c�<,FORN'P City Council Staff Report
April 11, 2023
Agenda Item No. 5
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Eric Loke, Senior Civil Engineer,
eloke@newportbeachca.gov
PHONE: 949-644-3336
TITLE: FY2022-23 Traffic Signal Rehabilitation Project — Award of Contract
No. 9095-1 (23T01)
ABSTRACT:
The City of Newport Beach (City) has received construction bids for the Fiscal Year 2022-
23 Traffic Signal Rehabilitation Project and requests City Council approval to award the
construction contract to International Line Builders, Inc., dba ILB Electric of Corona,
California. The proposed signal improvements will address the existing signals on
Newport Coast Drive from Sage Hill to Ridge Park Road.
RECOMMENDATIONS:
a) Determine this action is exempt from the California Environmental Quality Act (CEQA)
pursuant to Sections 15060(c)(2) and 15060(c)(3) of the CEQA Guidelines because
this action will not result in a physical change to the environment, directly or indirectly;
b) Approve the project plans and specifications;
c) Award Contract No. 9095-1 to International Line Builders, Inc. dba ILB Electric for the
bid price of $680,411, and authorize the Mayor and City Clerk to execute the contract;
and
d) Establish a contingency of $68,000 (approximately 10 percent of total bid) to cover the
cost of unforeseen work not included in the original contract.
DISCUSSION:
The Public Works Department operates 123 City -owned traffic signals. Annually, a project
is developed to replace and rehabilitate older traffic signals that are nearing or at the end
of their service life. The work consists of replacing aging poles, controller cabinets,
equipment and wiring to maintain the existing traffic signal operation and increase the
reliability of the traffic signal system. For this budget year, the project consists of the
following three locations:
Newport Coast Drive at Sage Hill
Newport Coast Drive at Gas Recovery
Newport Coast Drive at Ridge Park Road
5-1
FY2022-23 Traffic Signal Rehabilitation Project — Award of Contract No. 9095-1 (23T01)
April 11, 2023
Page 2
At 10 a.m. on March 23, 2023, the City Clerk opened and read the following bids for the
Fiscal Year 2022-23 Traffic Signal Rehabilitation Project:
RANK
BIDDER
TOTAL BID AMOUNT
Low
International Line Builders, Inc. dba ILB Electric
$680,411.00
2nd
Select Electric, Inc.
$695,875.00
3rd
Crosstown Electrical & Data, Inc.
$822,473.00
4th
California Professional Engineering, Inc.
$835,076.00
5th
Elecnor Belco Electric, Inc.
$910,556.00
The low bid amount is 10 percent above the Engineer's Estimate of $620,000. The low
bidder, ILB Electric, possesses a California State Contractors License Classification
"C-10" as required by the contract documents. The contractor has successfully completed
similar projects within Newport Beach and a check of the contractor's references indicates
satisfactory completion of similar projects for other public agencies.
Pursuant to the contract documents, ILB Electric has 100 consecutive working days to
complete the project. Failure to complete the work within the specified time will result in
liquidated damages set at a daily sum of $500.
The project plans and specifications will be available for review at the April 11, 2023, City
Council meeting or upon request.
a 6*973! 1►Vi l :7_TO IF
Sufficient project funding is available within the Fiscal Year 2022-23 Capital Improvement
Program (CIP) budget for completion of this contract. The following funds will be
expensed:
Account Description Account Number Amount
General Fund 01201927-980000-23T01 $ 752,500
Total: $ 752,500
Proposed fund uses are as follows:
Vendor
Purpose
Amount
ILB Electric
Construction Contract
$
680,411
ILB Electric
Contingency
$
68,000
Various
Incidentals, Printing
$
4,089
Total: $
752,500
Staff recommends establishing $68,000 (approximately 10 percent) for contingency
purposes and unforeseen conditions associated with construction.
5-2
FY2022-23 Traffic Signal Rehabilitation Project — Award of Contract No. 9095-1 (23T01)
April 11, 2023
Page 3
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this action is not subject to the California
Environmental Quality Act (CEQA) pursuant to Sections 15060(c)(2) (the activity will not
result in a direct or reasonably foreseeable indirect physical change in the environment)
and 15060(c)(3) (the activity is not a project as defined in Section 15378) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential for resulting in physical change to the environment, directly or indirectly.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
5-3
Attachment A
1
Q� Ilabm RedW, Nrwp m R4.Ixr
Newport Coast Dr
Sae Joaquin R—e t, at Sage Hill •
O
d Newport Coast Dr
at Gas Recovery
2
tiln vja•!w
J
SAN ]OAQUIN HI��S
RD
Newport Coast Dr
at Ridge Park Rd
`OP
Q�
QO
West \ cwpott toad
I
TRAFFIC SIGNAL REHABILITATION PROGRAM
CITY OF NEWPORT BEACH
FY 2022-2023
PUBLIC WORKS DEPARTMENT
C-9095-1
04/11 /2023
LOCATION MAP
5-4