HomeMy WebLinkAbout09 - Gateway Park Improvements — NOC of Contract No.8791-1 (23L01)Q �EwPpRT
CITY OF
s NEWPORT BEACH
`q44:09 City Council Staff Report
August 22, 2023
Agenda Item No. 9
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer,
tandefur@newportbeachca.gov
PHONE: 949-644-3321
TITLE: Gateway Park Improvements — Notice of Completion of Contract
No.8791-1 (231-01)
ABSTRACT:
On January 10, 2023, the City Council awarded Contract No. 87976-1, Gateway Park
Improvements, to Armstrong Cal Builders, Inc. (Armstrong Cal) of Signal Hill, California.
The project consisted of replacing turf and landscaping, reconstructing landscape walls,
and installing new lights and signage. The work is now substantially complete and staff
requests City Council acceptance and closeout of the contract.
RECOMMENDATIONS:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of the
Civil Code; and
c) Release the Faithful Performance Bond one year after acceptance by the City Council.
DISCUSSION:
Overall Contract Cost/Time Summary
Award Contract
Final Cost at
Total Contract
Percent Contract
Amount
Completion
Change Amount
Cost Change
$ 540,233.50
$ 569,283.47
+$ 29,049.97
+5.4%
Allowed Contract Time (days)
83
Actual Time
Under (-) or Over (+)
-15
The work necessary for the completion of this contract consisted of a complete landscape
refresh at the two park areas. Old vegetation was replaced. New palm trees were installed
along with groundcover and accent plants. New lighting and signage was installed. A
previously closed walkway was repaved and reopened between Newport Boulevard and
the Lido Marina Village.
9-1
Gateway Park Improvements — Notice of Completion of Contract No. 8791-1 (231-01)
August 22, 2023
Page 2
The contract has been completed to the satisfaction of the Public Works Department. A
summary of the construction cost is as follows:
Original Bid Amount:
$
540,233.50
Actual Cost of Bid Items Constructed:
$
540,233.50
Total Change Orders:
$
29,049.97
Final Contract Cost:
$
569,283.47
The project incurred five change orders. Additional demolition costs were approved for
the unusually thick concrete pathway on the Lido side of the park; additional waterproofing
was added to the existing planters; an existing electrical pull box was moved to clear the
way for a palm tree planting; the existing wall on the Balboa side was given an additional
coating to match the new portions of the wall; and a sprinkler lateral line was added to the
Balboa turf grass area for better coverage.
A summary of the project schedule is as follows:
Estimate Start of Construction per Annual Baseline Schedule November 15, 2022
Actual Start of Construction per Notice to Proceed April 3, 2023
Extended Contract Completion Date Inclusive of Extra Work July 28, 2023
Actual Substantial Construction Completion Date July 5, 2023
FISCAL IMPACT:
The Gateway Park Improvements Project was included in the FY 2022-23 Capital
Improvement Program (CIP) Budget, Landscape Enhancement Program. Neighborhood
Enhancement funds were used for the design and construction of the project. The
Neighborhood Enhancement fund was developed for installation or rehabilitation of
various citywide improvements, including landscape projects that beautify
neighborhoods.
Funds for the construction contract were expended from the following budget accounts.
Account Description Account Number Amount
Neighborhood Enhancement 53601-980000-23L01 $ 569,283.47
Total: $ 569,283.47
ENVIRONMENTAL REVIEW:
On January 10, 2023, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Class 2 Section 15302 (c) (reconstruction
of existing public facilities involving negligible or no expansion of capacity) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential to have a significant effect on the environment.
9-2
Gateway Park Improvements — Notice of Completion of Contract No. 8791-1 (231-01)
August 22, 2023
Page 3
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
9-3
ATTACHMENT A
nmm�n� � ► �°
n still
IIIIIIIIII/ '� i��
IIIIIIII/: _ � �j�i
- LIMITS OF WORK
GATEWAY PARK ENHANCEMENT
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-8791-2 221-01 10/25/22