HomeMy WebLinkAboutRS061252_068t0000003ZSm0AAG_Correction ListCounty of Orange
Resources & Development Management Department
Building Permits Division
Main Office
300 N. Flower Street
Santa Ana, CA 92702-4048
Residential Plan Check Corrections
It is the responsibility of the applicant to satisfy the requirements (clearances) of each of the departments listed in this document.
Normally, each section will stamp your plans indicating their approval.
To view your plan check status and the latest correction list on the Internet, please visit: http://www.ocplanning.net and click on
'Plan Check Status' Link
Project Number:RS061252
Submittal Date:Jul 31, 2006
CBC Edition: 2001
Plan Check Date: 8/22/2006 9:55 AM
Description:Room Addition
Job Address
90 ARCHIPELAGO DR
NEWPORT COAST, CA
Owner Address
Joann Cohn
90 Archipelago
Newport Beach CA92657
Current - 1st Plan Check
Architect of Record
Zachary Sham Architect
2600 Newport Blvd
suite 154
Newport Beach CA92663
949-675-7322
HYE4USC@earthlink.net
Plan Checked By
Ken Higbee
ken.higbee@pdsd.ocgov.com
714-834-5960
Contact Address
Zachary Sham Architect
2600 Newport Blvd
suite 154
Newport Beach CA92663
949-675-7322
HYE4USC@earthlink.net
Page 1 of 6
RS061252
OBTAIN CLEARANCES (approvals) from:
School Fees
See attached school fee worksheet
Irvine Ranch Water District (949) 453-5300
Fire Authority
Becky Schade, (714) 573-6134
1 Fire Authority Road, Building A
(Jamboree @ Tustin Ranch Road)
Irvine, California 92606
GENERAL INFORMATION
This correction list covers plan check of residential occupancies (R-1, R-3) and garage/carports only. Recreational
buildings, sales offices, retaining walls, etc. will require separate plan submittals to Commercial/Industrial
Plan Check Section for approval.
Application for which no permit is issued within 180 days following the date of application shall expire by limitation.
An extension of 180 days may be granted upon written request showing circumstances beyond the control of the applicant
have prevented action being taken. In order to renew action for an application after expiration, the applicant
shall resubmit plans and pay a new plan check fee. Sec. 107.4.
Valid Worker´s Compensation Certificate or Owner-Builder Verification is required prior to issuance of building
permits.
The Structural or Civil Engineer or Architect responsible for this project shall sign three final sets of plans.
The third set is for the Assessor´s Office.
Plans cannot be rechecked at the counter. Resubmit and allow additional time for recheck.
The section Nos. and table Nos. called out in this correction list are from the 2001 California Building Code unless
noted otherwise.
Page 2 of 6 8/22/2006 9:55 AM
RS061252
NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) NOTES
Notes must be shown as worded, on the title sheet of the plan
1. In the case of emergency, call___________________at Work Phone #___________________or Home Phone #_________
__________.
2. Sediment from areas disturbed by construction shall be retained on site using structural controls to the maximum
extent practicable.
3. Stockpiles of soil shall be properly contained to minimize sediment transport from the site to streets, drainage
facilities or adjacent properties via runoff, vehicle tacking, or wind.
4. Appropriate BMP's for construction-related materials, wastes, spills shall be implemented to minimize transport
from the site to streets, drainage facilities, or adjoining properties by wind or runoff.
5. Runoff from equipment and vehicle washing shall be contained at construction sites unless treated to reduce
or remove sediment and other pollutants.
6. All construction contractor and subcontractor personnel are to be made aware or the required best management
practices and good housekeeping measures for the project site and any associated construction staging areas.
7. At the end of each day of construction activity all construction debris and waste materials shall be collected
and properly disposed in trash or recycle bins.
8. Construction sites shall be maintained in such a condition that an anticipated storm does not carry wastes or
pollutants off the site. Discharges of material other than stormwater only when necessary for performance and
completion of construction practices and where they do not: cause or contribute to a violation of any water quality
standard; cause or threaten to cause pollution, contamination, or nuisance; or contain a hazardous substance in
a quantity reportable under Federal Regulations 40 CFR Parts 117 and 302.
9. Potential pollutants include but are not limited to: solid or liquid chemical spills; wastes from paints, stains,
sealants, glues, limes, pesticides, herbicides, wood preservatives and solvents; asbestos fibers, paint flakes
or stucco fragments; fuels, oils, lubricants, and hydraulic, radiator or battery fluids; fertilizers, vehicle/equipment
wash water and concrete wash water; concrete, detergent or floatable wastes; wastes from any engine/equipment
steam cleaning or chemical degreasing and superchlorinated potable water line flushing.
During construction, permittee shall dispose of such materials in a specified and controlled temporary area on
-site, physically separated from potential stormwater runoff, with ultimate disposal in accordance with local,
state and federal requirements.
10. Dewatering of contaminated groundwater, or discharging contaminated soils via surface erosion is prohibited.
Dewatering of non-contaminated groundwater requires a National Pollutant Discharge Elimination System Permit from
the respective State Regional Water Quality Control Board.
11. Graded areas on the permitted area perimeter must drain away from the face of slopes at the conclusion of each
working day. Drainage is to be directed toward desilting facilities.
12. The permittee and contractor shall be responsible and shall take necessary precautions to prevent public trespass
onto areas where impounded water creates a hazardous condition.
13. The permittee and contractor shall inspect the erosion control work and insure that the work is in accordance
with the approved plans.
14. The permittee shall notify all general contractors, subcontractors, material suppliers, lessees, and property
owners: that dumping of chemicals into the storm drain system or the watershed is prohibited.
15. Equipment and workers for emergency work shall be made available at all times during the rainy season. Necessary
materials shall be available on site and stockpiled at convenient locations to facilitate rapid construction of
temporary devices when rain is imminent.
16. All removable erosion protective devices shall be in place at the end of each working day when the 5-Day Rain
Probability Forecast exceeds 40%.
Page 3 of 6 8/22/2006 9:55 AM
RS061252
17. Sediments from areas disturbed by construction shall be retained on site using an effective combination of
erosion and sediment controls to the maximum extent practicable, and stockpiles of soil shall be properly containted
to minimize sediment transport from the site to streets, drainage facilities of adjacent properties via runoff,
vehicle tracking, or wind.
18. Appropriate BMPs for construction-related materials, wastes, spills or residues shall be implemented and retained
on site to minimize transport from the site to streets, drainage facilities, or adjoining property by wind or
runoff.
Page 4 of 6 8/22/2006 9:55 AM
RS061252
Residential Plan Check Corrections
Sheet Comments By
General
K. Higbeec0.1 In your responses, please refer to the alpha-numeric reference numbers that
are shown at the start of each of the following correction items.
K. Higbeec6.2 Note on Plans:
K. Higbeec7.2.1 Occupancy group, construction type.
K. Higbeec8.2.2 Assessor´s parcel number.
K. Higbeec5.3 Plans for single-family dwellings and duplexes are not checked for plumbing,
mechanical and electrical code compliance. These disciplines are subject to field
inspection.
K. Higbeec9.4 See red notes on your plans for clarification of corrections or comments, and
for additional corrections.
K. Higbeec15.5 Place Form 00-01 to be completed by the architect, engineer or owner on the
1st sheet of plans (the site plan). If no special inspection and/or structural observation
are required, the architect or engineer needs to include a note on the Site Plan
to indicate that it is not required.
NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM
K. Higbeec11.6 Include "National Pollutant Discharge Elimination System Notes" on first sheet
of plans. (This information is provided in the beginning of this document)
K. Higbeec12.7 Provide Erosion and Sediment Control (ESCP) plan.
Plot Plan
K. Higbeec14.8 Show drainage of the site and disposal point on your site plan. Reference
RDMD standard plan 1320.
Roof
K. Higbeec17.9 All new buildings and additions within the Special Fire Protection Areas shall
have a Class A roof covering. All other new building roofing shall have minimum
Class B. Clarify. O.C. Building Ordinance No. 03-003.
K. Higbeec18.10 The unincorporated area of the County is considered to be a "Special Wind
Region." All roof fasteners shall be installed per manufacturer´s instructions.
Call out fasteners to resist wind loads for winds over 80 mph. O.C. Bldg. Ord. No.
03-003.
Page 5 of 6 8/22/2006 9:55 AM = Indicates line item not Cleared.
RS061252
Residential Plan Check Corrections
Sheet Comments By
Wind and Earthquake Design
K. Higbeec20.11 Show the length of each shear wall.
Page 6 of 6 8/22/2006 9:55 AM = Indicates line item not Cleared.