HomeMy WebLinkAboutPA2022-0222_20221007_Bulkhead Conditions Report dated 09-28-22
P M A C O N S U L T I N G , I N C .
CONSULTING STRUCTURAL ENGINEERS
28161 Casitas Ct. PH. (714) 717-7542
Laguna Niguel, CA 92677
e-mail: consulting@pma-bg.com
September 28, 2022
Elizabeth Hanna
Brandon Architects
151 Kalmus Drive Unit G-1
Costa Mesa, CA 92626
BULKHEAD CONDITIONS REPORT
Jim and Angela Gates; Applicant
748 Via Lido Nord
City of Newport Beach, County of Orange
PMA Job #49722
Dear Ms. Hanna,
PMA Consulting, Inc. is pleased to provide this report in accordance with Section
21.30.15.E.3 of City of Newport Beach Municipal Code.
STATEMENT OF THE PREPARER’S QUALIFICATIONS
Plamen Petrov, P.E., the preparer of this report, holds a Master of Science in Structural
Engineering from University of Architecture, Structural Engineering & Geodesy of Sofia, Bulgaria,
and is a Licensed Civil Engineer by the State of California Certificate No. C66947. For the last 22
years of his professional career, he has been actively involved in the design and entitlement of
many Waterfront Developments such as custom homes, seawalls, piers, platforms, floating docks
and marinas. A great number of Bulkhead Condition Reports prepared by him have been reviewed
and accepted/approved by California Coastal Commission.
All the above being said, Plamen Petrov, P.E. shall be considered a qualified preparer for
the Bulkhead Conditions Report on this project.
OBSERVATION
A cursory observation of the existing seawall/bulkhead was conducted by a representative
of our office on August 22, 2022. Observed was the visible/exposed portion of the waterfront face
of the seawall. Due to the site conditions, tie-backs were not accessible, thus not observed.
FINDINGS
The pre-cast jetted-in concrete panels and cast-in-place concrete coping of the seawall were
found in generally good condition, without noticeable evidence of distress. Some minor cracks
were observed, which is a typical condition for many of the seawalls of this vintage in the area.
1PA2022-0222
CONCLUSION
Based on our site observation, we conclude that the existing seawall is required to protect
the proposed principal structure on the lot. To be able to do so, the seawall shall be
repaired/reinforced/raised as reflected on the enclosed Drawings SW-0 thru SW-2. Once the
seawall is reinforced in accordance with the enclosed drawings, no repair or replacement of the
seawall shall be anticipated in the next 75. If during this period though, the seawall displays any
sign of distress that requires immediate attention, it should be repaired or replaced at that time
accordingly, without seaward encroachment from its current location.
The above conclusion was prepared based on the existing conditions, proposed drawings,
and within the inherent limitations of this study, in accordance with generally acceptable
engineering principles and practices. We make no further warranty, either expressed or implied.
PMA Consulting, Inc. appreciates the opportunity to work with you towards the successful
completion of your project. Should you have any questions regarding this report, please give us a
call.
Respectfully submitted,
Plamen Petrov, P.E.
Principal
Enclosures:
Seawall Drawings SW-0 thru SW-2
2PA2022-0222
3PA2022-0222
4PA2022-0222
5PA2022-0222