HomeMy WebLinkAbout08 - FY 2021-22 Streetlight Improvements Project (Harbor View Hills) - NOC for Contract No. 766-3 (22V02)Q SEW Pp�T
CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
June 13, 2023
Agenda Item No. 8
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer,
tandefur@newportbeachca.gov
PHONE: 949-644-3321
TITLE: FY 2021-22 Streetlight Improvements Project (Harbor View Hills) —
Notice of Completion for Contract No. 7661-3 (22V02)
ABSTRACT:
On November 30, 2021, the City Council awarded Contract No. 7661-3, FY 2021-22
Streetlight Improvements Project (Harbor View Hills) to Calpromax Engineer, Inc.
(Calpromax) of Placentia, California. The work is now complete and staff requests City
Council acceptance and close out of the contract.
RECOMMENDATIONS:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
DISCUSSION:
Overall Contract Cost/Time Summary
Award Contract
Final Cost at
Total Contract
Percent Contract
Amount
Completion
Change Amount
Cost Change
$ 768,665.00
$ 729,154.68
- $39,510.32
- 5.1 %
Allowed Contract Time (days)
266
Actual Time
39
Under (-) or Over (+)
The project removed and replaced old conduits, wires, pull boxes and streetlight heads.
The project also installed new pull boxes, LED (light -emitting diode) streetlight lamps, and
six new service cabinets. Finally, the circuits along Marguerite Avenue from San Joaquin
Hills Road to Fifth Avenue, and the residential streets within the Harbor View Hills
community, were converted from high voltage to medium voltage.
RX
FY 2021-22 Streetlight Improvements Project (Harbor View Hills) —
Notice of Completion for Contract No. 7661-3 (22V02)
June 13, 2023
Page 2
The contracted work has now been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original Bid Amount:
$
768,665.00
Actual Cost of Bid Items Constructed:
$
681,725.00
Total Change Orders:
$
47,429.68
Final Contract Cost:
$
729,154.68
The final contract cost of $729,154.68 is approximately 5.1 percent lower than the original
bid amount. The original contract scope was reduced by removing most of the potholing
effort, re -specification of street light conduit, and by removing approximately half of the
street light foundation replacements. The FY 2023-24 Streetlight Improvement Project will
focus on streetlight foundations in the Corona del Mar and Eastbluff areas. With these
changes to the scope, the actual cost of bid items constructed was reduced to $681,725.
The project incurred approximately $47,000 in change order work. Approximately $35,000
was incurred due to bid quantity adjustments and overages related to conductors and
conduit work, including conduit boring due to unforeseen conduit blockages found in the
field and relocation of one service cabinet. Unforeseen rusty anchor bolts combined with
inclement weather resulted in approximately $11,000 in additional equipment rental.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule January 26, 2022
Actual Start of Construction Per Notice to Proceed January 26, 2022
Extended Contract Completion Date Inclusive of Extra Work May 5, 2023
Actual Substantial Construction Completion Date March 15, 2023
Additional time was added to the contract for supply chain and Southern California Edison
scheduling delays related to the six new service cabinets.
FISCAL IMPACT:
The FY 2021-22 Streetlight Improvement Project was included in the FY 2022-23 Capital
Improvement Program budget as a re -budget. The Neighborhood Enhancement Fund
(536) is used for projects that enhance neighborhood aesthetics and functionality and is
funded via surplus general funds. General Fund was also used for the project. Funds for
the construction contract were expended from the following accounts:
Account Description
Neighborhood Enhancement
General Fund
Account Number
53601-980000-22V02
01201927-980000-22V02
Total:
hue
$ 343,029.66
$ 386,125.02
$ 729,154.68
FY 2021-22 Streetlight Improvements Project (Harbor View Hills) —
Notice of Completion for Contract No. 7661-3 (22V02)
June 13, 2023
Page 3
ENVIRONMENTAL REVIEW:
On November 30, 2021, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(c) (replacement of existing
utility facilities involving negligible expansion of capacity) of the CEQA Guidelines,
California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a
significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
Iz
Attachment A
JOHN WAYNE
AIRPORT
NOT TO SCALI
FY 2021-22 STREETLIGHT
IMPROVEMENT PROJECT
(HARBOR VIEW HILLS)
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7661-3 1 11 /16/21