HomeMy WebLinkAbout03 - Concrete Replacement Program FY 2022-23 (Project No. 23R06) - NOC for Contract No. 8921-1Q SEW Pp�T
CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
September 12, 2023
Agenda Item No. 3
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Andy Tran, Senior Civil Engineer, atran@newportbeachca.gov
PHONE: 949-644-3315
TITLE: Concrete Replacement Program FY 2022-23 (Project No. 23R06) —
Notice of Completion for Contract No. 8921-1
ABSTRACT:
On February 14, 2023, the City Council awarded Contract No. 8921-1 for the Concrete
Replacement Program project to Towo Enterprise, Inc. The work is now complete and
staff requests City Council acceptance and close out of the contract.
RECOMMENDATIONS:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded Contract
Final Total Contract
Total Contract
Percent Contract
Amount
Amount
Change Amount
Cost Change
$1,096,200.00
$1,202,865.87
+$106,665.87
+9.7%
Allowed Contract Time + Approved
72
Actual Time Used (Days)
72
Extensions (Days) _
This project included replacing deteriorated concrete sidewalks, driveway approaches,
curbs and gutters, and access ramps and tree removals within the Irvine Terrace,
Corona del Mar and Shorecliffs neighborhoods. This project also included the
construction of sidewalks at Corona del Mar High School and Ensign Intermediate School
through a reimbursement agreement with Newport -Mesa Unified School District (District).
3-1
Concrete Replacement Program FY 2022-23 (Project No. 23R06) —
Notice of Completion for Contract No. 8921-1
September 12, 2023
Page 2
The contracted work has been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original Bid Amount:
$
1,096,200.00
Actual Cost of Bid Items Constructed:
$
1,067,226.50
Total Change Orders:
$
135,639.37
Final Contract Cost:
$
1,202,865.87
The final total contract amount was $1,202,865.87, which was approximately 9.7 percent
higher than the original bid amount. This cost increase was primarily due to additional
quantities of concrete driveway and cross gutters that were added to the project to repair
damaged areas. There were also six additional large tree removals necessary that were
identified by the City Arborist during the course of work.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule February 27, 2023
Actual Start of Construction Per Notice to Proceed April 3, 2023
Extended Contract Completion Date Inclusive of Extra Work July 18, 2023
Actual Substantial Construction Completion Date July 18, 2023
Additional working days were added to the contract to complete change order work that
were not part of the original contract.
FISCAL IMPACT:
The Concrete Replacement Program was included within the FY 2022-23 Capital
Improvement Program (CIP) Budget. Funds for the construction contract were expended
from the following accounts:
Account Description
General Fund
Newport -Mesa Unified School District
Neighborhood Enhancement
Account Number
01201927-980000-23R06
13501-980000-23R06
53601-980000-23R06
Total:
Amount
$ 947,150.00
$ 100,257.50
$ 155,458.37
$ 1,202,865.87
In accordance with the Reimbursement Agreement for the new sidewalk expansion at
Corona del Mar High School and Ensign Intermediate School, the District will reimburse
the City the total amount of $104,267.80. This total reimbursement amount includes a
four percent administration fee.
The Neighborhood Enhancement Fund (536) is used for projects that enhance
neighborhood aesthetics and functionality and is funded via surplus general funds.
3-2
Concrete Replacement Program FY 2022-23 (Project No. 23R06) —
Notice of Completion for Contract No. 8921-1
September 12, 2023
Page 3
ENVIRONMENTAL REVIEW:
On February 14, 2023, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301(c), Class 1 (maintenance
of existing public facilities involving negligible or no expansion of use) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
3-3
ATTACHMENT A
JOHN WAYNE
AIRPORT
NOT TO SCALE
CONCRETE REPLACEMENT PROGRAM
FY 2022-23
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-8921-1 1 9/12/2023
3-4