HomeMy WebLinkAbout08 - Assessment District No. 111 and Underground Utilities District No. 22 Phases 2 & 3, Contract No. 7833-1 (21A11) — Request for Additional ContingencyQ SEW Pp�T
CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
December 13, 2022
Agenda Item No. 8
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Michael J. Sinacori, Assistant City Engineer
msinacori@newportbeachca.gov
PHONE: 949-644-3342
TITLE: Assessment District No. 111 and Underground Utilities District
No. 22 Phases 2 & 3, Contract No. 7833-1 (21A11) — Request for
Additional Contingency and Approval of Budget Amendment
ABSTRACT:
On August 25, 2020, the City Council awarded a construction contract for the
Underground Utilities Assessment District (AD) No. 111 and Underground Utilities District
(UUD) No. 22 - Phase 2 & 3 project. The base project was substantially complete in
November 2021. Additional construction efforts were requested and funded by two of the
project's communication companies to extend their fiber optics systems further down the
Peninsula and ahead of the City of Newport Beach's (City's) improvement projects on
Balboa Boulevard. These same communication companies are now requesting further
extensions of their systems to complete their fiber optics networks to Peninsula Point
ahead of the recently awarded Balboa Boulevard Pavement Rehabilitation project
between Medina Way and G Street.
RECOMMENDATION:
a) On November 10, 2015, the City Council deemed this project exempt from the
California Environmental Quality Act (CEQA) pursuant to Class 2 Section 15302 (d)
(conversion of overhead electrical utility distribution lines where the surface is restored
to the condition existing prior to the undergrounding) of the CEQA Guidelines,
California Code of Regulations, Title 14, Chapter 3, because it will not have an adverse
effect on the environment. The exemption was posted and recorded at the County of
Orange on November 20, 2015;
b) Authorize staff to proceed with the additional work and increase project contingency
from $1,742,000 (approximately 25 percent of the contract award of $6,969,777.79)
to $3,500,000 (approximately 50 percent of the contract award) to cover the additional
cost of requested additional work; and
c) Approve Budget Amendment No. 23-042 recognizing $2,504,229.75 in contribution
revenue funding from multiple utility companies in Account No. 13501-561007-21A11
and appropriating $2,504,229.75 in increased expenditures in Account No. 13501-
980000-21 A11.
RX
Assessment District No. 111 and Underground Utilities District No. 22 Phases 2 & 3,
Contract No. 7833-1 (21A11) - Request for Additional Contingency
and Approval of Budget Amendment
December 13, 2022
Page 2
DISCUSSION:
On August 25, 2020, the City Council awarded Contract No. 7833-1 in the amount of
$6,969,777.79 to Asplundh Construction Corp. (Asplundh) for the construction of
AD No. 111 (AD 111) and UUD No. 22 Phase 2 & 3 (UUD22) and authorized
approximately 10 percent ($700,000) in contingency funds to cover the cost of unforeseen
work. The project includes the partners of Southern California Edison (SCE), AT&T,
Spectrum, Crown Castle, ExteNet Systems and MCI Business for the UUD22 Phase 2
work on Balboa Boulevard. Each company was charged an additional 5 percent of their
construction dollar amounts for City administration of the project.
In June 2021, ExteNet Systems and MCI Business (both Verizon subsidiaries) requested
additional work to continue their efforts along the Peninsula for the small cell system and
backbone fiber optics networks that these two companies are completing as part of the
Asplundh contract. The small cell system has required extensive staff time to review
construction drawings and cell site locations as part of the previously approved
agreement with Verizon in 2018. This joint review effort between the Community
Development, Public Works and Utilities Departments has been ongoing for four years.
In an effort to reduce staff permitting and review efforts, and to better coordinate with
other UUD22 project work in the area, an additional $1,467,829.19 of ExteNet and MCI
Business funded improvements have now been installed. This has brought the total
Asplundh contract, together with an additional contingency of $275,652.27, to
$8,713,259.25 (approximately 25 percent above base). The additional
telecommunications work was paid for in advance by the utilities and included a higher
City administration fee of 10 percent as the coordination of this effort was more
complicated than the base bid administration and only included these two companies.
The system has been extended and is now operational to Balboa Boulevard and Medina
Way intersection.
ExteNet Systems and MCI Business are pleased with the City's administration of their
construction efforts. There is also the added City benefit of reducing community impacts
by coordinating other City projects with their requested extension efforts. In addition,
there is reduced permit and inspection efforts by jointly assisting both companies rather
than if they proceeded independently.
On November 29, 2022, the City Council awarded a construction contract to All American
Asphalt for the rehabilitation of Balboa Boulevard from Medina Way to
G Street and Newport Coast Drive from Coast Highway to Ridge Park Road. To avoid
community impacts of two separate independent communication construction projects at
a future date (after the road has been paved), ExteNet and MCI Business have again
requested to fund and jointly extend their fiber optics system through the use of the City's
underground contractor (Asplundh). The project would include extension of the fiber
optics systems on Balboa Boulevard from Medina Way through Peninsula Point on Ocean
Boulevard to the Wedge. It would also include fiber optics to the recently installed Micro
Cell tower at the Balboa Pier. The extension would be coordinated with City's paving
rehabilitation efforts to minimize impacts to the community.
FIN
Assessment District No. 111 and Underground Utilities District No. 22 Phases 2 & 3,
Contract No. 7833-1 (21A11) - Request for Additional Contingency
and Approval of Budget Amendment
December 13, 2022
Page 3
Also included in this extra work will be power upgrades to several micro cell towers
already installed and operational. The existing power provided from the City's street light
system is proving problematic and Verizon has requested the power upgrades to be
included in this requested fiber optics extension work.
Staff believes allowing Asplundh to complete this additional fiber optics work requested
and funded by the utility companies will best accomplish the desired goal of installation
of the small cell system approved by the 2018 agreement with Verizon while minimizing
the impacts to the community.
FISCAL IMPACT:
Upon approval of the proposed budget amendment, sufficient funding will be available to
complete the requested work for ExteNet, MCI Business and Verizon Small Cell. These
communication companies were required on previous phases of the project to deposit
funds ahead of construction and is the same case with this requested work. A summary
of the overall final funding anticipated for the construction contract at completion is as
follows (not including administration fees):
Resident Self -Assessments via AD 111 $2,471,426.41
Contributions from Utility Companies $8,020,547.69
Public Works Department Operating Budget $17,965.20
Total $10,509,939.30
The resident self -assessment funds were previously appropriated when AD 111 was
approved by the residents and City Council on January 12, 2016 and included in the
adopted FY 2020-21 Capital Improvement Program (CIP) budget. Residents had until
April 30, 2020 to pay any portion or all of their assessments. The balance of the
assessments was funded by a bond sale approved by City Council on June 23, 2020,
closed on June 26, 2020, and paid for solely by the residents.
The additional contributions from utility companies are included in the proposed budget
amendment and recognizes a total of $8,741,649.34 in contribution revenue, for the
construction contract and $721,101.65 in City administration fees, from various utility
companies and appropriates $2,504,229.75 in increased expenditures for the utility
companies' share of the project. For this last remaining work, invoices have been sent to
the three companies, which included a 10 percent City administration charge. Most funds
have been received and any change order work required for this extension would be billed
to the various companies at the time of work. Verizon Small Cell was billed an additional
ten percent for potential change order work and will be issued a refund if not spent.
FIN
Assessment District No. 111 and Underground Utilities District No. 22 Phases 2 & 3,
Contract No. 7833-1 (21A11) - Request for Additional Contingency
and Approval of Budget Amendment
December 13, 2022
Page 4
ENVIRONMENTAL REVIEW:
On November 10, 2015, the City Council deemed this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Class 2 Section 15302 (d) (conversion of
overhead electrical utility distribution lines where the surface is restored to the condition
existing prior to the undergrounding) of the CEQA Guidelines, California Code of
Regulations, Title 14, Chapter 3, because it will not have an adverse effect on the
environment. The exemption was posted and recorded at the County of Orange on
November 20, 2015.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
Attachment B —Completed and Proposed Fiber Optics Extension Map
Attachment C — Budget Amendment No. 23-042
ATTACHMENT A
0
m
0
H
ASSESSMENT DISTRICT 111, UNDERGROUND
UTILITY DISTRICT 22 - PHASES 2 (BALBOA) & 3
LOCATION MAP
STREET
2
-1
7-
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7833-1 8/25/20
8-5
ATTACHMENT B
PACIFIC
OCEAN
Attachment C
Budget Amendment No. 23-042
RIM
e �EwP�kT
City of Newport Beach
BUDGET AMENDMENT
qC/FOF'\P 2022-23 BA#: 23-042
Department: Public Works
ONE TIME: ❑ Yes ❑ No
Requestor: Theresa Schweitzer
Approvals
❑ CITY MANAGER'S APPROVAL ONLY
Finance Director: Date 11a3 2?i
COUNCIL APPROVAL REQUIRED City Clerk: Date
EXPLANATION FOR REQUEST:
Request approval of recognizing additional revenue and appropriating expenses as it relates to Assessment District No. ❑ from existing budget appropriations
111 and Underground Utilities District No. 22 Phases 2 &3, Contract No. 7833-1 (21A11) ❑ from additional estimated revenues
❑ from unappropriated fund balance
REVENUES
Fund #
Org
Object
Project
Description
Increase or (Decrease) $
135
13501
561007
21A11
CONTRIBUTIONS FUND CIP - 20A CONTRIBUTIONS
2,504,229.75
Subtotal $ 2,504,229.75I
EXPENDITURES
Fund #
Org
Object
Project
Description
Increase or (Decrease) $
135
13501
980000
21A11
CONTRIBUTIONS FUND CIP - CIP EXPENDITURES FOR GL 2,504,229.75
Subtotal $ 2,504,229.75
FUND BALANCE
Fund #
Object
Description
Increase or (Decrease) $
13S
300000
CONTRIBUTIONS FUND - FUND BALANCE CONTROL
Subtotal, $
No Change In Fund Balance
: :