HomeMy WebLinkAbout05 - Central Library Boiler and Civic Center Hot Water Heater Replacement Project (Project No. 22F02) — NOC for Contract No. 8730-1Q �EwPpRT
CITY OF
s NEWPORT BEACH
`q44:09 City Council Staff Report
October 25, 2022
Agenda Item No. 5
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer,
tandefur@newportbeachca.gov
PHONE: 949-644-3321
TITLE: Central Library Boiler and Civic Center Hot Water Heater
Replacement Project (Project No. 221`02) — Notice of Completion for
Contract No. 8730-1
ABSTRACT:
On March 22, 2022, the City Council awarded Contract No. 8730-1, Central Library Boiler
and Civic Center Hot Water Heater Replacement Project, to F.M. Thomas Air
Conditioning, Inc. (F.M. Thomas) of Brea, California. This project replaced the existing
boiler and hot water heater at the Central Library and Civic Center, respectively. The work
is now substantially complete and staff requests City Council acceptance and closeout of
the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after Notice
of Completion has been recorded in accordance with applicable portions of the Civil
Code; and
c) Release the Faithful Performance Bond one year after acceptance by the City Council.
DISCUSSION:
Overall Contract Cost/Time Summary
Award Contract
Final Cost at
Total Contract
Percent Contract
Amount
Completion
Change Amount
Cost Change
$ 171,176.00
$ 183,880.39
$ 12,704.39
7.4%
Allowed Contract Time (days)
162
Actual Time
-8
Under (-) or Over (+)
5-1
Central Library Boiler and Civic Center Hot Water Heater Replacement Project
(Project No. 22F02) — Notice of Completion for Contract No. 8730-1
October 25, 2022
Page 2
The work necessary for the completion of this contract consisted of removing and
replacing the existing Central Library (1000 Avocado Avenue) boiler and the existing Civic
Center (100 Civic Center Drive) hot water heater, which were both at the end of their
service lives and were showing signs of failure. The scope also included installing seismic
anchorage and reusing existing electrical circuits. The replacement equipment meets the
current 2019 California Title 24 Energy code requirements. The project also included one
change order to add an in -line filter in order to reduce the amount of sediment deposits in
the new boiler.
The contract has been completed to the satisfaction of the Public Works Department and
the Library Services Department. A summary of the construction cost is as follows:
Original Bid Amount:
Actual Cost of Bid Items Constructed:
Total Change Orders:
Final Contract Cost:
A summary of the project schedule is as follows:
Estimate Start of Construction per Annual Baseline Schedule
Actual Issuance of Notice to Procure
Actual Start of Construction per Notice to Proceed
Actual Substantial Construction Completion Date
FISCAL IMPACT:
$ 171,176.00
$ 171,176.00
$ 12,704.39
$ 183,880.39
May 11, 2022
April 28, 2022
May 11, 2022
Sept. 28, 2022
The Central Library Boiler and Civic Center Hot Water Heater Replacement Project was
included within the FY 2021-22 CIP Budget. Funds for the construction contract were
expended from the following account:
Account Description Account Number Amount
Facilities Maintenance Master Plan 57101-980000-20F02 $ 183,880.39
Total: $ 183,880.39
The Facilities Maintenance Master Plan (FMMP) includes a comprehensive condition
assessment of all City of Newport Beach (City) facilities and prioritizes capital repairs
and/or major maintenance based on a variety of factors including current condition and
age of facilities. This program funds a variety of capital repair and maintenance projects
in an effort to keep City facilities is good condition.
ENVIRONMENTAL REVIEW:
On March 22, 2022, City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301 Class 1 (maintenance of
existing public mechanical equipment) of the CEQA Guidelines, California Code of
Regulations, Title 14, Chapter 3, because this project has no potential to have a significant
effect on the environment.
5-2
Central Library Boiler and Civic Center Hot Water Heater Replacement Project
(Project No. 22F02) — Notice of Completion for Contract No. 8730-1
October 25, 2022
Page 3
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
5-3
Attachment A
JOHN WAYNE
AIRPORT
NOT TO SCALI
CENTRAL LIBRARY BOILER & CIVIC CITY OF NEWPORT BEACH
CENTER HOT WATER HEATER PUBLIC WORKS DEPARTMENT
REPLACEMENT PROJECT
LOCATION MAP I C-8730-1 I 10/25122