HomeMy WebLinkAboutPA2023-0034_20230206_Hetherington Final Report 4-7-2021HETHERINGTON ENGINEERING, INC.
SOIL & FOUNDATION ENGINEERING• ENGINEER ING GEOLOGY • HYDROGEOLOGY
Gerson Bakar and Associates
c/o Park Newpo1t Apait ments
One Park Newporl Drive
Newporl Beach, California 92660
Attention: Mr. Jim Diaz
Facilities Manager
April 7, 2021
Project No. 8564.1
Log No. 21378
Subject: GEOTECHNICAL OBSERVATION or RO CK 1VIESH ANCHORING
INSTALLATION AND TESTING
West of Unit 4830
Park Newport Apartments
One Park Newport Drive
Newp01t Beach, California
References: Attached
Dear Mr. Diaz:
In accordance with your request, this report provides a summary of our geo techn.ical
services in conjunction with the drilling, installation and testing of rock mesh anchoring
for the emergency ro ckfall mitigation of the main scarp of the June 26, 2020 landslide at
the subject site based on plans prepared by Kane Geotech, Inc. (Reference 6). The
drilling and rock mesh anchoring installation were performed by Access Limited
Construction, between Februru·y 10 and March 18, 2021, with continuous geotechnical
observation by Hetherington Engineering, Inc.
Our services during installation of the rock mesh anchoring consisted of the following :
• Observation of drilled holes for compliance with minimwn diruneters and depths to
accommodate the specified grout diameler and length dimensions for the tlU'eaded bar
anchors.
• Observation of threaded bar anchor installations in the completed drilled holes to
confirm compliance with specified anchor bar lengths.
• Confirmation of proper grouting of the installed threaded bar anchors.
• Preparation of this report swnmarizing our geotechnical observation of the rock mesh
anchoring installation and testing.
5365 Avenida Encinas, Suite A • Carlsbad, CA 92008-4369 • (760) 931-1917 • Fax (760) 931 -0545
333 Third Street, Suite 2 •Laguna Beach, CA 92651-2306 • (949) 715-5440 •Fax (760) 931-0545
www. hetheringtonengineering. com
6 - Geotechnical Final Report
GEOTECHNICAL OB SERVATION OF ROCK MESH ANCHORING
INSTALLATION AND TESTING
Project No. 8564.1
Log No. 21378
April 7, 2021
Page 2
DESCRIPTION OF ROCK MESI-J ANCIIORS
A total of 3 sacrificial, 46 production, 8 border cable, and 4 spot anchors were installed in
support of the rock mesh surficial slope stabilization system. Our report of the locations
and numbering of the rock mesh anchoring are shown on Rock Mesh Anchor Plan,
Figure 1 , which is based on Sheel 2 of the "Park Newport Apartments Back Bay Drive,
Surficial Slope Stabilization and Rockfall Mitigation, Newport Beach, California" plan
set, by Kane GeoTech, Inc. (Reference 6).
The thJeaded anchor bars and wire-rope anchors were installed in the drilled holes in the
face of the slope. The tlu·eaded anchor bars consisted of Williams Grade 75 ATB epoxy
coated threaded bars. The ·wire-rope anchors consisted of 5/8-inch diameter IWRC, 6xl 9
wire rope (double legged). The threaded anchor bars were installed with SCH 40 PVC
centralizers, spaced at a maximum of 10-feet on center. The anchors were installed in
holes that were drilled at inclinations ranging from 15 to 18-degrees from horizontal,
where the slope inclination exceeded 70-degrees. Where the slope inclination was less
than 70-degrees, anchors were installed in holes that were drilled perpendicular to the
slope face. The original threaded bar and wire rope anchor specifications are shown on
Geobrugg Tecco G65/4 Surfi cial Slope Stabilization System Details, Figure 1, which is
an excerpt of Sheet 3 (Reference 6). Revised anchor specifications were issued by Kane
GeoTech, Inc. in a Memorandum, dated February 19, 2021 (Reference 8).
OBSERVATION OF ROCK MESH ANCHOR INSTALLATION
Drilling for rock mesh anchors was accomplished with 3.5 and 4-inch-dian1eter cl own
hole hammer drill and hand drill with 100 rope thread drill steel. No groundwater or
caving was encountered while drilling. The holes for the sacrificial verification anchors
were drilled to a length of 10-feet as specified on the plans, Sheet 3 (Reference 6). The
holes for the production and spot anchors were drilled to a length of 12-ft. The holes for
the border cable anchors were drill ed to a length of 10-ft. Information pertaining to the
drilling and installation of the rock mesh anchors is provided in Rock Mesh Anchor
Summary, Table I.
The tlu·eaded bar and wire rope anchors were installed and grouted. Complete
encasement of the bonded zones of the anchors with grout was assured by pun1ping until
grout flowed out of the holes. Dates on which the grouting occuned for each anchor are
shown in Rock Mesh Anchor Summary, Table I.
HETHERINGTON ENGINEERING, INC.
GEOTECl-INICAL OBSERVATION OF ROCK MESII ANCHORING
INSTALLATION AND TESTTNG
Project No. 8564.1
Log No. 21378
April 7, 2021
Page 3
VERIFICATION (PRE-PRODUCTION) ANCHOR TESTING
Performance testing o[ three sacrificial verification anchors was performed in accordance
with the Post Tensioning Institute (PTI) DC35. 1-14, Construction Drawings, and Project
Specifications (References 6, 7, and 9). Anchor performance testing was performed using
a 39-lon center-hole hydraulic ram and lcmporary cribbing and steel load frame setup.
The hydraulic ram was placed over the anchor bar and seated on the load frame. A steel
plate was fixed to the end of the threaded anchor bm to facilitate displacement
measuremen ts. A caliper bearing against the steel plate and supported on an independent
reference frame was setup to measure the !breaded bar anchor displacement.
The verification anchors were performance tested by cyclically and incrementally loading
and unload ing the anchor to the maximum test load (133% of the design load) or failure.
Loading of the anchor was accomplished by increasing the hydraulic pressure of the ram
in correspondence with calculated load pressures determined from the calibration sheet
supplied with the ram. A copy of the ram calibra tion sheet is provided as Hydraulic Ram
Calibration Sheet, Figure 1. After an initial alignment load of 25% of the design load
was applied, movement of the tendons was recorded for pressures corresponding to 50,
100, 125 and 150-percent of design load. Anchor testing acceptance criteria was provided
in the Proj ect Specifications (Reference 7). The results of proof testing for each
verifi cation anchor are provided in the Verification Anchor Performance Testing,
Appendix A.
During performance testing, sacrificial verification anchors SA-1 , SA-2, and SA-3 were
loaded to failure. Failure was defined by the design engineer in Memorandum No. 1,
dated February 19, 2021 (Reference 8), to be a load at which the anchor grout movement
was 1.0-inch or greater. The load at fai lure for SA-1, SA-2, and SA-3 was 18.2, 36.4, and
27.3 kips, respectively. The performance testing data was provided to the design
engineer, Bill Kane, of Kane GeoTech.
The verification anchor testing prompted the design change reconunendations by Kane
Geotech outlined in Reference 8. The reconunendations included the following: bar
anchor depths should be a minimum of 12-ft and grouted per specification, wire rope
anchor depths should be minimum of 9-ft, drill hole diameter should be a minimum of
3.5-inches, and no further anchor testing will be required.
HETHERINGTON ENGINEERING, INC.
OEOTEC.E-fNICAL OBSERVATION OF ROCK MESII ANCHORING
INSTALLATION AND TESTING
Project No. 8564.1
Log No. 21378
April 7, 202 1
Page 4
CONCLUSIONS
Based on our observati ons, it is our opinion thal the rock mesh anchors insta ll ed for lhe
surficial slope stabilization and rockfall mitigation at the subject site are in substantial
compliance wi th the referenced plans and specifications .
LIMITATIONS
Our observations were performed using the degree of care and skill ordinarily exercised,
under similar circumstances, by reputable geotechni cal consultants practicing in this or
similar localities. No other warranty , expressed or implied, is made as to the conclusions
and professional advice included in thls report.
This opportunity to be of service is appreciated and we hope this information is helpful to
you. Please call ifthere are any questions or inqui.J:es.
Respectfully submitted,
HETHERINGTON ENGINEERING, INC.
a ·
Civil Engineer 30
Geotechnlcal Eng.'il''1t~
(expires 3/3 1 /22)
£L p_ -------
Edwin R. Cunningham
Civil Engineer 81687
(expires 10/3 1/22)
Attachments: Plate 1
Plate 2
Figure 1
Table I
Appendix A
HETHERINGTON ENGINEERING, INC.
GEOTECilNICAL OBSERVATION OF ROCK MESH ANCHORING
INSTALLATION AND TESTING
Project No. 8564.1
Log No. 21378
Aprjl 7, 2021
Page 5
Distribution: 3-Addressee
1-via e-mail Ken Dressel (kdresscl@gba.com)
I-via e-mail Jim Diaz Qdiaz@gba.com)
I -via e-mail William Kane (William.kane@kanegeotech.com)
HETHERINGTON ENGINEERING, INC.
REFERENCES
l. Hetherington Engineering, Inc., "Geotechnical Summary of Landslide Miligalion,
West of Unit 4830, Park Newport Aparlmenls, One Park Newport Drive, Newport
Beach, California", daled July 21, 2020.
2. Hetherington Engineering, Inc., "Proposed Rockfall Mitigation, West of Unit 4830,
Park Ncvvport Apartmenls, One Park Newport Drive, Newport Beach, Cali [ornia",
elated September 4, 2020.
3. Hetherington Engineering, lnc., "Proposed Emergency Rockfall Mitigalion, Wesl of
Unit 4830, Park Newport Apartments, One Park Newpo1i Drive, Newport Beach,
California", dated January 6, 202 1.
4. Kane Geotech, In c., "Park Newport Apartments, Back Bay Dri ve, Rockfall
Assessment Letter, Newport Beach, Cali fornia", dated August 20, 2020.
5. Kane Geotech, Inc., "Park Newport Apartments, Surficial Slope Stabiliza tion and
Rockfall Mitigation, Engineering Design Calculation Repo.rl, Newport Beach,
California", dated August 20, 2020.
6. Kane Geotech, Inc., "Park Newport Apartments, Back Bay Drive, Surficial Slope
Stabilization and Rockfall Mitigation, Newport Beach, California", dated August 20,
2020 (Sheets 1 through 5).
7. Kane Geotech, Inc., "Park Newport Apartments, Surficial Slope Stabilization and
Rockfall Mitigation (Proj ect Specifications), Newport Beach, California", dated
August 20, 2020.
8. Kane Geotech, Inc., "Park Nev1porl Anchor Testing, Revised Anchor Depths,
Memorandum No.I", dated February 19, 202 1.
HETHERINGTON ENGINEERING, INC.
Project No. 8564.1
Log No. 21378
N
ROCK MESH ANCHOR PLAN
GEOTECHNICAL CONSULTANTS
HETHERINGTON ENGINEERING,INC.
PROJECT NO. PLATE NO.
012
5 1015200
S C A L E : 1 " = 1 0'
Park Newport ApartmentsNewport Beach, California
8564.1 1
LEGEND
APPROXIMATE LOCATION OF PRODUCTION ANCHOR
APPROXIMATE LOCATION OF SPOT ANCHOR
APPROXIMATE LOCATION OF BORDER CABLE ANCHOR
APPROXIMATE LOCATION OF SACRIFICIAL ANCHOR
7BCA8
SA3
SP5
7PA7
7BCA8
7BCA7
7PA6
7PA7
7PA57PA47PA37PA27BCA6
7BCA5
7PA1
6PA1
5PA1
3PA1
4PA1
2PA1
1BCA2
1BCA1
1PA1
1PA2 1PA3 1PA5 1PA6
1BCA3
1BCA4
2PA6
3PA7
4PA6
6PA6
6PA2 6PA3 6PA4
1PA4
2PA2 2PA3 2PA4 2PA5
3PA2 3PA3 3PA4
3PA5
3PA64PA24PA3
4PA4
4PA5
6PA5
5PA2
5PA3
5PA4
5PA5
5PA6
5PA7
SP1
SA3
SA1SP2SP3
SP4
SP5
SA2
SURFICIAL SLOPE STABILIZATION DETAILS
GEOTECHNICAL CONSULTANTS
HETHERINGTON ENGINEERING,INC.
PROJECT NO. PLATE NO.
NOT TO SCALE Park Newport ApartmentsNewport Beach, California
8564.1 2
~ ----------
Caltrans Transportation Laboratory
Date: 1 /1 5/2021 Contract No.:
Name of System: RACH 3010 Location: SAC-10
Jacl< No.: TE-10 Bridge:
Contractor Gauge #: Gauge A Contractor Gauge #: Gauge B
Load Cell Run 1 Run 2 Run 3 Average Run 1 Run 2 Run 2 Average (l<ips)
PSI PSI PSI PSI PSI PSI PSI PSI
10 1350 1400 1400 1383 1350 1300 1300 1317
20 2600 2700 2700 2667 2650 2600 2600 2617
30 4000 4000 4000 4000 3900 3900 3900 3900
40 5300 5300 5300 5300 5200 5200 5200 5200
50 6500 6500 6500 6500 6400 6400 6400 6400
Load Cell:
Verification Date:
HYDRAULIC RAM CALIBRATION SHEET
HETHERIN GTON ENGINEER ING, INC.
Parl< Newport Apa1i ments
New12ort Beach, CA
GEOTECHNICAL CONSULTA NT S PROJECT NO. 8564.1 I FIGURE NO. 1
Tendon Drilling I nformation
Rock
Mesh AnchOT Free Bonded Length Date Anchor Length Length Length Drilling Method Drilled No. (ft) (ft) (ft) Drilled (ft)
SAl 11 3 6 2/11/2021 Down Hole Hammer Drill 10
SA2 11 3 6 2/11/2021 Down Hole Hammer Drill 10
SA3 I 11 3 6 2/11/2021 Down Hole Hammer Drill 10
lBCAl 11 3 7 2/12/2021 Hand Drill 10
15CA2 11 3 7 2/12/2021 Hand Drill 10
1BCA3 11 3 7 2/12/2021 Hand Drill 10
1BCA4 11 3 7 2/12/2021 Hand Drill 10
7BCAS 11 3 7 2/23/2021 Hand Drill 10
7 BCA6 11 3 7 2/23/2021 Hand Drill 10
7 BCA7 11 3 7 2/19/2021 Hand Drill 10
7 BCAS ll 3 7 2/19/2021 Hand Drill 10
lPAl 13 3 9 2/16/2021 Hand Drill 12
1PA2 13 3 9 2/16/2021 Hand Drill 12
1PA3 13 3 9 2/17/2021 Down Hole Hammer Drill 12
1PA4 13 3 9 2/17/2021 Down Hole Hammer Drill 12
l PAS 13 3 9 2/17/2021 Hand Drill 12
1PA6 13 3 9 2/17/2021 Hand Drill 12
2PA1 13 3 9 2/17/2021 Hand Drill 12
2PA2 13 3 9 3/1/2021 Hand Drill 12
2PA3 13 3 9 2/26/2021 Down Hole Hammer Drill 12
2PA4 13 3 9 2/25/2021 Down Hole Hammer Drill 12
2PAS 13 3 9 3/1/2021 Hand Drill 12
2PA6 13 3 9 2/17/2021 Hand Drill 12
TABLE I
Surficial Slope Stabilization System
Park Newport Apartments, One Park Newport, Newport, California
ROCK MESH ANCHOR SUMMARY
Grouting
Drilled Initial Post-second
Inclination Post-Date Diameter Grouting Grouting
(inches) {degrees) Date Dat e Grouting Tested
Date
4 15 2/11/2021 2/16/2021
4 15 2/11/2021 2/16/2021
4 15 2/11/2021 2/16/2021
3.5 90 3/4/2021
3.5 90 3/4/2021
3.5 90 3/4/2021
3.5 90 3/4/2021
4 3/4/2021
4 3/4/2021
4 3/4/2021
4 3/4/2021
3.5 77 3/4/2021
3.5 80 3/4/2021
3.5 65 3/4/2021
3.5 72 3/4/2021
3.5 65 3/4/2021
3.5 67 3/4/2021
3.5 75 3/4/2021
3.5 15 3/4/2021
4 16 3/4/2021
4
16 3/4/2021
3.5 17 3/4/2021
3.5 18 3/4/2021
TABLE I --Page 1 of 3
Performance Testing
Total
Creep Design Elongation after 10 Load -at 1330/o of minutes D.L. D.L. (inches) at 1330/o (kips) D.L.
(inches)
36.4
36.4
36.4
Lock Off
Pressure
(psi)
I
I
I
Lock Off
Load
(kips)
HEi
Notes
Anchor failed @ 18.2 kips
Anchor failed @ 36.4 kips
Anchor failed @ 27 .3 kips
Project No. 6577.l
Log NO. 21310
Tendon Drilling Information
Rock
Mesh Anchor Free Bonded Length
Anchor Length Length Length Date Drilling Method Drilled No. (ft) (ft) (ft) Drilled (ft)
3PA1 13 3 9 2/18/2021 Hand Drill 12
3PA2 13 3 9 2/26/2021 Hand Drill 12
3PA3 13 3 9 2/25/2021 Down Hole Hammer Drill 12
3PA4 13 3 9 2/24/2021 Down Hole Hammer Drill 12
3PA5 :3 3 9 2/24/2021 Down Hole Hammer Drill 12
3PA6 13 3 9 2/23/2021 Hand Drill 12
3PA7 13 3 9 2/23/2021 Hand Drill 12
4PA1 13 3 9 2/18/2021 Hand Dnll 12
4PA2 13 3 9 2/23/2021 Down Hole Hammer Drill 12
4PA3 13 3 9 2/24/2021 Down Hole Hammer Drill 12
4PA4 13 3 9 2/24/2021 Down Hole Hammer Drill 12
4PA5 13 3 9 2/24/2021 Down Ho!e Hammer Drill 12
4PA6 13 3 9 2/25/2021 Hand Drill 12
5PA1 13 3 9 3/1/2021 Hand Drill 12
5PA2 13 3 9 2/23/2021 Down Hole Hammer Drill 12
5PA3 13 3 9 2/24/2021 Down Hole Hammer Drill 12
5PA4 13 3 9 2/18/2021 Down Hole Hammer Drill 12
SPAS 13 3 9 2/18/2021 Down Hole Hammer Drill 12
5PA6 13 3 9 2/22/2021 Hand Drill 12
5PA7 13 3 9 2/25/2021 Hand Drill 12
6PA1 13 3 9 2/22/2021 Down Hole Hammer Drill 12
6PA2 13 3 9 2/18/2021 Down Hole Hammer Drill 12
6PA3 13 3 9 2/18/2021 Down Hole Hammer Drill 12
TABLE I
Surficial Slope Stabilization System
Park Newport Apartments, One Park Newport, Newport, California
ROCK MESH ANCHOR SUMMARY
Grouting
Second Drilled Initial Post-
Diameter Inclination Grouting Grouting Post -Date
(inches) (degrees) Date Date Grouting Tested
Date
3.5 16 3/4/2021
3.5 15 3/4/2021
4 17 3/4/2021
4 17 3/4/2021
4 16 3/4/2021
3.5 16 3/4/2021
3.5 15 3/4/2021
3.5 16 3/4/2021 I
4 15 3/4/2021
4 15 3/4/2021
4 17 3/4/2021
4 17 3/4/2021
3.5 16 3/4/2021
3.5 15 3/4/2021
4 15 3/4/2021
4 47 3/4/2021
" 44 3/4/2021
4 45 3/4/2021
3.5 15 3/4/2021
3.5 3/4/2021
4 so 3/4/2021
4 45 3/4/2021
4 45 3/4/2021
TABLE I --Page 2 of 3
Performance Testing
Total
Creep Design Elongation after 10 Load -at 1330/o of minutes D.L. D.L. (inches) at 1330/o (kips) D.L.
(inches)
I
I
I
Lock Off
Pressure
(psi)
I
Lock Off
Load
(kips)
HEi
Notes
Proiect No. 8577 .1
Log No. 21310
Tendon Drilling Information
Rock
Mesh Anchor Free Bonded Length Date Anchor Length Length Length Drilling Method Drilled No. (ft) (ft) (ft) Drilled (ft)
6PA4 13 3 9 2/18/2021 Down Hole Hammer Drill 12
6PA5 13 3 9 2/22/2021 Down Hole Hammer Drill 12
6PA6 13 3 9 2/22/2021 Down Hole Hammer Drill 12
7PA1 13 3 9 2/23/2021 Down Hole Hammer Drill 12
7PA2 13 3 9 2/22/2021 Down Hole Hammer Drill 12
7PA3 13 3 9 2/22/2021 Down Hole Hammer Drill 12
7PA4 13 3 9 2/22/2021 Down Hole Hammer Dnll 12
7PA5 13 3 9 2/22/2021 Down Hole Hammer Drill 12
7PA6 13 3 9 2/19/2021 Down Hele Hammer Drill 12
7PA7 13 3 9 2/19/2021 Down Hole Hammer Drill 12
SPl 13 3 9 2/23/2021 Down Hole Hammer Dnll 12
SP2 13 3 9 2/2S/2021 Down Hole Hammer Drill 12
SP3 13 3 9 2/24/2021 Down Hole Hammer Drill 12
SP4 13 3 9 3/1/2021 Hand Drill 12
TABLE I
Surficial Slope Stabilization System
Park Newport Apartments, One Park Newport, Newport, California
ROCK MESH ANCHOR SUMMARY
Grouting
Drilled Initial Post-Second
Inclination Post-Date Diameter Grouting Grouting
(inches) (degrees) Date Date Grouting Tested
Date
4 4S 3/4/2021
4 42 3/4/2021
4 lS 3/4/2021
4 30 3/4/2021
4 42 3/4/2021
4 so 3/4/2021
4 so 3/4/2021
4 47 3/4/2021
4 47 3/4/2021
4 40 3/4/2021
4 lS 3/4/2021
4 17 3/4/2021
4 16 3/4/2021
3.5 40 3/4/2021
TABLE I-· Page 3 of 3
Performance Testing
Total
Creep Design Elongation after 10 Load -at 133% of minutes D.L. D.L. (inches) at 1330/o (kips) D.L.
(inches)
Lock Off
Pressure
(psi)
I
Lock Off
Load
(kips)
HEi
Notes
Proi ecr No. 8S77.l
Log No. 21310
APPENDIX A
(Verification Anchor Performance Testing)
HETHERINGTON ENGINEERING, INC.
Project No. 8564.l
Log No. 21378
Project Name: Park Newport
Project Number: 8564.1
In spector: ERC
PERFORMANCE TEST
Design Load DL 36.4 Kips
Ram Calibration Slope 0.0077
Stressing Length 9 feet
Free Length (Lf) 1 feet
Bond Length (Lb) 6 feet
Area (A) 0.79 sq. inches
Modulus of Elasticit~ E 28000 l<si
Dial Measured
Load Load Pressure Time Reading Elongation
(%of DL (kips) (psi) (minutes) (inches) (inches)
0.10 3.6 506 0.003 0.000
0.25 9.1 1215 2 0.473 0.470
0.10 3.6 506 3 0.433 0.430
0.25 9.1 1215 4 0.477 0.474
0.50 18.2 2397 5 1.011 1.008
0.10 3.6 506
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
0.10 3.6 506
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
0.10 3.6 506
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
1.20 43.7 5706
0.10 3.6 506
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
1.20 43.7 5706
1.33 48.4 6321
1.33 48.4 6321
1.33 48.4 6321 1
1.33 48.4 6321 2
1.33 48.4 6321 3
1.33 48.4 6321 4
1.33 48.4 6321 5
1.33 48.4 6321 6
1.33 48.4 6321 10
1.33 48.4 6321 15
0.10 3.6 506
Anchor Number: 1
Row:
Date Tested: 2/16/2021
Theo 80% Theo Theo
Elong. Elong. Elong.
LS LS LS+ 1/2Lb
(i nches) (inches) (inches)
0.018 0.014 0.024
0.027 0.021 0.036
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.154
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.1 16 0.092 0.154
0.1 60 0.128 0.213
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.154
0.160 0.128 0.213
0.195 0.156 0.261
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.154
0.160 0.128 0.213
0.195 0.156 0.261
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.21 9 0.175 0.291
0.219 0.175 0.291
0.219 0.1 75 0.291
0.219 0.1 75 0.291
0.000 0.000 0.000
HETHERINGTON ENGINEERING, INC
HETHERINGTON ENGINEERING, INC.
Project No.: 8564.1
Park Newport
VJ Q)
.<: u :§.
c 0 +:l Ill OJ c 0 i:iJ
8.580 ---I-
8.560 ---
8.540
8.520
8.500
8.480
8.460 -----
8.440
8.420 ----+--__ ,____
Creep Analyis For Performance Test
Time v. Elongation
Anchor No.: 1
Row No.:
Test Date: 2/16/2021
_,__
'---
-'--
-'---
1--l--+--'--
8.400 ~-----L-_ __J __ _L___J _ _J__J__L_j_4-------'---'----'--'----'--'--.!.-'--l
10 100
~-----Time lminut,~L...---~
Measured Elongation -•Creep Limit at 0.04 inches
HETHERINGTON ENGINEERING, INC.
Project No.: 4345.1
Belmont Slope Repair
Project Name: Park Newport
Project Number: 8564.1
Inspector: ERC
PERFORMANCE TEST
Design Load DL 36.4 l<ips
Ram Calibration Slope 0.0077
Stressing Length 9 feet
Free Length (Lf) 1 feet
Bond Length (Lb) 6 feet
Area (A) 0.79 sq. inches
Modulus of Elasticit E 28000 ksi
Dial Measured
Load Load Pressure Time Reading Elongation
(%of DL (kips) (psi) (minutes) (in ches) (in ches)
0.10 3.6 506 0.000 0.000
0.25 9.1 1215 0.057 0.057
0.10 3.6 506 0.007 0.007
0.25 9.1 1215 0.064 0.064
0.50 18.2 2397 0.331 0.331
0.10 3.6 506 0.202 0.202
0.25 9.1 1215 0.265 0.063
0.50 18.2 2397 0.360 0.158
0.75 27.3 3579 0.824 0.622
0.10 3.6 506 0.624 0.624
0.25 9.1 1215 0.670 0.670
0.50 18.2 2397 0.749 0.749
0.75 27.3 3579 0.872 0.872
1.00 36.4 4761 >1.00
0.10 3.6 506 11u~.1(1 1T1T1 I
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
1.20 43.7 5706
0.10 3.6 506
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
1.20 43.7 5706
1.33 48.4 6321
1.33 48.4 6321
1.33 48.4 6321 1
1.33 48.4 6321 2
1.33 48.4 6321 3
1.33 48.4 6321 4
1.33 48.4 6321 5
1.33 48.4 6321 6
1.33 48.4 6321 10
1.33 48.4 6321 15
0.10 3.6 506
Anchor Number. 2
Row:
Date Tested. 2/16/2021
Theo 8-0% Theo I Theo
Elong. Elong. Elong.
LS LS LS+ 1/2Lb
(inches) (in ches) (inches)
0.018 0.014 0.024
0.027 0.021 0.036
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.11 6 0.092 0.154
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.154
0.160 0.128 0.213
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.1 54
0.160 0.128 0.213
0.195 0.156 0.261
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.1 16 0.092 0.154
0.160 0.128 0.213
0.195 0.156 0.261
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.1 75 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.1 75 0.291
0.000 0.000 0.000
HETHERINGTON ENGINEERING, INC
'ii)
<ll .I:. (.) c:
c: 0 ·.;::; "' CJ c: 0 w
0.250
0.200 +--------
0.150
0.100
Bond Length Analys is For Performance Test
Load v. Elongati~n
Anchor No.:
Row No.: 2/16/2021
Test Date:
/ /
/
/
/
/
/
/
/
/
0.050+---------------1------.<-------~~--------~
/
/ /
/ ---.-' .· ~---
/
/ /
/
/
/
/
/
/
/
/
0.000~-----•t---.-------.------,.--------.---------.,..-----------,
0.00 5.00 10.00 15.00 20.00 25.00 30.00
Load (kips)
• Measured
------80% Stressing Length
---Stressing Length + 50% Bond Length
HETHERINGTON ENGINEERING, INC.
Project No.: 8564. 1
Park Newport
(i)
Q)
.!: (.) c
c ~ ro Cl c 0
jjj
8.580 I---
Creep Analyis For Performance Test
Time v. Elongation
Anchor No.: 2
Row No.:
Test Date: 2/16/2021
8.560 1-------+---+---+---+-------l
8.540 +----------;----+----+--
8.520
8.500
8.480
8.460 _, ____ _
8.440 _, ____ _
8.420 -1--------1----+-------l---+---+-+--I
10
~---------'-J.llJJ"-LLLU0LL1.Llfe£.1_ __ ~
---+--Measured Elongation -•creep Limit at 0.04 inches
HETHERINGTON ENGINEERING, INC.
100
Project No.: 4345.1
Belmont Slope Repair
Project Name: Park Newport
Project Number: 8564.1
Inspector: ERC
PERFORMANCE TEST
Design Load DL 36.4 l<ips
Ram Calibration Slope 0.0077
Stressing Length 9 feet
Free Length (Lf) 1 feet
Bond Length (Lb) 6 feet
Area (A) 0.79 sq. inches
Modulus of Elasticity E) 28000 l<si
Dial Measured
Load Load Pressure Time Reading Elongation
(%of DL (kips) (psi) (minutes) (inches) (inches)
0.10 3.6 506 0.013 0.000
0.25 9.1 1215 0.098 0.085
0.10 3.6 506 0.062 0.049
0.25 9.1 1215 0.102 0.089
0.50 18.2 2397 0.326 0.313
0.10 3.6 506 0.229 0.216
0.25 9.1 1215 0.273 0.260
0.50 18.2 2397 0.340 0.327
0.75 27.3 3579 0.866 0.853
0.10 3.6 506
0.25 9.1 1215 ·1 I ~· I ~: ·1 t) I · 1 ·I I 1 i
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
0.10 3.6 506
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
1.20 43.7 5706
0.10 3.6 506
0.25 9.1 1215
0.50 18.2 2397
0.75 27.3 3579
1.00 36.4 4761
1.20 43.7 5706
1.33 48.4 6321
1.33 48.4 6321
1.33 48.4 6321
1.33 48.4 6321 2
1.33 48.4 6321 3
1.33 48.4 6321 4
1.33 48.4 6321 5
1.33 48.4 6321 6
1.33 48.4 6321 10
1.33 48.4 6321 15
0.10 3.6 506
Anchor Number. 3
Row:
Date Tested: 2/16/2021
Theo 80% Theo Theo
Elong. Elong. Elong.
LS LS LS+ 1/2Lb
(inches) (inches) (inches)
0.018 0.014 0.024
0.027 0.021 0.036
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.11 6 0.092 0.154
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.154
0.1 60 0.128 0.213
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.154
0.1 60 0.128 0.213
0.195 0.156 0.261
0.000 0.000 0.000
0.027 0.021 0.036
0.071 0.057 0.095
0.116 0.092 0.154
0.160 0.128 0.213
0.195 0.156 0.261
0.219 0.1 75 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.219 0.175 0.291
0.2 19 0.175 0.291
0.219 0.175 0.291
0.000 0.000 0.000
HETHERINGTON ENGIN EERING, INC
Ii> QJ .c (j c
~
c 0 :;:: ro
Ol c 0
i.'ii
Bond Length Analysis For Performance Test
Load v. E longati~n
Anchor No.:
Row No.: 2/16/2021 Test Date:
0.350 ~-------------
0.300+-----------------------------------~
/
I
I
I
/
I
I
0.250 --1---------------------------/-------------
0.200 -
0.150
/
/
/
I
I
I
/
/
/
/
/
I
/
I
,I
I
/
______L __________ _
I
I
I
I /
0.100+-------------'-1------------------------~
,'
0.000 -!--------~-----~-----~-----~-----~------,
0.00 10.00 20.00 30.00 40.00 50.00 60.00
Load (kips)
• Measured
------80% Stressing Length
---Stressing Length + 50% Bond Length
HETHERINGTON ENGINEERING, INC.
Project No.: 8564.1
Park Newport
Ci> <ll .c 0 c
c: ~ ro OJ c: 0 w
8.580
Creep Analyis For Performance Test
Time v. Elongation
Anchor No.: 3
Row No.:
Test Date: 2/16/2021
8.560 !~------+------+--+--
8.540 -!----------+-----+-
8.520
8.500
8.480
8.460~-----
8.440 ~~----
8.420 ·'--------+------1--~>----+--I-
10
~------'-ime..Un.ioutes_\, __ ~
---&-Measured Elongation -•creep Limit at 0.04 inches
HETHERINGTON ENGINEERING, INC.
100
Project No.: 4345.1
Belmont Slope Repair