minimize sediment transport from the site to streets, drainage facilities of adjacent properties via runoff,
vehicle tracking, or wind.
18. Appropriate BMPs for construction-related materials, wastes, spills or residues shall be implemented and retained
on site to minimize transport from the site to streets, drainage facilities, or adjoining property by wind or
runoff.
Page 4 of 5 12/1/2004 10:15 AM
RT040709
Residential Tract Plan Check Corrections
Sheet Comments By
General (Rpt)
S. Nargizianc0.1 In your responses, please refer to the alpha-numeric reference numbers that
are shown at the start of each of the following correction items.
S. Nargizianc5.2 Show on plot plan, precise grading plan or street improvement plan:
S. Nargizianc6.2.1 All required mitigation measures from the acoustical report.
NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM
E. Nasrc22.3 Please provide all mitigation and BMP details.