HomeMy WebLinkAboutPA2022-034_20230320_NOE_Big Canyon Habitat Restoration - Phase 3_posted on 01-26-2023CITY OF NEWPORT BEACH
100 CIVIC CENTER DR PO BOX 1768
NEWPORT BEACH. CA 92658-8915
HUGH NGUYEN
CLERK-RECORDER
RECEIVED BY
COMMUNllY
DEVELOPMENT
MAR 2 0 2023
CITYOf
NEWPORT BEACH
Office of the Orange County Clerk-Recorder
Memorandum
SUBJECT: NOTICE OF EXEMPTION
The attached notice was received. filed and a copy was posted on 01/26/2023
It remained posted for 30 (thirty) days.
Hugh Nguyen
Clerk -Recorder
In and for the County of Orange
By: Claudia L Franco Gutien-ez Deputy
Public Resource Code 21092.3
BIRTH AND DEATH RECORDS
FICTITIOUS BUSINESS NAMES
MARRIAGE LICENSES/RECORDS
NOTARY REGISTRATION
ORANGE COUNTY ARCHIVES
PASSPORTS
PROPERTY RECORDS
The notice required pursuant to Sections 21080.4 and 21092 for an environmental impact report shall be posted in
the office of the County Clerk of each county *** in which the project will be located and shall remain posted for
a period of 30 days. The notice required pursuant to Section 21092 for a negative declaration shall be so posted
for a period of 20 days, unless otherwise required by law to be posted for 30 days. The County Clerk shall post
notices within 24 hours of receipt.
Public Resource Code 21152
All notices filed pursuant to this section shall be available for public inspection. and shall be posted *** within 24
hours of receipt in the office of the County Clerk. Each notice shall remain posted for a period of 30 days.
•••Thereafter.the clerk shall return the notice to the local lead agency••• within a notation of the period it was
posted. The local lead agency shall retain the notice for not less than nine months.
Additions or changes by underline; deletions by***
(714) 834-2500 ♦ FAX: (714) 834-2675 ♦ OCRECORDER.COM ♦ OCARCHIVES.COM
PA2022-034
State of California -Department of Fish and Wildlife
202:\ ENVIRONMENTAL DOCUMENT FILING FEE
CASH RECEIPT
DFW 753.5a (REV. 01101/22) Previously DFG 753.5a
SEE INSTRUCTIONS ON REVERSE. TYPE OR PRINT CLEARLY.
LEAD AGENCY I LEAD AGENCY EMAIL
CITY OF NEWPORT BEACH
COUNTY/STATE AGENCY OF FILING
!orange G
PROJECT TITLE
BIG CANYON HABITAT RESTORATION-PHASE 3
Print I 159; I Save
RECEIPT NUMBER
30 -01/26/2023 -0060
STATE CLEARINGHOUSE NUMBER (If applicable)
DATE
01/26/2023
DOCUMENT NUMBER
202385000064
PROJECT APPLICANT NAME PROJECT APPLICANT EMAIL PHONE NUMBER
CITY OF NEWPORT BEACH
PROJECT APPLICANT ADDRESS CITY
100 CIVIC CENTER DRIVE NEWPORT BEACH
PROJECT APPLICANT (Check appropriate box)
~ Local Public Agency D School District D Other Special District
CHECK APPLICABLE FEES:
D Environmental Impact Report (EIR)
D Mitigated/Negative Declaration (MND)(ND)
D Certified Regulatory Program (CRP) document -payment due directly to CDFW
~ Exempt from fee
0 Notice of Exemption (attach)
D CDFW No Effect Determination (attach)
D Fee previously paid (attach previously issued cash receipt copy)
D Water Right Application or Petition Fee (Stale Water Resources Control Board only)
D County documentary handling fee
D Other
PAYMENT METHOD:
(949) 644-3200
STATE ZIP CODE
CA 92658
D State Agency 0 Private Entity
$3,839.25
$2,764.00
$1,203.25
$850.00 $
$
$
$ 0.00 ----------
$ 0.00 -----------
$ 0.00 -----------
0.00
0.00
D Cash D Credit 0 Check D Other TOT AL RECEIVED $ 0.00
SIGNATURE AGENCY OF FILING PRINTED NAME AND TITLE
X DEPUTY CLERK, CLAUDIA FRANCO
ORIGINAL -PROJECT APPLICANT COPY -CDFW/ASB COPY -LEAD AGENCY COPY -COUNTY CLERK DFW 753.5a {Rev. 01012022)
PA2022-034
~ 8
' l\Q
~
POSTED
JAN 2 6 2023
Recorded in Official Records, Orange County
Hugh Nguyen, Clerk-Recorder
I IIIII I l llllll Ill lllll lllll lllll lllll lllll lllll lllll 11111111111111111111111 N ° FEE * $ R O O 1 4 1 7 1 1 1 6 $ *
ORANGECOUNTYCLER REC RDERDEPARTIIIE,ljr 202385000064 11 :26 am 01/26/23
BY: ____ -\:,,,__ ___ DEP
Notice of Exemption
To:
County Clerk
County of Orange
Public Services Division
Santa Ana, CA 92702
Project Title: Big Canyon Habitat Restoration -Phase 3
383 Vitlndx 201
0.00 50.00 0.00 0.00 0.00 0.00 0.00 0.00
From:
City of Newport Planning Division
100 Civic Center Drive P.O. Box 1768
Newport Beach, CA 92658-8915
(949) 644-3200
Project Applicant: City of Newport Beach, 100 Civic Center Drive, Newport Beach, CA 92660
Attention: Makana Nova, Senior Planner
Project Location -Specific: 1950 Back Bay Drive, Newport Beach, CA 92660
Project Location -City: Newport Beach Projecl Location -County: Orange
Description of Nature, Purpose and Beneficiaries of Project: The Big Canyon Habitat Restoration -Phase 3
("Project") area measures approximately 14.3 acres of the larger 60-acre Big Canyon Nature Park. The Project's
scope is the last phase in this ongoing restoration effort of Big Canyon Nature Park. The Project involves removing
the existing selenium impacted salt-water lake, eliminating inv;isive plants, and re-gr;iding the site. The proposed
grading will ext end saltwater influence from the Back Bay into the Phase 3 site; the area will then be replanted with
nat ive plants to restore riparian and upland habitats. The Project restores historical salt marsh and establishes
transitional wetlands that will allow for upslope migration and resiliency t o long-term sea level rise (SLR). ~ ';i-~ The Project will further reduce selenium bioavailability found naturally within marine deposits in the watershed, 'S--maintain positive drainage during low flows, and address mosquito breeding habitat. The City will also incorporate
0 fuel modification on the surrounding sloping parcels the City owns as part of the project scope to reduce fire risks to
I nearby homes.
~ Name of Public Agency Approving Project: City of Newport Beach
Name of Person or Agency Carrying out Project: Newport Bay Conservancy, City of Newport Beach, and
Ca lifornia Department of Fish & Wildlife
Exempt Status: (check one):
D Ministerial (Sec. 21080(b)(1); 15268); D Declared Emergency (Sec. 21080(b)(3); 15269(a));
D Emergency Project (Sec. 21080(b)(4); 15269(b)(c));
D Categorical Exemption. State type and section number: __
~ Statutory Exemptions. State code number: 21080.56
FILED
JAN 2 6 2023
DER DEPARTMENT
Reasons why project is exempt: In accordance with Public Resources Code Section 21080.56, subsection(e), the
project meets all the qualifying criteria in subdivisions (a) to (d), inclusive. The City of Newport Beach has
determined that this Project will both (1) conserve, restore, protect, or enhance, and assist in the recovery of
California native fish and w ildlife, and the habitat upon which they depend and (2) restore or provide habitat for
California native fish and wildlife. The project proposes to replace existing degraded habitat by restoring historic salt
marsh and freshwater/riparian habitat. Salt marsh was filled in the 1950-60s as a result of dredged material
placement in Big Canyon. By restoring salt marsh habitat , this will provide habitat for a variety of California wildlife
that utilize this habit at. Upland Coastal Sage Scrub habitat enhance ment will benefit the coastal California
gnatcatcher (Polioptila californica californica), song sparrow (Melospiza melodia), California towhee (Melozone
crissalis) and the wrentit (Chamaea fasciata), to name a few.
PA2022-034
Big Ca~yon Nature Park is used by residents and visitors for passive recreation. This is an important destination for
thousands of children participating in the Orange County Department of Education Inside the Outdoors program.
Inside the Outdoors provides watershed educational activities for grade school children throughout the county
including disadvantage communities. As the largest undeveloped canyon adjacent to Newport Bay, it has the
potential to become an integral part of the Upper Newport Bay State Ecological Preserve and to provide unique
opportunities for the public to learn about the diversity of biological resources and environmental protection within
a short walking distance. Along with the restoration of a mosaic of coastal riparian, alkaline marsh, salt marsh,
transitional habitat and coastal sage scrub, the existing and planned construction and operation and maintenance
roads will provide incidental public benefits serving an ancillary function as trails around the perimeter of the
restoration that will provide an enhanced experience of the different ecotones in a coastal watershed.
The City has obtained a concurrence letter from the Director of CDFW that the exemption applies to the Project, in
accordance with Section 21080.S6(e), see attached.
Lead Agency
Contact Person/Title:Makana Nova, Senior Planner Contact Phone No./Ext: 949-644-3249
If filed by applicant:
1. Attach certified document of exemption finding.
2. Has a Notice of Exemption been filed by the public agency approving the project? □Yes D No .-::--· .
Signature: --\~V\_{7\__~ Title: Senior Planner Date: 01-25-2023
[8JSigned by Lead Agency D Signed by Applicant
Authority cited: Sectio;;s 21 083 and 21110, Public Resources Code.
Reference: Sections 21108, 21152, and 21152.1, Public Resources Code.
FILED
JAN 2 6 2023
ORANGE COUNTY CLERK
04104/2019
POSTED
JAN 2 6 2023
ORANGE COUNTY CLERK-RECORDER DEPARTMENT
BY: fJ(/ DEPUTY
PA2022-034
§tate of California -Natural Resources Agency
. Df:PARTMENT OF FISH AND WILDLIFE
Dirf:\ctor's Office
Post Office Box 944209
Sacramento, CA 94244-2090
www.wildlife.ca.gov
May 4, 2022
Makana Nova, Senior Planner
Planning Division
Community Development Department
City of Newport Beach
100 Civic Center Drive
Newport Beach, CA 92660
GAVIN NEWSOM. Governor ~
CHARLTON H. BONHAM, Director •
POSTED
JAN 2 6 2023
ORANGE COUNTY CLER~K· CORDER DEPARTMENT
------fj,"/~ __ DEPUTY BY:
California Environmental Quality Act Statutory Exemption for Restoration Projects,
Big Canyon Coastal Habitat Restoration and Resiliency Project -Phase 3 (Request
No. 21080.56-2022-003-RS)
Dear rvls. Nova:
I am pleased to inform you as the Director of the California Department of Fish and Wildlife
(CDFW) that I concur with the Lead Agency determination by the City of Newport Beach
that the Big Canyon Coastal Habitat Restoration and Resiliency Project -Phase 3 (Project)
qualifies as a statutorily exempt restoration project under the California Environmental
Quality Act (CEQA). (Pub. Resources Code,§ 21080.56, subd. (e).) My concurrence as the
CDFW Director is based on CDFW's independent review of the City of Newport Beach's
request for concurrence, which CDFW received on March.24, 2022. In my opinion, informed
by the best available science and described in the separate CDFW Concurrence, the
Project meets all the qualifying criteria in Public Resources Code section 21080.56,
subdivisions (a) to (d), inclusive.
This concurrence signifies the continued commitment by CDFW and its partners in
advancing the "Cutting the Green Tape" initiative, which is a collaborative effort to increase
the pace and scale of restoration projects in California in a way that protects the
environment and results in long-term net benefits to climate resiliency, biodiversity, and
sensitive species recovery. CDFW stands ready to continue this effort in coordination with
the City of Newport Beach.
CDFW's Concurrence will be posted on our website as provided by Public Resources Code
section 21080.56. If you have any related questions, please contact Brad Henderson,
Cutting the Green Tape Program Manager, at (530) 351-5948, or by email at
Brad.Henderson@wildlife.ca.gov.
Sincerely,
{y/1 (J.YJt /4--
Charlton H. Bonham
Director
FILED
JAN 2 6 2023
ORANGE COUNTY CLE0:RDER DEPARTMENT
BY: DEPUTY
Conserving Ca{ifornia 's Wi{d'{ife Since 1870
PA2022-034
Makana Nova, Senior Planner
City of Newport Beach
May 4, 2022
Page 2
ec: Valerie Termini
Chief Deputy Director
California Department of Fish and Wildlife
Wendy Bogdan
General Counsel
Office of the General Counsel
California Department of Fish and Wildlife
Julie Vance
Acting Deputy Director
Ecosystem Conservation Division
California Department of Fish and Wildlife
Ed Pert
Regional Manager
South Coast Region (Region 5)
California Department of Fish and Wildlife
Christian Romberger
Senior Environmental Scientist
South Coast Region (Region 5)
California Department of Fish and Wildlife
Brad Henderson
Environmental Program Manager
Watershed Restoration Grants Branch
California Department of Fish and Wildlife
Alys Arenas
Restoration Manager
Newport Bay Conservancy
FILED
JAN 2 6 2023
ORANGE COUNTY CLERZK ECORDER DEPARTMENT
1/__ DEPUTY BY:: ___ -c;,~--
POSTED
JAN 2 6 2023
ORANGE COUNTY CLER~~O-RDER DEPARTMENT
BY: V DEPUTY
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 2,1080.56 (New 01/27/22) Page 1
CEQA STATUTORY EXEMPTION FOR RESTORATION PROJECTS (SERP) CONCURRENCE REQUEST
Completion and submission of this form is voluntary. This form may be submitted to request concurrence
from the Director of Fish and Wildlife pursuant to Public Resources Code section 21080.56.
Submit this form (pdf) and all attachments via the Department's Environmental Permit Information
Management System (EPIMS) Document Repository.
1 LEAD AGENCY
Lead Agency Name: City of Newport Beach n f"'\ c-T r:: n
I --I -...,
Contact Person Name Makana Nova, Senior Planner
Street Address: 100 Civic Center Drive JAN 2 6 2023
City, State, Zip: Newport Beach, CA 92660 ORANGE COUNTY CLERK·,;i:~RDER DEPARTMENT
01: , ; ·u I Y
Contact Person's Telephone: 949.644.3249 -. ----·-----------...... ___ ,. _____ -·-·---------·-·· . -·-•----------· ---.. ------·. --------------···-----------------· --------···-----· ---------·----·--------__ ., ____ -·--------· --·--
Contact Person's E-rnail: mnova@newportbeachca.gov
2. PROJECT PROPONENT □ Check Box and Skip to Number 3 if Same as Lead Agency
Business/Agency/Organization Newport Bay Conservancy
.
Contact Person's Name: Alys Arenas -..
Street Address: P.O. Box 10804 r ILt:.U
City, State, Zip: Newport Beach, CA 92658 JAN ? i; ?nn
Contact Person's Telephone: 951.202.8945 ORANGE COUNTY CLERK-RECORDER DEPA" .......
. . BY: (I I Contact Person's E-mail: alys.arenas@newportbay.org -DEPUTY
3. PROJECT INFORMATION
A. Project Name: . ' .. -_
Big Canyon Phase 3 Restoration Project
B. Ei;timated Project Start: Fall 2023; End Fall 2024 Start/End Dates:
C. Provide a brief description of project location, size, and funding sources. Please cite supporting documents
and provide as an attachment.
The Big Canyon Coastal Habitat Restoration and Resiliency Project -Phase 3 (Project) is the final phase of this
multi-phase habitat restoration project in the Big Canyon Nature Park. The Project is situated within the United
States Geological Survey (USGS) 7.5' series Newport Beach Quadrangle, Orange County, Township 6 South,
Range 10 West, Section 24. NAD83 Lat/Long is: 33.630890, -117.880724. The address assigned to the Phase 3
Project by the City of Newport Beach is 1950 Back Bay Dr, Newport Beach, CA 92660.
The 60-acre Big Canyon Nature Park is located at the downstream end of the Big Canyon Watershed in the City
of Newport Beach (City), Orange County, California. Big Canyon Creek drains the 1,300-acre Big Canyon
Watershed (Figure 1) in the City of Newport Beach directly into the Upper Newport Bay (UNB) State Marine
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 2~080.56 (New 01/27/22) Page 2
Conservation Area (SMCA) and Ecological Reserve (UNSER). Big Canyon Creek winds through Big Canyon in
a general southeast to northwest direction and discharges into UNB. Big Canyon Nature Park is the only
remaining natural, undeveloped portion of the Big Canyon watershed and the only significant remaining natural
canyon on the east side of UNB. Big Canyon Nature Park, located between Jamboree Road and Back Bay
Drive, has been degraded by numerous well documented impacts and requires habitat restoration and
enhancement to improve the site's biological productivity and ecological function. Land uses in the vicinity
include Upper Newport Bay (UNB) State Marine Conservation Area (SMCA) and Ecological Reserve to the west,
the restored section of Big Canyon to the east and residential and commercial development to the north and
south.
The Newport Bay conservancy (NBC) is the project proponent, and they have a standing record of successfully
soliciting and being awarded funding for the Big Canyon Restoration Project through a variety of grant funding
sources. Currently, NBC has an active grant with the Ocean Protection Council (OPC) for $779,000. An
additional $30,000 was also received from a corporate donor for planning and design for Phase 3. This OPC
grant will fund 100% restoration design construction drawings and specifications, environmental review, and
permitting. Previously, the State Coastal Conservancy (SCC) had awarded NBC $640,000 for the design,
planning, and permitting of the previous phase of the project (Phase 2A). Implementation funding for Phase 2A
was awarded from USFWS/SCC ($1,049,991.00), CDFW ($638,740.00) and OPC ($68K of active grant). NBC
has reached out to the following agencies for potential implementation funding: Wildlife Conservation Board
(WCB), OPC, CDFW and USFWS/SCC. All agencies have expressed interest in supporting the project
implementation but have asked to submit proposals and/or applications once 30% design and CEQA are
complete. NBC has been in communication with these agencies to provide briefings on the project's progress
and receive updates on potential future grant funding for implementation. NBC is confident in the ability to obtain
funding for implementation of Phase 3.
D. Provide a project summary and expected environmental benefits (i.e., acres or stream-miles
restored/enhanced, species benefitted, etc.). Please cite supporting documents and provide as an attachment.
Project Summary
The Big Canyon Coasta! Habitat Restoration and Resi!iency Project -Phase 3 (Project) is the final phase of this
multi-phase water quality, restoration, and adaptation project in the Big Canyon Nature Park. Big Canyon Nature
Park has been degraded by numerous well documented impacts and requires habitat restoration and
enhancement to improve the site's biological productivity and ecological function. Big Canyon Nature Park has
been subjected to the effects of water quality degradation from upstream development and selenium-laden
groundwater seepage, historical land disturbance from grazing and agricultural activities, year-round dry weather
fiows due to watershed urbanization, increased habitat degradation from invasive plants and insects, and dredge
and fill materials placed within the lower canyon marsh plain and riparian areas. Without future intervention, these
impacts will continue to degrade the remaining habitats and impact the listed species that have been identified by
previous and recent surveys.
The restoration of Phase 3 will restore approximately 14.3 acres of degraded habitat (within the 29-acre project
area) impacted by dredged material placement, non-native Brazilian pepper trees, and selenium impacted dry
weather flows.
POSTED
JAN 2 6 2023 JAN 2 6 2023
ORANGE COUNTY CLERK·RJ:,ORDER OEPARTME~~NGE COUNTY CL~CORDER DEPARTMENT
BY: _____ _;{_.V~:_ __ □EPUJY. ____ J...£ ____ ,□EPUTY
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 2,1080.56 (New 01/27/22) Page 3
Overall, the objectives and components of the preliminary design include:
• Restore historical salt marsh through grading that extends tidal influence into northern portion of project
area
• Creating Transitional Freshwater Wetlands including Wet Alkaline Marsh Habitat in the central portion of
the project area
• Placement of soils and restoration of degraded upland in the southern portion of the project area
• Removing non-native vegetation throughout the project area
• Removing human-made berm that bifurcates the freshwater flow and restore historical salt marsh in the
central portion of the project area
• Increase tidal extent and range through focused dredging in the tidal channel at the northwestern extent
of the project area
• Manage dry weather flows and create a continuous riparian corridor that transitions to tidal wetland by
realigning freshwater channel to flow through the southern side of the project area
• Restoring and Enhancing Riparian Habitat throughout the project area
• Improving Resiliency of Restored and Enhanced Riparian Habitat throughout the project area
• Grading to support marsh transitional habitat to adapt to sea-level rise throughout the project area
• Addressing vector concerns by removing Mosquito Breeding Habitat throughout the project area
• Improve the site's natural hydrology to reduce the Accumulation and Bioavailability of Selenium from
Ponded Dry Weather Flows
• Encouraging Public Participation and Provide Education
• Maintaining Existing Recreational Opportunities
Phase 3 restoration consists of several components, including restoration of historical salt marsh and
establishment of transitional wetlands that will allow for upslope migration and resiliency to long-term sea level
rise (SLR). Big Canyon Nature Park provides a valuable resource in Upper Newport Bay (UNB) as an opportunity
to establish these transitional zones as SLR alters the habitat within the Upper Newport Bay Ecological Reserve
(UNSER). The Project proposes to extend the saltwater influence into the Project limits, resulting in the restoration
of tidal marsh, which also further reduces selenium bioavailability found naturally within marine deposits in the
watershed. Big Canyon Phase 3 provides an opportunity to support salt marsh areas with future sea-level rise to
improve the overall resiliency of salt marsh in Upper Newport Bay. The invasive Brazilian pepper trees ( Schinus
terebinthifo/ia) will be removed as part of the salt marsh restoration.
Phase 3 also includes the modification to the terminus of Big Canyon Creek to maintain positive drainage during
low flows to reduce the accumulation of selenium in the soil and vegetation and address mosquito breeding habitat.
The freshwater channel re-alignment will establish a riparian corridor that integrates with upstream restored
corridor in Phases 1 and 2. The freshwater channel will also convey dry weather flows away from the planned
intertidal salt marsh habitat to maintain the required salinity levels to establish the salt marsh vegetation. Storm
flows will still inundate the full marsh plain to maintain the full extent of the existing wetlands. Periodic freshwater
inundation of the salt marsh during storm event provides natural hydrology processes that occur in these systems.
The Project achieves no net loss of wetlands.
Existing access roads and trails that are not impacted by the planned grading efforts will remain. On the northern
side of the site, a construction and long-term operations and management (O&M) access road will be graded
outside planned wetland restoration to connect with existing access roads.
Project construction is anticipated to commence in Fall 2023 with substantial completion by Fall 2024, followed
by a five-year plant and habitat establishment and maintenance period. The project is led by the Newport Bay
Conservancy (NBC) with collaboration with CDFW and the City of Newport Beach (City). NBC has successfully
completed Phase 2A and collaborated with the City on the successful completion of Phase 1.
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 21080.56 (New 01/27/22) Page 4
Environmental Benefits
Overall, upon completion the Project will restore/enhance/create approximately 0.3 acres of low marsh, 0.8 acres
of mid marsh, 1.7 acres of high marsh, and 7.3 acres of transitional freshwater wetland habitat restored on site.
lnaddition, 4.2 acres of upland scrub habitat will be restored/enhanced for a total of approximately 14.3 acres of
restoration.The distribution of these proposed habitat types are shown on the Habitat Restoration Design map
included as Figure 3 in the attached Appendix A, Project's Biological Technical Report (Trestles, 2022). This
restoration work will take place within the approximately 29-acre Project Area.
Through this restoration project, additional habitat that can support a variety of specials status flora and fauna
will be created. Some of the special status faunal species that would be benefit from this restoration project
include the California gnatcatcher (Po/ioptila ca/ifornica), the least Bell's vireo (Vireo be/Iii pusillus), and the
light-footed Ridgway's rail (Ra//us longirostris levipes). Additional common and special status species that will
benefit from the project can be found in sections 4C of this application.
Native Plant communities will also benefit from the Project due to the removal and restoration of the upstream
portions of the site that are currently dominated by pepper trees. Shot hole borer have also invaded many of the
upland tree species, primarily the Brazilian pepper trees and will be addressed to attempt to contain this outbreak.
This will be done through mulching the non-native trees and solarizing the mulch for several months. This
technique has proven effective in Phase 1 and 2 of the project.
The newly established salt marsh will support species of plant including common pickleweed (Salicornia
pacifica), alkali heath (Frankenia salina), salt marsh rosemary (Limonium californicum), saltwort (Batis
maritima ), and Parish's glasswort (Arthrocnemum subterminale ). Once the pepper trees are removed riparian
woodland characterized by a mosaic of native tree species that will include several species of willow, western
sycamore, Fremont's cottonwood, Mexican elderberry, white alder, and coast live oak will be planted and cared
for. This woodland will be supported by anunderstory of native mulefat scrub and an herbaceous vegetation
stratum composed of rushes, grasses, and sedges.
While much of the project area could likely be defined as Environmental Sensitive Habitat Areas (ESHA) as
defined by the California Coastal Act, this restoration project is specifically designed to enhance these areas and
create more biologically productive EHSA. This restoration project will provide a functional lift to the ecological
communities that connect two recent restored upstream ESHA areas (Phase 1 & 2) with a highly productive
ESHA downstream in the UNB Marine Protected Area.
More details about this project can be found in the attached Appendix B, Project Description and Project's
Biological Technical Report (Trestles, 2022)._
Current Vegetation Alliances Present on Site
Based on a survey performed in August 2021, the Project Area currently supports seventeen vegetation alliances
and open water/tidal habitats, as well as disturbed and developed areas. Wetland vegetation alliances or habitat
types include: Alkali Meadow (0.84 acres), California Bulrush Marsh (0.13 acres), California Cordgrass Marsh
(0.21 acres), Freshwater Marsh (4.22 acres), Intertidal Mudflat (0.40 acres), Arroyo Willow/Peppertree Grove
(6.91 acres), Willow Riparian (0.25 acres), Mule/at/Coyote Brush Scrub (0.14 acres), Open Water (2.09 acres)
and Pickleweed Mat (2.04 acres). Upland/transitional habitats include: Alkali Heath/Menzies' Goldenbush Scrub
(0.55 acres), California Brittlebush/California Sagebrush Scrub (1.93 acres), California Sagebrush Scrub (0.69
acres), Coyote Brush/California Sagebrush Scrub (1.11 acres), Disturbed California Sagebrush/ Saltbush Scrub
(0.20 acres), Disturbed Menzies' Goldenbush Scrub (2.61 acres), and Fourwing/Swamp Saltbush Scrub (2.36
acres) (Figure 4 of the Biological Technical Report).
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 2·1080.56 (New 01/27/22) Page 5
E. CDFW recommends that lead agencies meet and confer with tribes, representatives of any affected local
~gencies, and other .stakeholders prior to submitting a SERP request to CDFW. Please provide a summary of
project consultation with tribes, agencies, and other stakeholders and submit documentation as an attachment.
As part of the Native American outreach effort for Phase 2 and future Phase 3, the cultural resource consultant
(ESA) contacted the NAHC on March 18, 2018, to request a search of the SLF. In a letter response dated March
20, 2018, the NAHC indicated that "sites have been located within several of the quadrangles" provided and they
may be impacted by the Project. No specific information regarding the types of resources or their locations was
provided; however, the NAHC indicated that the Juaneno Band of Mission Indians -Acjachemen Nation should
be contacted. This was done as part of the AB 52 outreach discussed below and further detailed in the attached
Appendix C, Phase 3 Cultural Resource Assessment Report (Burns & McDonnell, January 2022).
Pursuant to AB 52, the City sent letters to the three contacts on the City's AB 52 consultation list. The letters
described the Project, provided a Project map, and invited the individuals to consult on the Project. Individuals
contacted included: Mr. Andrew Salas, Chairperson of the Gabrielefio Band of Mission Indians -Kizh Nation, by
letter dated March 16, 2018; Ms. Joyce Stanfield Perry, Tribal Manager of the Juaneno Band of Mission Indians,
Acjachemen Nation, by letter dated March 19, 2018; and Mr. Anthony Morales, Chairperson of the San Gabriel
Band of Mission Indians, by letter dated March 19, 2018. One response was received.
By letter dated March 29, 2018, Mr. Andrew Salas of the Gabrielefio Band of Mission Indians -Kizh Nation
requested consultation pursuant to Public Resources Code 21090.3.1, indicating that the Project occurs within
the tribe's ancestral territory. Mr. Salas provided the City with documentation supporting this. As part of
consultation, the tribe also requested a field visit to the Project site. On May 17, 2018, Robert Stein with the City,
Mr. Salas and Matt Teutimez with the Gabrieleiio Band of Mission Indians -Kizh Nation, and representatives
from ESA conducted a walkover of the Project site. Mr. Salas indicated that while permanent encampments
were not likely to occur within the canyon, there may have been temporary day camps in the Project area. Mr.
Salas further indicated that monitoring during Phase 2 and Phase 3 construction activities would be sufficient for
protecting any cultural resources that might be encountered during Project implementation. Both archaeological
and Native American monitoring are planned for as part of the project's implementation.
In addition, prior to the City's tribal outreach efforts, Mr. Salas provided the City with documentation concerning
the extent of the tribe's traditional territory, which encompasses the Project area, and the proper name for the
tribe, which should be the Kizh. Some of this information was provided during implementation of Phase 1 of the
Project but pertains to all phases. Mr. Salas also provided a list of known ethnographic villages in the area.
These are discussed in the Ethnographic Setting section of the attached Phase 3 Cultural Resource
Assessment Report, January 2022.
As a result of Native American outreach and consultation, no tribal cultural resources have been identified within
the Project area. Consultation pursuant to AB 52 is ongoing and NBC will continue to coordinate with involved
tribal representatives. NBC has been in communication with Mr. Salas on the Phase 3 project and has
requested review of this cultural resources report. Meetings are being planned with Mr. Salas to go through the
report and any comments and recommendations will be incorporated.
This project will directly benefit the residents of the City of Newport Beach and the constituents that use City
facilities throughout the greater Big Canyon watershed. The City and CDFW are landowners of the project site.
CDFW is the entity that directly manages the adjacent Marine Protected Area, the Upper Newport Bay Ecological
Reserve. NBC has a history of supporting restoration projects in Big Canyon. NBC has a mission to protect and
preserve the Upper Newport Bay thorough restoration, education, research, and advocacy. In partnership with
the City, NBC has successfully managed, soliciting funding, and implemented restoration projects in Big Canyon.
The Newport Aquatic Center (NAC) will also directly benefit from this project from a water quality perspective.
The NAC hosts water-based recreations programs, in partnership with NBC, on the bay that will benefit from
improved water quality conditions. The following stakeholders, which sit on the Technical Advisory Committee,
also support this project: U.S. Fish and Wildlife Service, State Coastal Conservancy, Ocean Protection Council,
WCB, OC Vector Control, Army Corps of Engineers, the Irvine Ranch Conservancy, UC Irvine, OC California
Native Plant Society, Sea & Sage Audubon, and the Santa Ana Regional Water Quality Control Board.
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 21080.56 (New 01/27/22) Page 6
4. REQUIRED DETERMINATIONS
Provide a full description for each determination below:
A. The project is exclusively one or both of the following: (1) a project to conserve, restore, protect, or enhance,
and assist in the recovery of California native fish and wildlife, and the habitat upon which they depend, or (2)
a project to restore or provide habitat for California native fish and wildlife. Please cite supporting documents
and provide as an attachment.
The City of Newport Beach has determined that this Project will both (1) conserve, restore, protect, or enhance,
and assist in the recovery of California native fish and wildlife, and the habitat upon which they depend and (2)
restore or provide habitat for California native fish and wildlife. The project proposes to replace existing
degraded habitat by restoring historic salt marsh and freshwater/riparian habitat. Salt marsh was filled in the
1950-60s as a result of dredged material placement in Big Canyon. By restoring salt marsh habitat, this will
provide habitat for a variety of California wildlife that utilize this habitat including, but not limited to, the Light-
footed Ridway's Rail (Raf/us longirostris /evipes), osprey (Pandion haliaetus), white-tailed kite (Elanus /eucurus),
great blue heron (Ardea Herodias), white-faced ibis (Plegadis chihi), and snowy egret (Egret/a thula).
Restoration of freshwater riparian and alkaline meadow habitat will provide habitat and assist in the recovery of
the least Bell's vireo (Vireo be/Iii pusi/!us). An array of other California wildlife will benefit from the restoration of
this habitat including, but not limited to, the yellow warbler (Setophaga petechia), yellow-breasted chat (/cteria
virens), Mastiff bat (Eumops perotis), Western red bat (Lasiurus blossevillii), and yellow-rumped warbler
(Setophaga corona/a). Upland Coastal Sage Scrub habitatenhancement will benefit the coastal California
gnatcatcher (Po/ioptila californica californica), song sparrow (Melospiza melodia), California towhee (Me/ozone
crissa/is) and the wrentit (Chamaea fascia/a), to name a few.
See the attached Biological Technical Report (Trestles 2022), as well as technical appendices, for a list of
California wildlife that are found within Big Canyon that would benefit from the project implementation.
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 21080.56 (New 01/27/22) Page 7
B. An eligible project may have incidental public benefits, such as public access and recreation. Please cite
supporting documents and provide as an attachment.
The City of Newport Beach has determined that this project may have incidental public benefits resulting from
the need for establishing dirt and/or gravel roads to allow for restoration construction equipment access the
site. These access roads will be kept in place for ongoing project maintenance but will also be open to the
public as walking trails around the perimeter of the restoration site. The location of these incidental public
benefits are shown on the Conceptual Access Plan (Appendix D, Sheet 5), Existing access roads and trails that
are not impacted by the planned grading efforts will remain.
Big Canyon Nature Park is used by residents and visitors for passive recreation. This is an important destination
for thousands of children participating in the Orange County Department of Education Inside the Outdoors
program. Inside the Outdoors provides watershed educational activities for grade school children throughout the
county including disadvantage communities. As the largest undeveloped canyon adjacent to Newport Bay, it has
the potential to become an integral part of the Upper Newport Bay State Ecological Preserve and to provide
unique opportunities for the public to learn about the diversity of biological resources and environmental
protection within a short walking distance. Along with the restoration of a mosaic of coastal riparian, alkaline
marsh, salt marsh, transitional habitat and coastal sage scrub, the existing and p!anned construction and
operation and maintenance roads will provide incidental public benefits serving an ancillar; function as trails
around the perimeter of the restoration that will provide an enhanced experience of the different ecotones in a
coastal watershed.
The Project \•Viii provide direct benefits to students from nearby disadvantaged communities. The restoration is
designed to be an important educational resource for teachers bringing students to Upper Newport Bay. NBC
fosters relationships with multiple southern California schools to provide ongoing educational and stewardship
opportunities for over 3,000 students annually. UNB, and the trails in Big Canyon are a regular destination for
Early College High School and Back Bay High School students to provide ongoing monitoring and maintenance
of the Project site through hands on learning. Education programs are aligned with California Science and
Social Science standards and provides a feet-on-the-ground program for over three thousand students every
year for students in Orange County, including disadvantaged communities. The restoration is being designed by
ecologists to provide a spectrum of integrated habitats to facilitate the educational experience of students
visiting Upper Newport Bay. Two programs offered by NBC, in partnership with the Orange County Department
of Education and the City of Newport Beach, include Inside the Outdoors for 4th grade students
(https://ocde.us/ito/Pages/Upper-Newport-Bay.aspx) and the Fostering interest in Nature (FiiN) program for 5th
grade students (https://www.newportbeachca.gov/governmenUdepartments/recreation-senior-services/marine-
protection-tidepools ). Both programs serve Title 1 schools in Orange County and include educational hikes,
experiments and exploring through Big Canyon. Working with local Native American tribes, educational
opportunities will be realized that include information kiosks and signage about the Native American culture and
how local vegetation and natural resources were used by th ese communities. Specific site cultural resources will
not be identified to protect these resources. The Newport Bay Conservancy has provided environmental
education programs for over 40 years and serves over 50,000 people each year. NBC provides volunteer
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 21080.56 (New 01/27/22) Page 8
support for programs at the Interpretive Center and the Back Bay Science Center that leads tours and
interactive learning with school-aged children from throughout the region including disadvantaged communities.
C. The project does both of the following: (1) results in long-term net benefits to climate resiliency, biodiversity,
and sensitive species recovery; and (2) Includes procedures and ongoing management for the protection of
the environment. Please cite supporting documents and provide as an attachment.
Long Term Net Benefits to Climate Resiliency:
The City of Newport Beach has determined that this project will provide long-term net benefits to Climate
Resiliency. Long-term sea level rise will increase the extent and inundation of tidal flows in the Upper Newport
Bay (UNB). Big Canyon Nature Park provides a valuable resource in UNB as an opportunity to establish
transitional zones as SLR alters the habitat within the UNB. The transitional habitat provided in the Phase 3
project restoration willprovide for climate resiliency. As tidal extent and inundation increases, the transitional
zones allow for the migration of salt marsh vegetation and habitat. By providing for these transition zones
between planned salt marsh and freshwater wetlands in the Phase 3 design, the project provides an
opportunity to support salt marshareas with future sea-level rise to improve the overall resiliency of salt marsh
in Upper Newport Bay. This design resiliency is demonstrated in the Appendix B, Project Description
(attached) as shown on figures of the planned salt marsh and freshwater wetland that will be restored after
construction and the predicted habitats based on SLR projections. These predicted habitats and SLR
projections are from the selected alternative that was presented in the Feasibility Study (ESA, 2020) that is the
basis for the 30% Design.
More detailed information on climate resiliency is provided in the attached Appendix E, Coastal Hazards
Analvsis Renart /Burns & McDonnell, 2022).
Long Term Net Benefits to Biodiversity:
The City of Newport Beach has determined that this project will provide long-term net benefits to Biodiversity.
Currently large portions of the habitats in the Project area have either been invaded by non-native plant species
or are dominated by monotypic stand of native vegetation. Where non-native species like Brazilian pepper trees
(Schinis terebinthifolia) or swamp atripiex (Atnplex amnicola) have invaded, the biodiversity of native plant ana
animal populations has been affected. This project will target these non-native plant populations and control
them as part of the grading plan and create a hydrological setting that will support a more balanced assemblage
of native vegetation that is resilient to dominance by non-native plant species. These diverse plant communities
will then support a greater diversity of native wildlife species up and down the trophic levels.
Specifically, much of the downstream area dominated by pepper trees will be converted to intertidal salt marsh
which is well known to be a highly biologically productive ecosystem that supports a diversity of marine
communities. The upstream portions of the site dominated by pepper trees will be restored to a riparian
woodland characterized by a mosaic of native tree species that will include several species of willow, western
sycamore, Fremont's cottonwood, Mexican elderberry, white alder, and coast live oak. This woodland will be
supported by an understory of mulefat scrub and an herbaceous vegetation stratum composed of rushes,
grasses, and sedges. This layering of canopies does not currently exist in the pepper tree groves and therefore
the site does not support bird species like the least Bell's vireo (Vireo be/Iii pusil/us) that thrive in these
conditions.
Another example is found in upland areas that have become invaded by swamp atriplex. These uplands will be
selectively filled and regraded in order to eliminate the non-native plant infestation and promote the
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW 2·1080.56 (New 01/27/22) Page 9
establishment of a diverse assemblage of Diegan coastal sage scrub which will expand potential breeding
habitat for the threatened California gnatcatcher (Po/ioptilla californica ).
The same approach to creating a long-term net benefit to biodiversity will be taken in areas that are currently
dominated by monotypic stands of native vegetations. For instance, the existing freshwater marsh is composed
almost exclusively of dense stands of cattails ( Typha spp.). This restoration project will regrade the stream so
that water is focused through a narrower channel that will not pond. This will create intermittently saturated
wetland soils that can support a diverse willow woodland habitat in areas currently dominated by cattails. This
will also create riparian benches that can support alkali and brackish marsh habitat which can support certain
sensitive species like southwestern spiny rush (Juncus acutus) which in turn provides potential breeding habitat
for the endangered light-footed Ridgway's rail (Ra/lus obso/etus).
Additional species that will benefit from the Project include an array of wildlife species such as California least
tern (Sterna antillarum browni), elegant tern (Tha/asseus e/egans), tiger beetle (Cicindela spp.), Belding's
savannah sparrow (Passercu/us sandwichensis beldingi), salt marsh wandering skipper (Panoquina errans),
western fence lizard (Sceloporus occidenta/is), coyote (Canis la/rans), Botta's pocket gopher (Thomomys
bottae), desert woodrat (Neotoma lepida), California ground squirrel (Spermophi/us (Otospermophi/us)
beecheyi), bushtit (Psaltriparus minimus), song sparrow (Melospiza melodia), spotted towhee (Pipi/o
maculatus), common yellowthroat (Geothlypis trichas), Allen's hummingbird (Se/asphorus sasin), turkey vulture
(Cathartes aura), red-shouldered hawk (Buteo lineatus), white-tailed kite (Elanus /eucurus), and osprey
(Pandion haliaetus). More information can be found in the Project's Biological Technical Report (Appendix A).
Long Term Net Benefits to Sensitive Species Recovery:
The City of Newport Beach has determined that this project will provide long-term net benefits to Sensitive
Species Recovery. Restoration of salt marsh habitat would benefit the following salt-marsh dependent
sensitive species:
Light-footed R;dgway's Rail (Ra//us obsoletus) [SE/FE]
Belding's savannah sparrow (Passercu/us sandwichensis beldingi) [SE]
Southern tarplant ( Centromadia parryii ssp. australis) [CRPR 1 B.1]
Salt marsh bird's beak (Chloropyron maritimum ssp. maritimum) [CE, FE, CRPR 1 B.1]
Estuary seablite (Suaeda esteroa) [CRPR 1 B.2]
Woolly seablite (Suaeda taxifolia) [CRPR 4.2]
California boxthorn (Lycium californicum) [CRPR 4.2]
Restoration of riparian habitat would benefit the following riparian-dependent sensitive species:
California gnatcatcher (Polioptila califomica) [FT/SC]
Yellow warbler (Setophaga petechia) [BCC/SC]
Least Bell's vireo (Vireo be/Iii pusil/us) [FE/SE]
Southwestern spiny rush (Juncus acutus ssp. /eopoldii) [CRPR 4.2]
Limited habitat exists for any of these species under existing conditions. Following project completion, habitat for
these various sensitive species would be created, allowing for establishment of rare plants in and around the
restored habitat, as well as creating habitat for either nesting or foraging for the sensitive avian species.
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
. DFW 21080.56 (New 01/27/22) Page 10
Removal of swamp saltbush in adjacent upland areas would also improve habitat for the coastal California
gnatcatcher (Polioptila ca/ifornica ca/ifomica) [FE/SSC]. Brief descriptions of the special status plant species are
provided below. More information can be found in the Project's Biological Technical Report.
Salt marsh bird's beak (Ch/oropyron maritimum ssp. maritimum) is a hemiparasitic annual herb listed as
federally-and state-endangered and designated as a CRPR 1 B.2. It is known to exist in just 8 locations in the
United States including Upper Newport Bay. Numerous occurrences of this species were documented by Tidal
Influence in 2018 near the drainages from Big Canyon and the presence of those occurrences were confirmed
during the survey performed on June 24th, 2021. This species is found relatively extensively along the edges
of both tidal channels that extend from the Big Canyon outfalls and is often intermixed with Suaeda esteroa.
Southern tarplant (Centromadia parryi ssp. austra/is): Southern tarplant is an annual herb designated as a
CRPR 1 B.1. This species was observed within the project boundary and was found mostly along the edges of
roads and trails. Several narrow occurrences are located along the edges of Back Bay Drive, while the other
major grouping of occurrences is along the main trail that leads from the parking lot along the south edge of
theexisting cattail marsh. One occurrence was also documented in the Phase 2 restoration area that overlaps
withthe Phase 3 project boundary.
California boxthorn (Lycium ca/ifornicum): California boxthorn is a perennial shrub designated as a CRPR 4.2.
Three individuals of this species were documented within the project boundary. One individual is located on the
tidal marsh side of Back Bay Drive in the upland transition zone, another was found intermixed with saltbush
scrub along the main trail, and the final individual is located on the bluff just above the Phase 2 restoration area.
Estuary seablite (Suaeda esteroa): Estuary seablite is a perennial shrub designated as a CRPR 1B.2. This
species is ubiquitous throughout the mid-marsh zone of Upper Newport Bay and therefore was found
extensively within the portions of the project area that overlap with tidal marsh habitat. This species dominates
the plant community that is found along the edge of the tidal channel that connects to the northernmost
drainagefrom Big Canyon.
Southwestern spiny rush (Juncus acutus ssp. leopoldil): Southwestern spiny rush is a perennial grass-like herb
designated as CRPR 4.2. The densest of these occurrences are found aiong the edges of Back Bay Drive
mostly around a small ditch that runs parallel along the east side of the road. One individual is found on the west
side of Back Bay Drive in the upland transition zone. Another grouping of individuals is found at the northwestern
edge of the arroyo willow/pepper tree woodland along the trail that runs between the bluff and the woodland.
Lastly, this species was planted extensively as part of the Phase 2 restoration project and is found in
abundancewhere the project boundary overlaps with these plantings.
Woolly seablite (Suaeda taxifolia) is a perennial shrub designated as a CRPR 4.2. Two naturally existing
occurrences of this species were documented in the upland transition zone in close proximity to J. acutus and L.
californicum. This species was also extensively planted as part of the Phase 2 restoration project and is found in
abundance where the project boundary overlaps with these plantings.
Procedures and Ongoing Management for the Protection of the Environment
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
. DFW 21080.56 (New 01/27/22) Page 11
Ongoing Monitoring, Maintenance and Adaptive Management
Monitoring
Implementation of the Project would require a biological monitoring program to ensure the revegetation is
successful and the wetland functions and services are achieved and maintained into the future. The program
would include pre-and post-construction monitoring, as well as monitoring for longer-term habitat functions.
Monitoring objectives would focus on ensuring compliance with project features and measures, particularly with
respect to biological resources. After construction is completed, ongoing monitoring would be focused on the
restoration component and designed to document achievement of project goals and objectives, including habitat
improvements for plants and wildlife, success of revegetation efforts, and use of the site by sensitive species.
The applicant will prepare a Habitat Restoration Plan (HRP) as part of the final design package, which would
govern restoration measures and the collection of monitoring data to assess the effectiveness toward the various
goals and objectives of the program. The habitat monitoring program, to be described in more detail in the HRP,
would provide an implementation plan to ensure the successful restoration of wetlands. The program would
include a restoration work plan with recommended methodologies for site preparation, seeding/planting, irrigation,
etc.; a maintenance plan: specific monitoring and reporting requirements, including site performance standards,
and a description of long-term management of the restoration areas described in the attached Biological Technical
Report. This document would also be used to inform potential future adaptive management decisions and actions.
The post-construction monitoring phase would identify a post implementation timeframe that would focus on
meeting restoration permit conditions and/or success criteria. Once those criteria are met, monitoring and
management would shift over to the long-term program focused on adaptive management discussed below.
Maintenance and Adaptive Management
The HRP would include both the anticipated maintenance regime and an adaptive management plan. Long-term
monitoring would be an integral part of an adaptive management program established to guide maintenance
strategies into the future. The adaptive management plan would identify remedial measures that may be
implemented if success criteria put in place as part of the project or permit conditions are not met or if conditions
change during long-term monitoring and need to be addressed. Some of these actions may include, but are not
limited to, replanting of riparian, salt marsh and transitional habitats, control of invasive pests, and amendment of
soils. Detailed plans would be developed as part of consultation with permitting and natural resource agencies
during the permitting approval process; however, it is anticipated that the long-term management plan would be
a living document and would be updated regularly, as necessary. General components associated with the
adaptive management strategy are described below.
1. Site Grading. Site grading will occur outside of nesting season (September 1 to January 31 ).
2. Replacement Planting. Planted material that fails to become established would be replaced with similar
plantspecies. Replacement vegetation would be installed between October 1 and March 31, to the extent
possible.
3. Biological Monitoring and Maintenance of Habitat Quality. Regular biological monitoring would be
conducted to ensure that the habitat meet biological goals. These activities would include:
a. Monitoring of plant establishment and cover, per an approved Habitat Restoration Plan, and
b. Control of nonnative invasive plant species by mechanical and chemical means as appropriate.
c. Monitoring and management of emergent freshwater vegetation (e.g. cattails) to maintain freshwater
flowrates and eliminate ponding.
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
DFW21080.56 (New 01/27/22) Page 12
D. The project does not include any construction activities, except for construction activities solely related to
habitat restoration. Please cite supporting documents and provide as an attachment.
As lead agency, the City of Newport Beach has determined that all work is related to habitat restoration. All
proposed work is related to habitat restoration, site access, and incidental public benefits. No building structures
are proposed as part of this project. Habitat restoration grading activities would commence with the installation
of construction stormwater pollution prevention BMPs in accordance with the project Stormwater Pollution
Prevention Plan (SWPPP). Following the installation of stormwater BMPs, project construction work would
occur in phases for a duration of five to six months. The following schedule presents the construction phases,
the activities to be completed under each phase, and the duration of the activities. Several activities willrun
concurrently to achieve the overall construction schedule of approximately five months.
Clearing and grubbing activities with the construction of the access roads will initiate the construction after the
erosion and sediment controls are installed. Grading will then occur to establish the salt marsh and transitional
habitats within Phase 3. Focus dredging of the tidal channel will occur during site grading. Placement of soil
from the salt marsh grading to the upland area will be conducted during the grading activities. The total
earthwork cut volume is anticipated to be approximately 37,000 cubic yards. Earthwork fill will be placed in the
marsh pond area once the vegetation has been removed. Additional placement areas are anticipated in upland
areas along the northern perimeters of Phase 3 and the area to the south as shown on Figure 9. No material is
anticipated for off-haul.
As per the attacherl 30% design documentation, all construction FJctivity will be solely related to habitat
restoration.
PA2022-034
State of California -Department of Fish and Wildlife
CEQA RESTORATION STATUTORY EXEMPTION REQUEST FORM
'DFW 21080.56 (New 01/27/22) Page 13
5. CERTIFICATION
I certify that I have the authority to determine whether a project is exempt pursuant to CEQA Guidelines section
15025(a)(1), and this project meets all the requirements described in Public Resources Code section 21080.56,
and that I have submitted all the determinations required therein necessary to obtain the concurrence of the
Director of Fish and Wildlife.
Senior Planner, AICP Date: March 4, 2022
Lead Agency Signature
Printed Name and Title: Makana Nova, Senior Planner
Appendices (In order of reference)
A. Biological Technical Report
B. Project Description
C. Cultural Resource Assessment
D. Project Plans (30% Design) including Conceptual Public Access
E. Coastal Hazards Analysis Report
Pending Supporting Studies
Selenium Report
WQMP/SPPP
Weed Control Eradication Plan
Habitat Restoration Plan
PA2022-034
Hugh Nguyen
Orange CoW1ly Clerk-Recorder
601 N. Ross 3treet
Santa Ana, CA 92701
County
Finalization: 20230000022050
1/26/23 11:26 am
383 Vitindx
Item Title Count
1 ZOl 1
EIR: Exempt or Previously Paid
Document ID Amount
DOC# 202385000064 50.00
Time Recorded 11:26 am
Total
Payment Type
NO FEE
Amount Due
THANK YOU
0.00
Arnount
50.00
0.00
PLEASE RE"rAIN 'fHIS RECEIPT'
FOR YOUR RECORDS
PA2022-034