Agenda Item No. 5
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer,
tandefur@newportbeachca.gov
PHONE: 949-644-3321
TITLE: Civic Center Dog Park Refurbishment (Project No. 22P12) — Notice
of Completion for Contract No. 8717-1
ABSTRACT:
On February 8, 2022, the City Council awarded Contract No. 8717-1, Civic Center Dog
Park Refurbishment, to Western State Builders, Inc. (WSB) of Escondido, California. This
project replaced the worn-out synthetic turf, drinking water fountains, and fence
screening, repainted fencing and signage, repaired uplifted sidewalk, and added two new
shade structures for the small dog park users. The work is now complete and staff
requests City Council acceptance and closeout of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after Notice
of Completion has been recorded in accordance with applicable portions of the Civil
Code -land
c) Release the Faithful Performance Bond one year after acceptance by the City Council.
DISCUSSION:
Overall Contract Cost/Time Summary
Award Contract
Final Cost at
Total Contract
Percent Contract
Amount
Completion
Change Amount
Cost Change
$ 241,036.26
$ 240,868.51
- $ 167.75
- 0.1 %
Allowed Contract Time (days)
30
Actual Time
1
Under (-) or Over (+)
5-1
Civic Center Dog Park Refurbishment (Project No. 22P12) —
Notice of Completion for Contract No. 8717-1
December 13, 2022
Page 2
The work necessary for the completion of this contract consisted of replacing the
worn-out synthetic turf, drinking water fountains, and fence screening; repainting fencing
and signage; repairing uplifted sidewalk; and installing two new shade structures for the
small dog park users.
The contract has been completed to the satisfaction of the Public Works Department and
the Recreation and Senior Services Department. A summary of the construction cost is
as follows:
Original Bid Amount:
$
241,036.26
Actual Cost of Bid Items Constructed:
$
237,036.26
Total Change Orders:
$
3,832.25
Final Contract Cost:
$
240,868.51
The -0.1 % contract cost change is due to a reduced drinking fountain unit cost and two
change orders issued for the project. The contractor was able to reuse the existing
drinking fountain foundations thereby reducing the concrete and labor costs for this
scope. The two change orders issued were for replacing additional concrete panels,
polishing benches, replacing broken drinking water fountain valves, and issuing additional
working days due to unforeseen field conditions.
A summary of the project schedule is as follows:
Estimate Start of Construction per Annual Baseline Schedule August 1, 2022
Actual Issuance of Notice to Procure April 11, 2022
Actual Start of Construction per Notice to Proceed October 3, 2022
Actual Substantial Construction Completion Date November 14, 2022
FISCAL IMPACT:
The Civic Center Dog Park Refurbishment Project was included within the FY 2021-22
Capital Improvement Program (CIP) Budget. Funds for the construction contract were
expended from the following account:
Account Description
General Fund - CIP
ENVIRONMENTAL REVIEW:
Account Number
01201929-980000-22 P 12
Total
Amount
$ 240,868.51
$ 240,868.51
On February 8, 2022, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301 Class 1 (maintenance of
existing public facilities) of the CEQA Guidelines, California Code of Regulations, Title 14,
Chapter 3, because it has no potential to have a significant effect on the environment.
5-2
Civic Center Dog Park Refurbishment (Project No. 22P12) —
Notice of Completion for Contract No. 8717-1
December 13, 2022
Page 3
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
5-3
Attachment P
Q
( >
0
41 cc
0
17TH Sl LCL'
15TH S
CITY OF COSTA
MESA
BALBOA
Y
JOHN WAYNE
AIRPORT
FF J�
�P
CITY OF
P
IRVINE
`P
UPPER o
P�
Q
NEBPORT YL � �
NNIVERSITY
a
A,gCoFjC '0//o"T
ocz- q of
OPROJECT LOCATIONS
CIVIC CENTER DOG PARK
N
HILL
Fqs
P T
VICINITY MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
NOT TO SCALE
CIVIC CENTER DOG PARK
REFURBISHMENT
LOCATION MAP
FREEwq Y
0
C-8717-1 1 12/13/22
5-4