P ROJECT R EVIEW R EQUEST
C OMMUNITY D EVELOPMENT D EPARTMENT
Planning Division Please Distribute to:
Building – WQMP & Grading – Public Works – Fire/Life Safety –
Date: April; 19, 2023
Please return PRR and Plans to Staff Planner
Joselyn Perez, Associate Planner 949-644-3312, jperez@newportbeachca.gov
Applicant & Contact:
Michael Coon, AIA
michaelcoonarchitects@gmail.com 949-375-1736
Project Name Hosseinzadeh Residence
Address: 3033 Bayside Drive
(PA2023-0070) Variance, Coastal Development Permit
Request for a variance and coastal development permit to exceed floor area limit, height limit, and to
encroach into required setbacks to construct an approximately 1,083 sq. ft. addition to a single unit dwelling and convert the dwelling into a 3-story, two-unit, dwelling.
REPORT REQUESTED BY: May 3, 2023
Planning Commission HEARING DATE: TBD
Check all that apply:
No comments on the project
as presented.
Notes:
1. Automatic fire sprinklers will be required for the following condition: New construction or addition/reconstruction which exceeds 2,000 sf. and 50% of the area of the existing structure will require installation of a fire sprinkler system throughout the
structure. NBMC 15.04.120 Where the valuation of the permit for the remodel or renovation is equal to or exceeds 50% of the market value of such building the entire building shall comply with the code
provisions for new construction. Exception: Permits having a valuation less than $320,700.00. NBMC 15.02.060
Sprinkler drawings and hydraulic calculations to be submitted to plan check and approved prior to issuing a building permit, or, list under ‘Deferred Submittals” on cover sheet. Provide a note on the drawing stating: “Obtain fire sprinkler permit prior to calling for roof sheathing inspection.”
Duplex shall have independent fire risers from each separate water meter.
Application of Standard Code requirements are not expected to alter the project design.
Recommended conditions of approval are attached.
Application of Standard Code requirements or the attached
conditions of approval will substantially impact or alter the design of the project.
I contacted the applicant on
To schedule an appt. for
Code review To discuss the following (see notes)
Tmplt: 10/10/12
James Gillespie 3354 5/4/23
Signature Ext. Date Please indicate the approximate time spent on reviewing this project: