HomeMy WebLinkAboutWASTE TO ENERGY FACILITY111111111 lill 11111111111111111111
*NEW FILE*
WASTE TO ENERGY FACILITY
Preliminary
Feasibility Study
WASTE•TO-ENERGY
02 a
FACILITY
PRELIMINARY
FEASIBILITY STUDY
FOR A
WASTE -TO -ENERGY FACILITY
IN THE
CITY OF NEWPORT BEACH
CALIFORNIA
PREPARED BY THE
OFFICE OF THE CITY MANAGER
FEBRUARY 141 1983
C
ACKNOWLEDGMENTS
Many documents and interviews were used to prepare this report. Many private
1 engineering consultants contributed their time and provided copies of studies
prepared for other jurisdictions. Portions of those studies were used
liberally in the preparation of this report. The City Manager's Office
retains the responsibility for the accuracy of this report but acknowledges
the contributions of the following firms:
Blyth Eastman Paine Webber, Inc.
Brown and Caldwell
CH2MHill
Cooper and Clark
CSI Resources Systems Incorporated
Eijumaily-Sutler Associates
Engineering Science
Franklin Associates, Ltd.
KVB Inc.
Metcalf & Eddy Inc.
Mitre Corporation-Metrek Division
II
II
IZ
IJ
II
i
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY AND RECOMMENDATIONS 1
CHAPTER I CURRENT PRACTICES AND COSTS I-1
COLLECTION PRACTICES I-1
DISPOSAL PRACTICES I-1
MSW VOLUMES I-2
COLLECTION AND DISPOSAL COSTS I-6
FUTURE DISPOSAL COSTS I-7
COMMERCIAL HAULERS 1-8
CHAPTER 11 MSW DISPOSAL COST REDUCTION
IMPOSE REFUSE FEE II-1
RECYCLING OR RESOURCE RECOVERY 1I-2
ALTERNATE DISPOSAL SITES AND
TRANSFER STATIONS II-2
WASTE -TO -ENERGY FACILITY II-5
CHAPTER III WASTE -TO -ENERGY TECHNOLOGY III-1
BICONVERSION
III-1
Composting
III-1
Anaerobic Digestion
11I-2
PYROLYSIS
III-3
REFUSE DERIVED FUEL (RDF)
III-4
MASS BURNING
III-6
Refractory Lined vs. Waterwall
Furnaces
III-8
Modular (Controlled Air)
Incineration
III-8
Stoker Fired Units
III-11
Rotary Furnaces
III-13
RDF Fired Units
III-14
CMI-ENCON COMBINATION
II1-16
ii
TABLE OF CONTENTS
Page
CHAPTER IV ENERGY MARKETS IV-1
ELECTRICITY
IV-1
STEAM
IV-3
METHANE GAS
IV-5
REFUSE DERIVED FUEL
IV-5
SOIL AMENDMENTS
IV-5
DESALINATED WATER
IV-5
SECONDARY MATERIALS MARKET
IV-6
CHAPTER V LEGAL AND ADMINISTRATIVE
REQUIREMENTS
V-1
WASTE STREAM GUARANTEES
V-1
MARKET GUARANTEES
V-2
SITE GUARANTEES
V-2
PROCUREMENT
V-2
CONSTRUCTION AND OPERATION
GUARANTEES
V-5
FINANCING OPTIONS
V-6
Conventional Revenue Bonds
V-6
Industrial Development Bonds
V-7
Lease Revenue Bonds
V-8
Leveraged Leasing
V-8
Private Debt and Equity
V-9
PERMITS
V-10
City of Newport Beach Permits
V-10
Air Pollution Permits
V-10
Ash Disposal Authorization
V-11
Sold Waste Facility Permit
V-11
CHAPTER VI ECONOMIC FEASIBILITY
VI-1
COMPOSTING
VI-1
ANAEROBIC DIGESTION
VI-1
PYROLYSIS
VI-1
REFUSE DERIVED FUEL (RDF)
VI-2
MASS BURNING STOKER UNITS
VI-4
MODULAR CONTROLLED - AIR UNITS
VI-5
CMI-ENCON
VI-8
O'CONNOR COMBUSTOR
VI-9
CONCLUSIONS ON ECONOMIC FEASIBILITY
VI-10
iii
TABLE OF CONTENTS
Page
CHAPTER VII ENVIRONMENTAL IMPACTS
VIZ-1
DESCRIPTION OF PROJECT
VII-1
LOCATION OF PROJECT
VII-
ENVIRONMENTAL IMPACTS AND
MITIGATION MEASURES
VII-1
Air Quality
VII-1
Vehicle Traffic
VII-2
Noise
VII-2
Odor and Dust
VII-3
Vectors
VII-3
Aesthetics
VII-3
Safety
VII-3
APENDIX A CALCULATIONS FOR MSW DISPOSAL
COST REDUCTION ALTERNATIVES A-1
iv
LIST OF TABLES
Page
I-1
Annual Volumes of City
Collected MSW
1-3
I-2
Typical NSW Compositions
I-5
I-3
1982-83 MSW Handling Costs
I-6
I-4
Annual Dumping Fee Increases
1-7
1-5
MSW Disposal Hauling Costs
per Mile
I-8
II-1
1982-83 MSW Costs per Dwelling
Unit
II-2
11-2
Transfer Station Costs
II-4
12-3
Comparison of MSW Disposal Cost
Reduction Alternatives
II-6
IV-1
SCE Energy Payment Schedule
IV-2
IV-2
SCE Capacity Payment Schedule
IV-2
IV-3
SCE Avoided Cost Payments
IV-3
IV-4
Prices for Recovered Materials
IV-7
V-1
Risk Sharing Under Alternative
Prqcurement Approaches
V-6
VI-1
Economics of RDF
VI-3
VI-2
Economics of Stoker Units
VI-5
VI-3
Economics of Modular Units
VI-7
VI-4
CMI-ENCON Revenues Per Ton MSW
VI-9
v
LIST OF FIGURES
Page
I -A
Monthly Refuse Volumes
I-4
III -A
RDF Processing
III-5
III-B
Mass Burning
III-7
III-C
Modular Unit
III-9
III-D
Stoker Mechanisms
III-12
III-E
O'Connor Combustor
III-14
vi
EXECUTIVE SUMMARY AND RECOMMENDATIONS
A waste -to -energy facility has the potential to save the City several hundreds
of thousands of dollars each year in refuse disposal costs. However, such
facilities require large capital expenditures and present both financial and
environmental risks. Private industry will participate in such a venture and
assume most of the financial risk. Therefore, it is recommended that the City
of Newport. Beach continue to pursue a waste -to -energy project by first
selecting and approving a suitable site.
CURRENT PRACTICES AND COSTS
The City collects approximately 50,000 tons of assorted municipal solid wastes
(MSW) each year and disposes of it at the Coyote Canyon landfill. Seasonal
differences vary the daily average collections between 100 TPD (tons per day)
in January to 160 TPD in July. The City will spend approximately $1.5 million
in fiscal 1982-83 to collect and haul MSW. Additionally, the County imposed
dump fees in October, 1981, at $4.90 per ton. This fee will rise to $7.00 per
ton on July 1, 1983 and will cost the City approximately $310,000 in fiscal
198344. Dump fees may continue to escalate considering that the national
average is $10 per ton and the Orange County system requires major capital
improvements.
Hauling costs may also increase in future years if the Coyote Canyon landfill
closes and the City is forced to haul to a much more distant site. Every mile
of hauling distance costs the City approximately $16,500 annually in vehicle
and labor costs, and alternate landfill sites may add 10 to 15 miles to the
hauling distance. In sum, additional disposal costs will total hundreds of
thousands of dollars in coming years.
MSW DISPOSAL COST REDUCTION ALTERNATIVES
Several alternatives were investigated to determine their potential for
lowering City costs. These included alternate disposal sites, a transfer
station, a trash fee, and waste -to -energy facilities. As demonstrated on the
following table and excepting the trash fee alternative, a waste -to -energy
facility provides the most potential for cost reduction.
1
COMPARISON OF MSW
DISPOSAL COST REDUCTION ALTERNATIVES
(1982-83 Dollars)
Total
Hauling
Annual
Annual
Additional
Cost
Other
Cost to
Alternative
Base Costs
Dump Fee sl
Difference
Difference
City
Continue to dump
at Coyote Canyon
$lt500,000
$310,000
-0-
-0-
$1,810,000
Dump at Bee Canyon
$lt500,000
$310,000
+$243,000
-0-
$2,053,000
Dump at Hntg.Beach
Transfer Station
$1,500,000
$478,000
+$ 72,000
-0-
$2,050,000
Dump at new County
Transfer Station
near JWA
$1,500,000
$478,000
-$ 94,000
-0-
$1,884,000
Build and Operate
a Transfer Station
for the City at
the City Yard
$lt500>000
$310,000
-$188,000
+$402,000
$2,024,000
(TS costs)
Waste -to -Energy
w/$5 per ton fee
located mid -point
in City
$1,500,000
$224,000
-$ 94,000
-0-
$1,630,000
Waste -to -Energy
w/$0 per ton fee
located at
City Yard
$1,500,000
$ 10,000
-$142,000
-0-
$1,368,000
bpose Refuse Fee
$1,500,000
$310,000
-0-
-$1,491,000
$ 319,000
(fees
collected)
$7/o1 at landfills and $10.80/ton at County Transfer Stations
2
II
WASTE -TO -ENERGY TECHNOLOGY
Dozens of technologies exist to convert MSW to saleable energy. Simple
techniques like composting and theoretical ones like pyrolysis are available,
and each has individual pluses and minuses. However, after much
experimentation, most consideration is now given to successfully operating
incineration techniques that produce steam and/or electricity. Pretreatment
of MSW to separate and shred it to produce Refuse Derived Fuel (RDF) before
incineration also has been a successful technique. A very promising but as
I yet untested technology involves digesting presorted MSW with waste water to
produce pipeline quality natural gas and then burning the sludge to produce
steam and/or electricity. Incineration techniques include several stoker type
units that churn burning refuse and mix it with air. , Several rotary furnace
units and many types of simple modular incinerators are available. Each
technology has various advantages and disadvantages.
0 ENERGY MARKETS
Electricity and natural gas are the most easily marketed products of a
waste -to -energy facility. Southern California Edison by law must buy all the
electricity that can be produced and has indicated a strong desire to buy any
natural gas that can be produced. Recovered materials like ferrous metals,
aluminum, and glass are also marketable, but the volume and prices will yield
relatively little income. Steam may be sold to Mobil Oil in West Newport; to
Hoag Hospital, and to the Hughes Company. There are only limited markets for
other potential products such as compost, soil amendments, pyrolytic fuel oil,
refuse derived fuel, or desalinated water. Only electricity, natural gas, and
steam have good markets near Newport Beach.
Energy prices paid to small producers declined during 1982 and are expected to
stabilize over the next few years. Southern California Edison paid 8.2G/Kwh
in January, 1982, and only 6.624/Kwh in December, 1982. Forecasts for
exponentially rising energy costs heard often in the past few years are being
reevaluated. Declining demand, conservation, the oil glut, cogeneration, and
waste -to -energy projects are serving to limit price increases. Accordingly,
promises of future revenues to balance the costs of a waste -to -energy facility
must be weighed carefully.
LEGAL AND ADMINISTRATIVE REQUIREMENTS
A major public work, a waste -to -energy facility requires permits and approvals
from many institutions and requires extensive contractual and financial
assurances.
Sufficient amounts of MSW must be guaranteed as well as energy product sales.
Many facilities have suffered for lack of both.
Site approval is critical. Many jurisdictions have spent large sums only to
find that they have no acceptable site. More than all other factors,
referendums and resident opposition have defeated proposed facilities.
Procuring a facility is a complicated task involving the mixing and matching
of both an organizational approach and bidding procedures. Possible
approaches include conventional A/E, turnkey, full service, or private
contractors. Bidding procedures include sealed, competitive, two-step
advertising, or sole source.
.r7
I
Construction and operation guarantees are necessary to protect against delays,
overruns, system failures, inflation, productivity losses, labor strikes, and
similar problems.
Financing can take the form of conventional revenue bonds, industrial
development bonds, lease revenue bonds, leveraged leasing, or private debt and
equity. The most profitable method, leveraged leasing, is extremely
complicated and requires special attorneys and IRS rulings.
Permits are required from many agencies starting with the City of Newport
Beach. The Zoning Code prohibits "incineration or reduction of garbage,
sewage,... or refuse." A waste -to -energy facility would require the following
permits:
City of Newport Beach
General Plan Amendment
Local Coastal Plan Amendment
Zoning Text and Map Amendment
Use Permit
Building Permit
EIR
• South Coast Air Quality Management District
Permit to Construct
Permit to Operate
• Regional Water Quality Control Board and Orange County
Health Care Agency
Ash Disposal Authorization
• California Solid Waste Management Board and Orange County
Solid Waste Enforcement Agency
Solid Waste Facility Permit
ECONOMIC FEASIBILITY
only privately financed facilities exhibit the potential to provide cost
savings to Newport Beach. Dumping fees, or tipping fees, at waste�to-energy
facilities represent the difference between costs and revenues. Revenue from
energy sales is not expected to equal debt service and operation costs within
the next few years. Smaller sized plants of the type required for Newport
Beach do not have the advantage of economy of scale. Debt service costs for
conventionally financed facilities necessitate tipping fees of $15 to $40 per
ton. Only tax leveraged private financing can reduce debt service costs to
the point where tipping fees are attractive to the City. Consequently, only
those technologies which are supported by private financing appear to be
economically feasible for Newport Beach.
I
2
ENVIRONMENTAL IMPACTS
Air quality, truck traffic, and aesthetics are the major concerns. Noise,
odor, dust, and safety impacts are more easily mitigated by enclosing all
operations in protective buildings. Air pollution will be strictly controlled
by expensive equipment, but trace quantities of hydrochloric acid, dioxin, and
heavy metals will be released to the atmosphere. Offsets may actually reduce
regional air pollutants. Vehicle traffic will be localized at the site, but
trip miles should be reduced overall. Architectural treatment and landscaping
can reduce aesthetic impacts, but refuse processing is rarely considered an
attractive neighbor. Generally, a waste -to -energy facility would have the
same environmental impacts as any other industrial process.
CONCLUSIONS AND RECOMMENDATIONS
A waste -to -energy facility in Newport Beach has the potential to save the City
hundreds of thousands of dollars each year while reducing overall
environmental impacts. However, substantial financial risks are involved, and
t environmental impacts will be shifted and concentrated.
f At the present time, it appears that only a privately financed facility which
produces steam, electricity, or natural gas is appropriate. The private
financing will reduce the tipping fee, and the energy markets will support
only those products. Only two technologies demonstrate that combination of
attributes and these are CMI-ENCON and O'Connor Combustor.
Both of these technologies present unanswered questions which will be
addressed during 1983 and 1984. Both are completing EPA tests for air
emissions, and both produce ash which is being tested for its disposal
classification. No CMI-ENCON plant is operating completely, and performance
values need to be confirmed. This and other necessary information will be
forthcoming and will better demonstrate the feasibility of each technology.
Siting is and will remain the biggest single obstacle to development of a
facility. Conversely, an approved site will generate enthusiastic financial
backing and ease the entire development process. Efforts to locate an
acceptable site can proceed while awaiting the information regarding the
CMI-ENCON and O'Connor technologies.
Based on the above findings, it is recommended that the City continue to
pursue a waste -to -energy facility but in a cautious manner. Because siting is
the most' critical factor, it is recommended that selection and approval of a
site precede all other efforts in order to minimize the risk of expending
considerable funds unproductively.
Site investigations can proceed using the requirements associated with the
1 CMI-ENCON and O'Connor technologies. Appropriately sized parcels can be
located and analyzed. Appraisals, property owner interviews, development
costing, and environmental analysis can be conducted at minimal expense. The
results of this analysis would provide the necessary information and
documentation to enable the City Council to approve a location for a
waste -to -energy facility within the City of Newport Beach. When, and if, an
acceptable site is approved, further development actions can be pursued with
more confidence and less risk.
5
CHAPTER I CURRENT PRACTICES AND COSTS
Collection and disposal of municipal solid wastes (MSW) in Newport Beach is
conducted by both City government and private haulers. This chapter explains
primarily the functioning of the City's operations in order to provide a basis
for understanding and evaluating the advantages of a waste -to -energy facility.
COLLECTION PRACTICES
The General Services Department collects most of the MSW within the City. The
Refuse Division collects trash and refuse from most residences, some
businesses and from City facilities. The Refuse Division collects only from
smaller cans, so multiple family units and businesses using large bins must
contract a private hauler. The Field Maintenance Division collects beach
refuse, street sweepings, and assorted debris. The General Services
Department owns and operates a fleet of assorted vehicles for this purpose.
The Utility Department collects and disposes of debris from its repair and
construction activities, and the Parks, Beaches, and Recreation Department
collects and disposes of cuttings and trimmings from its landscaping and tree
pruning activities.
The Refuse Division collects trash from curbsides five days per week except
for an additional Saturday collection in beach areas during the twelve summer
weeks. Newspapers are also collected from curbside on monthly trash pickup
days and deposited in a storage bin at the City Yard where they are picked up
and paid for by a private recycling contractor. The City is divided into five
collection areas, one of which is serviced each Monday through Friday. The
Refuse Division collections service approximately 23,000 dwelling units and
150 businesses.
The Field Maintenance Division collects trash from the ocean beach areas using
a large (38 cubic yard) load packer, special sand sifters, and assorted
hauling vehicles. The 38 yard packer averages three loads per week throughout
the year, but may run five or six loads per week during the summer. Street
sweepings and assorted debris are collected from locations scattered
throughout the City and from accumulations deposited at the City Yard.
DISPOSAL PRACTICES
Disposal of all MSW is at the County operated landfill at Coyote Canyon. Each
collection vehicle travels to the landfill, and there are no transfer
operations.
I-1
Vehicle routes vary within certain patterns. All refuse collection vehicles
are parked overnight at the City Yard on Superior Avenue. Each workday the
vehicles travel to the collection area and then make one or more trips to the
landfill. Routes between the City Yard, the collection areas, and the
landfill vary according to the hour, day, and season, depending on traffic,
road conditions, and driver preference. Generally refuse vehicles utilize
major streets such as 17th Street, Irvine Avenue, Pacific Coast Highway,
Jamboree Road, Ford Road, and MacArthur Boulevard, to go from the City Yard to
the collection areas and to Bonita Canyon Road leading to the landfill.
Vehicles returning to the City Yard from the landfill generally traverse
Bristol Street, Irvino Avenue, and 17th Street to arrive oh Superior Avenue.
A map of collection areas and routes is contained in Appendix A.
MSW VOLUMES
MSW is normally measured in tons but no scales are used to weigh the City's
refuse. The weight of MSW is estimated based on cubic yard volumes and the
rated weight capacity of each vehicle. Orange County residents typically
generate 3.5 lbs/day of residential MSW.
MSW generation per population or dwelling unit in Newport Beach is difficult
to determine. The City experiences large fluctuations in population and
occupancy during the year. Tourists may number 20,000 to 100,000 on any given
day with peaks during the summer months. Residential trash sometimes is
difficult to separate from beach refuse. occupancy per unit may rise in
summer months. Nevertheless, annual volumes of City -collected MSW (as
currently measured) have remained relatively constant on a per -dwelling -unit
basis. Accordingly, projections of future MSW volumes can be reasonably
extrapolated from past records on the basis of the number of dwelling units.
The following tables present a variety of statistics on the refuse volumes
generated and collected within the City.
I-2
NUMBER OF
DWELLING UNITS
MSW SOURCE
RESIDENTIAL
COMMERCIAL
SPECIAL
NEWSPAPERS
BEACH CLEANINGS
STREET SWEEPINGS
UTILITIES2
PBR TRIMMINGS2
TABLE I - 1
CITY OF NEWPORT BEACH
ANNUAL VOLUMES OF CITY -
COLLECTED MSW IN TONS
YEAR
1980-81 1981-82 1982-83-BuILDOUT
(ESTIMATED)'(ESTIMATED)
31,285 32,182
32,332 38,0001
29,082
28,547
29,IE00
34,515
4,815
4,810
4,900
5,000
99
83
100
120
1,117
1,296
1,235
1,500
9,236
8,027
8,500
10,000
2,895
2,497
2,800
3,000
1,400
2,100
TOTAL (TONS/YR) 50,744
1,400
2,100
48,760
1,400
2,100
50,435
SOURCE: GENERAL SERVICES DEPARTMENT,
MONTHLY ACTIVITY REPORTS,
1NEWPORT BEACH PLANNING DEPARTMENT
2DEPARTMENT ESTIMATES
I-3
1,600
2,300
58,035
IH
i
F
Figure z-1
1g80-82 Monthly Volumes of MSW
Collected by the City of Newport Beach
Key:
N=Newspapers
B=Beach Cleaning
C=Commercial
R=Residential
Source: General Services Activity Reports Oct. 80 to Sept. 82
'� W r W "" W U$ We ft W M A 'a* 00 00 00 Me
COMPONENT
Combustibles
Paper
Cardboard
Newspaper
Misc. Paper
Paper Subtotal
Plastic
Rubber, Leather
Textiles
Lumber
Garbage
Yard Waste
Total Combustibles
Noncombustibles
Metals
TABLE I- 2
TYPICAL MSW COMPOSITION
LONG BEACH LOS ANGELESa SAN DIEGOb SAN FRANCISCOo NATIONALe
THIS STUDY 1973 1975 AREA--1977 1979
11.72
3.7
15.0
17.6
---
6.32
11.3
5.1
6.0
--
20.56
25.2
36.3
25.0
-
38.60
40.2
56.4
48.0
33.5
6.35
2.3
5.6
2.0
3.6
1.02
0.5
0.9
1.Od
2.6
2.86
2.3
2.4
2.0d
2.0
3.07
2.1
2.7
2.Od
3.2
8.48
5.4
4.2
--
17.0
20.90
33.1
17.5
23.0
17.5
81.28
85.9
89.7
78.0
79.4
Ferrous 4.65 5.2 4.9 6.0 8.0
Aluminum 1.45 ** 0.9 0.5 0.9
Other Nonferrous ** 0.9 ** 0.2 0.3
Metal Subtotal 6.10 6.1 5.8 6.7 9.2
Glass 11.69 7.3 4.2 8.0 9.9
Miscellaneous 0.93
(Rock,dirt,etc.)
0.7
0.3
7.3
1.5
Total Noncombustibles 18.72 14.1 10.3 22.0 20.6
Total 100.0 100.0 100.0 100.0 100.0
a Envirogenies Systems Co. "System Engineering Analysis of Solid Waste Management
in the SCAG Region" June 1973.
b Stanton, Stockwell, Henningson, Durham & Richardson "Southern California Urban
Resource Recovery Project" December 1976.
c Brown & Caldwell, State Solid Waste Management Board "Bay Area Solid Waste
Management Project, Phase I" February 1977.
d Assumed breakdown of 5% leather, rubber, textiles and lumber.
e 1980 Resource Recovery Update, by NCRR.
** Not evaluated separately.
I-5
COLLECTION AND DISPOSAL COSTS
The City will pay approximately $1,493,000 in fiscal 1982-83 to collect MSW
and haul it to the Coyote Canyon landfill. The City will pay an additional
$138,000 in 1982-83 for dumping fees which were instituted in October, 1982,
at approximately $4.90 per ton. Street sweepings and trimmings are exempt
from dump fees. These costs are summarized on Table I-3.
TABLE 1 - 3
City of Newport Beach
1982-83 MSW Handling Cost
General Services Department
Refuse Division
Budget $1,025,655
Revenue Sharing 287,700
Newspaper Revenue (34,610)
Total Net Cost $1,278,745
Field Maintenance Div.
Beach Cleaning
(collection & hauling)
Street Sweeping & Misc.
(hauling only)
Sub -Total
Utilities Department
(hauling only)
Vehicles
Labor
Sub -Total
PBR Department
(hauling only)
Vehicles
Labor
Sub -Total
Dump Fees (EstimatedI
Refuse Division
Field Maintenance Div.
Utilities
Sub -Total
$ 150,000
36,710
$ 186,710
$ 7,293
2,357
$ 9,650
$ 12,155
6,442
$ 18,597
$ 109,058
24,738
4,050
$ 137,846
TOTAL $1,631,548
From Oct. - Nov. 182 Actuals and 180-82 Monthly Activity Reports.
I-6
FUTURE DISPOSAL COSTS
Dumping fees and possibly hauling costs will increase in the future. The
$4.90 per ton dumping fee is slated to increase to $7.00 ton July 1, 1983.
(Initial administration of the fee is averaging $4.50 per�ton for the City,
but more experience should raise that to the full figure.) Further increases
are very possible as the national average is $10 per ton, and the Orange
County system requires major capital improvements.
Additionally, the Coyote Canyon landfill may close and necessitate hauling to
much more distant locations. One alternative site is Bee Canyon in the north
Irvine area which adds more than 16 miles to the average roundtrip to the
landfill. Each additional mile of hauling distance costs the City
approximately $16,492. These costs are detailed on the following tables:
TABLE I-4
ANNUAL DUMPING FEE INCREASES
2003
(projected
1982-83
buildout)
Tons Subject to Fees
44,300
51,235
Total Fee @ $4.90/ton
$217,070
$251.050
Total Fee @ $7.00/ton
310,100
358,645
Total Fee @ $10.00/ton
443,000
512,350
I1 From Table I-1
a
I-7
c
�a
TABLE I - 5
City of Newport Beach
MSW Disposal Hauling
Costs Per Mile
Vehicle
0 & M
Labor Cost
Total
Trips
Annual
Type
Cost/Mile
Per Mile3
Vehicle
Per Year to
Cost
@ 25 MPH
Cost/Mile
Land Fill
Per Mile
Refuse Div.
29 YD
$1.3351
$ .708
$2.04
1512
$ 3,084
16 YD
0.795i
1.198
1.99
4452
8,860
10 YD
0.47
1.198
1.67
204
341
Field Main.
Div.
38 YD
$1.0251
$
.986
$2.01
144
$ 290
All Others
1.00
.51
1.51
1608
2,428
Utility Dpt.
$1.30
$
.59
$1.89
288
$ 544
PBR Dept.
$1.00
$
.53
$1.53
624
$ 945
TOTAL
$16,492
Assumes open road costs are 50% of total mileage costs which
include expensive stop and go collection miles.
2 From Oct. - Nov, experience and 182 vehicle logs.
3 See Ap
pendix A
COMMERCIAL HAULERS
Private hauling companies collect refuse from most businesses and some
residences. The City collects only 45 gallon or 50 pound containers, and
multiple family units and businesses using large dumpster bins must contract a
private hauler. The commercial haulers licensed to operate in Newport Beach
are hesitant to disclose the volumes they collect. However, given the large
number of commercial establishments within the City, it is assumed that
commercial haulers could supplement the City collections to provide a total of
200 TPD to 250 TPD of MSW.
I-8
iI
CHAPTER II MSW DISPOSAL COST REDUCTION ALTERNATIVES
Expected refuse disposal cost increases may be offset by several methods which
are discussed in this chapter.
IMPOSE REFUSE FEE
The Newport Beach Municipal Code requires the costs of refuse collection and
disposal to be defrayed solely from property tax revenues. Most other cities
in the County collect some sort of fee to defray refuse costs and, thus, pass
increases to the property owner. Because the pertinent City Code section was
created by the initiative process, another vote would be required to amend it.
Imposition of a trash fee probably would require the City to handle the fees
for all refuse service. Because the City collects refuse only from small
containers, some residences and most businesses need to contract private
refuse haulers. Refuse fees are normally collected through the property tax
bills on a per unit basis. To provide uniformity, the City would need to
collect fees from all property owners and pay private haulers as needed.
Possibly the City could cease its refuse collection operations and simply
collect fees and hire private haulers.
Disposal of refuse such as street sweepings, tree trimmings and utility debris
would still need to be accomplished by the City. Thus, only the costs of
trash pickup and perhaps beach cleaning could be passed directly to property
owners. Because property taxes would not decrease with the imposition of a
refuse fee, those residents now receiving City refuse collection service would
experience increased costs.
Those residents and businesses now using private haulers only would switch the
address to which they send their payment. As indicated on the following
table, the City could defray current residential collection and disposal costs
by imposing a refuse fee of approximately $54.88 per dwelling unit, per year.
The City, of course, could impose a lower fee to defray only part of the
costs.
TABLE XI - 1
1982-83 MSW Costs Per Dwelling Unit
Refuse Division Costs
(from Table I - 3) $1,278,745
Refuse Division Collections
(from Table I - 1) 35,635 tons
Collection Cost per Ton $35.88
Dump Fee (1983) 7.00
Total Cost $42,88 per ton
Average Dwelling Units Generates
(at 3.5 lbs/day and 2.01 persons/ ) 1.28 tons/year
Average Annual Cost Per
Dwelling Unit $ 54.88
RECYCLING OR RESOURCE RECOVERY
The City on many occasions has investigated various recycling processes and
has discovered them to be largely impractical and not cost effective. The
City practices newspaper recycling and both reduces its hauling costs and
recovers $30,000 to $40,000 each year from this program. Problems with other
recycling programs, at this point in time, include cumbersome and expensive
separation requirements, high transportation costs and poor markets. Even if
these problems were overcome, recycling could provide no more than a 20-25%
reduction in refuse volume. The City will continue to investigate recycling,
but at this time, it is not an attractive solution to the waste disposal cost
problems.
ALTERNATE DISPOSAL SITES AND TRANSFER STATIONS
If the Coyote Canyon landfill closes, the City may be faced with increased
costs to haul to more distant disposal sites. At this time, neither the life
span of Coyote Canyon or its replacement site is known. Three likely
alternative disposal sites have been investigated to determine potential
savings in hauling costs. (None of these alternatives would help reduce
dumping fees.)
II-2
U
1 Bee Canyon, in the unincorporated County territory near MCAS, E1 Toro, is the
site planned by the County of Orange to replace Coyote Canyon. However,
attempts by the County to purchase the site from The Irvine Company have
failed, and a condemnation trial is anticipated. Additional costs to haul MSW
to Bee Canyon are summarized on Table II - 3.
The County of Orange also operates a refuse disposal transfer station in
Huntington Beach which has an indefinite life span. The hours of operation
are currently very restricted due to insufficient capacity. However, if
Coyote Canyon closes without a replacement, it is expected that the Huntington
Beach Transfer Station will be expanded and upgraded. Costs to haul refuse to
this site are summarized in Table II - 3.
New transfer stations could be constructed in a variety of locations. The
County of Orange has considered as lately as 1980 a new transfer station in
the vicinity of John Wayne Airport to service those communities which now have
direct access to Coyote Canyon. The site previously studied by the County
would reduce hauling distances for Newport Beach refuse disposal vehicles.
The maximum reduction in hauling distances would be provided by a transfer
station located at the City Yard on Superior Avenue. Such savings are
summarized in Table II
- 3.
In the absence of a new County transfer station, a
City constructed transfer
station is an option.
Costs for such a facility are
detailed in Table II - 2.
I
II-3
TABLE II - 2
Transfer Station Costs
(1982-83 Dollars)
Assumes capacity of 200 tons per eight hour day
Vehicles (2 hr round trip haul time)
Truck tractors (3) and trailers (4)
with 65 cubic yard capacity $ 475,0001
Annual 0 & M at $30,000 each tractor $ 90,000
Construction2
Building $ 110,000
Compactor and push pit $ 88,000
Land - $0 -
Labor (with 40% fringe)
Drivers (3 at $35,000/yr.) $ 1051000
Crew (2 at $28,000/yr.) $ 56,000
Annual Costs,
vehicles (amortized over 5 yrs. at 10%) $ 125,000
Buildings (amortized over 15 yrs. at 10%) $ 26,000
Vehicle 0 & M $ 90,000
Labor $ 161,000
Total Annual Cost $ 402,000
'City of Beverly Hills bid documents, April 1581.
2The Heil Co., Handbook of Transfer System Analysis, 1978,
inflated 10% per year to 1982.
II-4
WASTE -TO -ENERGY FACILITY
A waste -to -energy facility would convert the energy contained in refuse to
useable energy such as electricity or steam. Such useable energy can be sold
to defray the costs of refuse collection and disposal. Such a facility
located within the City would reduce hauling costs and vehicle maintenance.
such facilities have the potential not only to reduce or eliminate dumping
fees, but also to produce a profit.
Hauling costs would be reduced by a waste -to -energy facility located anywhere
in the City because all areas of the City are closer to the City Yard and to
the refuse collection areas than the Coyote Canyon landfill. Any potential
increased hauling distances necessitated by the closing of Coyote Canyon also
would be avoided. Additionally, time savings and maintenance cost savings
would be experienced because of the speed and ease of dumping from a concrete
surface rather than the rough, uneven working face of a landfill.
Reductions in dumping fees are dependent on energy markets, financing
arrangements, operational costs, and a variety of other factors which are
detailed later in this report. The tipping fee (or dumping fee) at a
waste -to -energy facility represents the difference between all costs and all
revenues. The cost savings over a range of performance values for a
waste -to -energy facility within the City are presented on Table II - 3.
Table II - 3 clearly indicates substantial potential cost savings resulting
from a waste -to -energy facility within the City, and the remainder of this
report addresses the feasibility of such a facility.
(Notes on Table II - 3)
Table II - 3 summarizes the cost reduction alternatives. Starting with the
Coyote Canyon baseline, the table presents the total annual cost differences
resulting from dump fees and hauling costs. The haul costs presented in Table
II - 3 are calculated in Appendix A. The dumping fee increases shown with the
County transfer station alternatives assume a $10.80 per ton fee when landfill
fees are $7.00 and assume a $15.43 fee when landfill fees are $10.00 per ton.
The hauling cost figure for the County transfer station near JWA assumes a
reduction of six miles in the round trip, and uses the per mile figure of
$16,492 from Table I - S. The hauling cost for the Newport Beach transfer
station subtracts the haul savings from the cost of the transfer station
appearing on Table II - 2. The dump fee savings for the waste -to -energy
alternatives assume that the tipping fee covers the dump fee for the residue,
and that Utility Department debris would still need to be hauled directly to
the County landfill.
The waste -to -energy alternative, with the $5 fee, assumes that the site is
located so as to take advantage of 50% of the $188,000 saving of hauling to
the City Yard. The waste -to -energy facility, with the $0 fee, assumes that
the site is located at the City Yard and assumes full advantages of the haul
cost savings except for Utility debris and street sweeping, which would still
need to be hauled directly to the landfill. The refuse fee alternative
assumes that all Refuse Division costs would be defrayed, but that Beach
cleaning dump fees and costs, and Utility dump fees would remain.
II-5
TABLE II - 3
Comparison of MSW Disposal
Cost Reduction Alternatives (1982-83 Dollars)
Annual Cost Increases
Total Annual Increase
Dump Fees
Haul
Above Original 1982-83
Costs
Budget
Disposal Site
at $7
at $10
with $7 Fee
with $10 Fee
Coyote Canyon
(base line)
$31OK
$443K
-$0-
$ 310,000
$ 443,000
Bee Canyon
+$243K
Total
$31OK
$443K
$243K
$ 553,000
$ 6860000
Huntington Beach
Transfer Station
,6h
+$168K
240K
+$ 72K
Total
$478K
$683
$ 72K
$ 550,000
$ 755,000
County Transfer
Station near JWA
,d
+$168K
$240K
-$94K
Total
$478K
$683K
-$94K
$ 384,000
$ 5899000
NB Transfer
Station at City Yd
-$188K
Gx
-0-
-O-
+$402K
Total
$31OK
$443K
$214
$ 524,000
$ 657,000
Waste -to -Energy
with $5/ton
Tipping Fee
LI
-$ 86K
$172K
-$ 94K
Total
$224K
$271K
( $ 94K)
$ 130,000
$ 177,000
Waste -to -Energy
with $O/ton
Tipping Fee and
located near City
Yard &
-$300K
$430K
-$142K
Total
$ 10K
$ 15K
($142K)
($ 132,000)
($ 127,000)
Impose Refuse Fee
0
-$30OK
$430K
-$1,300K
Total
$ IOK
$ 15K
$1,300K)
$i 290,000
$1,285,000
II-6
11
'1
CHAPTER III WASTE -TO -ENERGY TECHNOLOGY
The conversion of municipal refuse to energy can be accomplished in many ways.
This chapter describes most known technologies with emphasis on those with
proven performance. Each description includes some operating history of the
process and the known advantages and disadvantages of each technology.
BIOCONVERSION
This technology refers primarily to the conversion of the organic elements of
refuse into fertilizer and methane gas. Composting and anaerobic digestion
are the most common forms of bioconversion.
Composting
Solid waste composting in Europe and the Far East is currently practiced at
over.100 plants. Over the past 25 years, however, the composting facilities
established in the United States have met with little success, and all have
closed with the exception of the pilot -scale plant at Altoona, Pennsylvania.
The process for composting solid waste consists of three basic steps:
1. Coarse treatment - Shredding to uniform size
(smaller than two inches), hand-picking noncom-
postables, and magnetic separation of ferrous
metals.
2. Digestion - Aerobic or anaerobic bacteria and
fungi digest the waste, using methods that range
from windrows to mechanical digesters to stablize
the material and produce heat to kill pathogens.
3. Fine treatment - Shredding and screening to remove
dust and glass from the finished compost.
The basic technology of composting is well developed, and there are no real
technological barriers to making compost. The history of failure in the
United States is due primarily to inadequate markets. Compost from municipal
solid waste cannot qualify as a fertilizer because it is low in nutrients
(less than one percent nitrogen). Its main use is as a soil conditioner;
however, the value as a soil conditioner is low, and economics do not favor
any extensive shipment. In addition, compost has not proved to be a viable
alternative to composted manures and chemical fertilizers. The primary
benefits of composting from a solid waste management point of view appear to
be volume reduction, ferrous metals recovery, and production of a relatively
stable landfill material.
Reliability of composting is good because the technology is well developed and
the mechanical systems are not too sophisticated. A composting plant
following the coarse -treatment stage is relatively inflexible because it
cannot be easily adapted to new systems or converted to another use. The
system is easily expanded and therefore capable of handling changing waste
loads. The relatively long digestion period (10 to 15 days) requires sites
significantly larger than for most other resource recovery systems. As noted
in the next chapter, there is no market for composted refuse in Orange County.
Anaerobic Digestion
This technology, a type of bioconversion, involves breaking down the organic
portion of solid wastes and sewage sludge by bacteria and other anaerobic
microorganisms. Carbon dioxide and methane gas is a decomposition by-product.
The anaerobic digestion process consists of four steps:
1. Waste handling and mixing - Shredding and separating the organic
solid waste material through staged shredding and screening or hydro
pulping (wet separation of fibrous material) and mixing with sewage
sludge as a nutrient.
2. Digestion - Anaerobic digestion of the organic mass takes place in a
controlled environment and well -mixed reactor for a detention time
period of 5 to 45 days. The final products are methane and carbon
dioxide gas and sludge.
3. Methane gas treatment or direct use - Removal of moisture, carbon
dioxide, and traces of hydrogen sulfide gases produces
medium -quality methane gas (700 Btu per cubic foot). The generated
digester gas (300 Btu per cubic foot) may be used unprocessed in
equipment (boilers and engines) modified to burn this type of gas.
4. Residual sludge liquids would be separated from the digester sludge
by dewatering and returned to a sewage treatment plant. The
dewatered sludge (20 percent by volume, 50 percent by weight of
incoming waste stream) could be landfilled, incinerated, or land
spread as a soil amendment.
The relatively short detention time converts only 30 to 35 percent of the
solid waste energy content to methane. Up to 50,000 cubic feet of gas per 100
tons of refuse has been produced with retention times of up to 20 days.
Assuming the gas is used for steam production and the sludge is incinerated,
overall recovery efficiencies approach 40 percent. However, if the sludge is
not incinerated, the overall efficiency drops to 10 to 20 percent.
A demonstration size anerobic digestion system (50 to 100 tons per day) has
been constructed in Pompano Beach, Florida. Another system is operating in
Oklahoma City, and one is planned for Ventura, California. Such systems are
capital intensive; and because of the long digester storage times, significant
amounts of land are required as compared to other energy recovery systems.
III-2
I
Marketability of steam or gas is limited unless the plant can be located next
to potential customers or a natural gas transmission line. Transmission of
the gas or steam for distances in excess of one to two miles rapidly impacts
the economics of the system. In addition, large volumes of sewage are
required. This impacts system economics because credit cannot be claimed for
sludge -disposal costs that would be eliminated.
PYROLYSIS
Pyrolysis is the chemical decomposition of organic material by heating it in
the absence or near absence of oxygen. This process, the basis of petroleum
refining, as applied to solid waste involves feeding shredded municipal solid
waste into a controlled -atmosphere reaction vessel where it is heated or
partially burned. Pyrolysis differs from incineration in that it is
endothermic (heat absorbing) so that it takes 20 to 30 percent of the energy
content of the refuse to sustain the process. The primary products of this
process are:
° A gas primarily consisting of hydrogen, methane,
carbon monoxide, and carbon dioxide with 15 to
30 percent of the heating value of natural gas
° A liquid or oil that includes organic chemicals
such as acetic acid, acetone, and methanol and
water with 70 percent of the heating value of
No. 6 fuel oil
° A char or ash consisting of almost pure carbon
plus inerts such as glass and metals
The design and process controls such as temperature, pressure, and reaction
time determine which of the products predominates.
At least ten firms have developed a pyrolysis system; however, only three
systems have advanced to the demonstration or full-scale stage.
° Monsanto Corporation's "Landgard" system (Baltimore,
Maryland). Monsanto has withdrawn, and the full-
scale plant reopened following extensive modifications.
° Occidental Petroleum Corporation's "Garrett" process
(San Diego County, California). The demonstration
plant has been dismantled.
Union Carbide Corporation's "Purox" System (South
Charleston, West Virginia). The demonstration plant
operated successfully since 1974, but further develop-
ment depends on sale of full-scale process technology
and plant.
Recovery of the energy in solid wastes through pyrolysis gas and conversion to
steam is 50 to 60 percent efficient; however, recovery as a liquid oil is only
20 to 30 percent efficient. Because of shredding, it is possible to use
material recovery front-end processes along with pyrolysis to capture ferrous
and aluminum metals and glass. Landfilling of char and ash would be required.
'II
III-3
Pyrolysis should still be classified as a developing technology with none of
the processes identified for use in any of the presently planned resource
recovery systems. The problems with pyrolysis center on reliability
(technical problems) and cost considerations. Pyrolysis systems are not
flexible, and their high capital costs would make it impossible to abandon all
or part of a system to take advantage of future developments. Pyrolysis
systems have not yet been developed and produced in convenient modular systems
to allow phased expansion to handle future waste loads. Site availability
would be similar to that for other industrial facilities. Both the oil and
gas products have excellent heating and handling qualities for use in steam
boilers when compared to refuse -derived fuel (RDF). The oil does tend to
cause some corrosion problems.
REFUSE DERIVED FUEL (RDF)
This technology involves processing refuse into a fuel for use either as a
supplement to fossil fuels in conventional boilers or as an exclusive fuel in
specially designed boilers.
The RDF process can include any of a variety of shredding, flailing,
screening, separating, recovery, or classifier mechanisms to reduce the refuse
into highly flammable pellets, chips. fluff, or any other easily handled form.
Typically, 80 percent of municipal refuse can be processed into RDF. Several
such mechanisms are illustrated on Figure III -A.
There are currently 28 RDF systems under construction or operation in the
United States and more in various stages of planning and design. At present,
there are no RDF plants operating in the Southwestern U.S. Thirteen of the 28
produce RDF which is transported to a separate steam/power generating
facility. The other fifteen use RDF on site to fuel dedicated boilers. A
large RDF project is planned in Long Beach, California.
RDF plants cover a wide capacity range from small facilities of 100 TPD to
large systems of 3,000 TPD. The smaller facilities usually sell RDF to coal
fired power plants. The average size RDF plant firing dedicated boilers to
cogenerate steam and electricity is slightly over 1,700 tons per day.
Most of the RDF plants have experienced major problems in the materials'
handling section of the facility, RDF is very light, abrasive, and highly
viscous. Downtime has been very high at many sites as problems with
conveying, storing, and feeding the product into the furnaces have continued.
Howeveri proponents of RDF systems using dedicated boilers point to these
advantages compared to mass -burning facilities:
° Maximizes materials' recovery by separating recyclables
at front end.
Provides a cleaner, higher BTU fuel for combustion.
° Lower excess air requirements result in smaller air
pollution control devices, a smaller boiler, and
higher thermal efficiency.
° Less ash is produced which can affect significant
savings in ash hauling and disposal.
III-4
7� 60 IV it i♦ iMi so i* mai• owes it a it m em m !
FLAIL MILL
FERROUS
S' NOMINAL
MAGNETIC SEPARATOR
O
\ _TROMMEL
SHREDDER
4' NOMINAL
UNDERFLOW
AIR CLASSIFIER
OVERFLOW
H v
H
v+ AND DISPOSAL OR MATERIAL RECOVERY 4' DISC SCREEN
RDF
TO FUEL STORAGE
FIGURE III - A
RDF PROCESSING TRAIN
Disadvantages of this system include:
° operating experience at existing plants has proven that
fluff RDF is very difficult to handle and store. This
has lead to extensive modifications and downtime.
° The market for ferrous metals, which is the easiest
material to recover, is very weak at present.
° The most valuable material in the waste stream is
aluminum; however, a reliable process for selectively
removing aluminum from the waste stream has not yet
been demonstrated. Three emerging technologies offer
promise in this area: eddy current separation,
electrostatic separation, and dense media separation.
However, the RDF facility in New Orleans has opted for
hand-picking of aluminum cans after repeated failure
of new technologies to perform to specification.
Some plants have required millions of dollars in
modifications.
MASS BURNING
As the name implies, this technology involves the incineration of unprocessed
municipal refuse. Steam and/or electricity is produced by the waste heat from
the process.
The basic configuration of a mass burning facility is relatively consistent.
Refuse is delivered to an enclosed pit or tipping floor from where it is
charged into some sort of a furnace by a crane or a front loading tractor.
The refuse is burned as it moves over or through some conveying mechanism.
The heat from the process is recovered in a boiler to produce steam. Waste
gases are treated by air pollution control equipment and then released through
a stack. The remaining bottom ash and fly ash are collected and hauled to
a landfill. The general configuration of a mass burning facility is presented
on Figure III-B.
Numerous configurations of incinerators and boilers exist with various methods
of moving and stoking the burning refuse. The major variable features of
these facilities are described below:
III-6
W" i"" 6090" m o m I ft"" m ,r " m
Pit% I / a I
Heat
Recovery Precipitators
S
t
Heat a
Recovery c
r'1 k
0
Metal Magnetic Metal
Refractory Lined vs. Waterwall Furnaces
These two different linings of incinerator furnaces have varying properties
that affect their refuse burning characteristics. Refractory material acts as
a heat sink to absorb and retain heat from the combustion process. Refractory
materials typically are ceramic resembling brick, stone, or lava rock.
waterwall furnaces are formed by closely spaced waterfilled tubes that lower
incinerator temperatures and are an integral part of the steam generator.
Each of these two general types of furnaces have their own separate advantages
and disadvantages.
The refractory lined furnaces tend to have high but constant temperatures.)
Refractory walls will tend to absorb any small explosions which occur.
Slagging of refuse material on refractory walls will not harm the incineration
process. Combustion gases in refractory lined incinerators must be carefully
controlled to minimize fluctuations in oxidizing and reducing atmospheres that
promote boiler corrosion. Some heat recovery efficiency is lost in the
interest of obtaining a more complete burnout. Thus, refractory walled
furnaces tend to reduce refuse volumes at the expense of generating useable
energy. Refractory walled incinerators are well suited for continuous
operation, but their maintenance shutdowns are more time consuming. Common in
Europe, refractory walled municipal refuse incinerators have not yet been
operated in the United States.
Waterwall furnaces are, by far, the most widely used waste -to -energy
technology worldwide, and many are operating in the United States. Waterwalls
recover more radiant heat and easily produce super heated steam for the
generation of electricity. Steam rate fluctuations are more common however.
Boiler corrosion is minimized in waterwalls, but is replaced by soot buildup
which must be controlled by soot blowers. Water tubes are susceptible to
exploding refuse and must be protected. Maintenance is similar to refractory
lined furnaces, but waterwalls have demonstrated lower overall availability.
Waterwalls also tend to emit more carbon monoxide. Waterwalls are more
expensive to build than refractory lined units.
Modular (Controlled Air) Incineration
A modular incinerator is a small prefabricated combustion unit which normally
operates on a "controlled air" principle. Basically designed to be a low
polluting incinerator, this process only recently has been adapted to energy
recovery. I
The basic elements of a typical controlled air modular incinerator with
attached waste heat boiler are shown in Figure III-C. Combustion takes place
in two zones --the primary chamber and a secondary chamber, although at least
one manufacturer employs a third chamber as well. The incinerator's primary
combustion zone is filled with combustible refuse and ignited using a gas or
oil burner. The amount of air supplied to the primary chamber is maintained
at a level that is typically insufficient for complete combustion. The
resulting low air velocity in the primary chamber serves to minimize the
entrainment of particulates in the gas stream. Since air into the primary
chamber is limited, partial combustion takes place, along with partial
pyrolysis of the waste to a low Btu gas. This gas, consisting primarily of
carbon monoxide and low molecular weight hydrocarbons, rises into the
secondary chamber of the incinerator where complete combustion is assured by
the addition of excess air.
BOILER
RETURN
FIGURE III - C
CONTROLLED -AIR MODULAR INCINERATOR
TO AIR POLLUTION
CONTROL EQUIPMENT
CROSS SECTION VIEW
RECOVER( BOILER
LOADER
Both stages of combustion normally require. auxiliary fuel burners for
start-up, temperature control, and complete burnout. By a combination of
auxiliary fuel injection and air control, the primary chamber temperature is
maintained at about 1,400°F and the secondary at approximately 1,800°F. In
addition, the primary chambers are often equipped with water spray systems
which are automatically actuated when temperatures exceed the desired value.
Hot gases from combustion in the secondary chamber are directed through a heat
recovery boiler to produce steam. Because of the controlled combustion in the
two -stage incinerators, relatively low particulate levels are present in the
exhaust gases.
The process is similar to other technologies. Waste is initially received on
a tipping floor. Tractor operators, in response to a signal from an automatic
demand light, push the waste into the loading hopper of the incinerator from
which an operator -controlled hydraulic ram feeds the primary combustion
chamber. The loading cycle is automatic and interlocked to protect operating
personnel from exposure to the heat of incineration and to maintain controlled
air conditions in the incinerator. Ash and partially burned waste are
continually pushed through the primary chamber by transfer rams, movable
grates, or other means. The ash ultimately leaves the chamber and is water
quenched in a sump and then conveyed into a container to be hauled to the
landfill for final disposal.
Energy efficiencies and burnout are relatively low in comparison to other mass
burning technologies. Reported energy recovery rates range between 50 to 60
percent, even though manufacturers claim 70 percent. Ash residue is
reportedly 40 percent to 50 percent of the original refuse weight.
Consumat Systems has manufactured the most modular incinerators of the type
described above. Locations where Consumat controlled air incinerators burning
MSW are in operation include Auburn, Maine; Dyersburg, Tennessee; North Little
Rock, Arkansas; Salem, Virginia; Durham, New Hampshire; Windham, Connecticut;
and a number of others. Sizes of these facilities range from less than 50 TPD
to 200 TPD.
Another type of controlled air incinerator is manufactured by Basic
Environmental Engineering, Inc., Glen Ellyn, Illinois. Basic incinerators
utilize three -chamber combustion; the primary chamber is maintained at
stoichiometric combustion conditions, with excess air supplied to the dual
afterburners. The manufacturer states that the three -chamber design affords a
higher degree of controllability than is possible with two chambers.
Incinerators manufactured by Basic Engineering incorporate water tubes in the
combustion chamber to absorb the radiant heat of the burning process. Twenty
percent of the steam output is produced in this section. Another major
difference with this system is the use of a moving hearth in the larger sizes;
the wastes are "bumped" through the combustor, which serves to mix the refuse,
reportedly improving the burnout.
The manufacturer states that emissions from this incinerator will meet Federal
air emissions standards without the use of auxiliary pollution abatement
devices, provided that the wastes are not biased with sulfur products,
halogens products, or excessive metal oxides of lead, zinc, etc.
Basic's first installation operating on municipal solid waste started
operation in December 1981 at Collegeville, Minnesota (St. John's University);
it is a single 64 TPD unit.
In general, modular incinerators have not been used to generate superheated
steam or electricity, and they have not been operated on a continuous, 7-day a
week, 24-hour a day basis on municipal solid waste. Saturated steam pressures
of 100 to 200 psig are typical for modular incinerators. The manufacturers of
the systems are working toward achieving steam of higher temperatures and
pressures, and new operating data are becoming available regularly. The
capital cost of modular systems is considerably below that of other mass
burning technologies. Construction and start-up times can be as little as one
year. Refractory breakdown due to the highly corrosive reduced air
environment has been a major problem. Furnace lifetimes are generally
regarded to be only ten years even though some contractors are willing to
guarantee them for twenty years.
Stoker Fired Units
Stoker fired refers to the mechanism that conveys the refuse through the
incinerating furnace and simultaneously churns the refuse and mixes it with
air to stoke the fire. Stoker mechanisms include moveable grates, rollers, or
bars with air ports. Air is forced through the ports as the mechanism churns
the refuse. Developed and used primarily in Europe, this technology is
licensed to United States firms. Examples of the stoker mechanisms are
presented on Figure III-D.
Stoker fired units are configured as other mass burning units with dumping
pits or tipping floors, boilers, air pollution equipment, etc. Both
refractory lined and waterwall units are available, even though the waterwall
variety is more common and is the only type in use in the United States.
Stoker fired incinerator boilers are the most common type used to generate
steam from solid wastes. The technology was first developed in Europe due to
necessity because disposal sites were limited and energy costs were higher
than in the United States. Increased costs of fuel and disposal of municipal
solid waste to landfill has led to the construction of eleven field -erected
mass -burning waterwall incinerator/boiler facilities in the United States
since 1970.
In the earlier stages of development of solid waste stoker fired boilers,
problems were encountered with erosion and corrosion of boiler tubes, and
failure of stoker grates and ash conveyors. These have been greatly overcome
1 by new designs and the selection of better material of construction for this
application.
The advantages of the stoker fired units are that they are available in larger
sizes than the controlled -air modules and are similar in design to
conventional stoker fired boilers used in the coal-fired power plants. Also,
efficiencies are higher than for the controlled -air modular
incinerator/boilers. Heat recovery approximates 70 percent, and burnout is 75
percent by weight and 90 percent by volume. Although reliability is
considered good, maintenance costs of the stoker and ash handling equipment
are high. Also, more frequent replacement of boiler tubes should be expected
than for a boiler burning low sulfur coal or fossil fuels.
REFUSE
1 COMBUSTION GASES
2 GRATE
3 ASH
MARTIN -REVERSE RECIPROCATING
VON ROLL 3
FI"GURE III - D
VKW- DUSSELDORF
EXAMPLES OF EUROPEAN MASS FIRING GRATES
Primary control would be via steam'pressure rather than combustion chamber
temperature as used by the controlled -air modular incinerators, thus assuring
a more uniform steam pressure being delivered by the boiler. Also, an energy
plant having fewer but larger units would have simpler controls and would be
easier to operate with fewer personnel.
Stoker fired units have demonstrated excellent capabilities to produce both
superheated steam and electricity, even though steam producing applications
are more common. However, stoker fired units are capital intensive, heavily
constructed power plant -like units. High excess air requirements necessitate
large boilers and air pollution equipment. Most appropriate for large
capacity applications, stoker fired units in operation average 700 TPD for
steam producing units and 1,200 TPD for electricity producing units.
Rotary Furnaces
Rotary kiln furnaces have been in use in a number of countries through the
world as well as the United States. The Volund Company of Denmark has
installations dating back to 1932. The Volund design uses a refractory lined
stoker fired furnace followed by a refractory lined rotary kiln for maximum
burnout of organic matter in the furnace residue.
In the past few years, a United States' based firm called O'Connor Envirbtech
Corporation developed a waterwall rotary furnace. The first installations
were in Japan, and recently a 200 TPD plant was completed in Gallatin,
Tennessee. While the technology looks promising, there are only a few years
of operating experience to evaluate the reliability of the system. The
O'Connor system uses a rotating, water-cooled cylinder in the combustion zone
in lieu of the conventional stoker used with other waterwall boilers. The 8-
to 10-foot diameter cylinder is made up of axial tubes carrying pressurized
cooling water connected by perforated spacer plates. The cylinder is tilted
downward slightly from the horizontal plane to promote movement of the burning
wastes toward the boiler as the cylinder rotates slowly at 1/6 RPM. The
cylinder is enclosed in an insulated metal housing. Combustion air enters the
rotating cylinder from damper -controlled wind boxes through the holes in the
perforated plates. Figure III-E portrays the rotary combustor/boiler system.
The pressurized cooling water circulating through the rotating cylinder is
supplied from the lower drum of the boiler and returned to the upper boiler
drum where a portion is flashed into steam. Approximately 30 percent of the F
net energy derived from the solid waste is produced from the water circulated
through the tubes of the rotary combustor. The remaining 70 percent is
captured by the boiler.
Wastes are fed to a hopper and charging chute by a crane. The combustor is
fed from the charging chute by a hydraulic ram. The ash and other
noncombustibles are discharged into an ash quench tank at the base of the
furnace section of the boiler.
Comparison points regarding the rotary combustion/boiler system are:
° The simple rotating cylinder has no internal moving
parts as compared to the stoker and controlled -air
incinerators and is easy to maintain.
III-13
H
H
N
I
r
F
FIGUREIZL - E
O'CONNOR WATER-COOLED ROTARY COMBUSTOR
im MAW m woomaw m&w,ter m 4r m vw so son* rs we
° Preheated combustion air entering the combustor promotes
drying of the waste, as well as burning.
° Cooling water circulated through the tubes in the
combustor prevents high metal temperatures and "burn outs"
which are experienced with stokers cooled with air.
° operating experience indicates little or no wear inside
the combustor and low maintenance costs.
° Since approximately 30 percent of the available heat
from the municipal solid waste is transferred to the
water circulating through the tubes of the combustor,
a smaller boiler can be used for a plant having the
same capacity as compared with a stoker fired boiler.
° Energy efficiency and burnout compare well with stoker
fired units.
° The low temperatures and absence of refractory material
do not require long cool -down or start-up times during
maintenance.
° The units are well suited to continuous operations, and
the availability of multiple units allows for alternating
maintenance schedules.
° Factory assembly of units reduces construction costs.
(Costa Mesa location would provide extra cost savings
to Newport Beach.)
The O'Connor facility in Gallatin, Tennessee, has exhibited little corrosion
and has shown availability approaching 90 percent. An aluminum slagging
problem in the ash hopper has been solved. Heat recovery or energy efficiency
is rated at 70 percent, and ash residue is 27 percent by weight and 10 percent
by volume. Steam can be produced at 600 psig and 600°F, but reports indicate
fluctuations in the steaming rate. More operating data will become available
in the near future.
RDF Fired Units
Several types of incinerator/boiler combinations require the processing of
refuse into pellets or other easily handled form called refuse derived fuel
(RDF). This RDF process is discussed earlier in this chapter.
RDF fired incinerators/boilers include conventional stoker spreader boilers
which normally burn coal. Unlike mass burning units, spreader stoker boilers
require a reduction of refuse to a maximum size of four to six inches. This
size reduction allows the injection of the refuse through feed ports above a
traveling grate. Some of the refuse burns in suspension while the remainder
is spread over the grate near the back wall of the boiler. The grate, moving
toward the injection ports, supports the ash and burning fuel until complete
burnout is achieved. After traversing the boiler, the ash is dumped in ash
hoppers.
III-15
Spreader stoker boilers have been in successful operation for decades,
utilizing coal and low-grade fuels. In recent years, an adaptation of the
design has been used for the firing of RDF in various locations. Six spreader
stoker RDF units are currently operating.
Spreader stoker RDF systems offer some advantages over mass -fired technology.
The use of a thin fast burning fuel bed provides rapid response to variations
in load superior to that found in the mass -fired boiler. Spreader stoker
units operate with a lower excess air requirement than mass -fired units and
with higher efficiencies. Because of front-end preparation, the distribution
of fuel on the grate is more precise and residue quantities from the boiler
less. It would generally be found that spreader stoker units arel
correspondingly less costly than a mass -fired unit of equivalent heat input.
To date, problems associated with spreader stoker installations have revolved
around the refinement of the refuse -derived fuel. When in operation, boilers
have performed satisfactorily. The front-end preparation and storage
requirements needed would usually incur additional capital -and -operating costs
relative to similar functions for mass -burning. However, low boiler costs and
higher operating efficiencies should be expected to provide an offset.
Fluidized bed combustion is another process requiring RDF. Research into the
fluidized bed combustion concept has been ongoing for many years in all parts
of the world. Advantages include: low excess air requirements; high
efficiency; dual fuel capability; combustion of low grade fuels (including
RDF). Difficulties have included poor turn -down control, and carry-over of
grit and other particulates causing boiler erosion problems.
For municipal solid waste disposal, the concept includes the preparation of a
refuse -derived fuel for injection into a fluid bed combustor. The combustor
would be constructed of carbon steel with refractory brick and ceramic fiber
insulation. A bed of sand is used as a fluidizing medium. RDF would become
included in the dynamic condition of the fluidized bed. High temperature
gases are transported to a waste heat boiler for steam generation.
Fluidized bed combustion of RDF occurred in 1977 at Bournville, Birmingham,
England. By 1978, the unit had been shut down and dismantled. Carry-over of
ash and sand from the fluidized bed had completely eroded the boilers.
In the fall of 1979, a fluidized bed co -disposal facility located in Duluth,
Minnesota, began shakedown operations. Design had commenced in 1974. Two 100
percent capacity fluidized bed reactors are installed to burn 340 tons per day
of sludge cake and 200 tons per day of RDF. Initial start-up of the Duluth
project immediately identified the problem common to all fluidized bed
reactors to date. excess carry-over of sand into the waste heat boiler.
Other problems of an equipment nature are not considered to be substantial.
At Duluth, fluidized bed combustor off -gases are used for the generation of
low pressure steam for electrical power generation. steam is fed to turbine
generators at a 250-pound saturated condition. Exhaust from the turbine
generators is at 5 psig which is used for building heating. Generated power
is used to run high pressure blowers for the fluidized bed reactor and other
miscellaneous uses within the facility. Net available energy for sale by the
facility is not available, but in the view of engineers associated with the
project, it is minimal. The principal design criterion for the Duluth
facility is sludge disposal not resource recovery.
III-16
Fluidized bed combustion has long been viewed as the most promising new
technology in the solid waste disposal field. Problems as noted above have
plagued the technology, but all concerned with the Duluth plant are optimistic
that these problems are being solved. The technology, however, is still in
its infancy and, as a result, subject to refinement as operating data is
collected at the demonstration plant. A further disadvantage is that the
leading contractor in this field has removed itself from further work.
Suspension -fired waterwall technology also requires the preparation of a
highly refined RDF. It will normally be expected that a suspension -fired
boiler would operate at a higher thermal efficiency than mass -firing or
spreader stoker firing. However, a major penalty is incurred when the cost of
waste processing, storage, and firing systems are included.
A small number of facilities in the United States burn RDF in combination with
coal as outlined earlier in this chapter. Only one operating full
suspension -fired RDF unit in the United States utilizes waste as a fuel
exclusively. This is a facility owned by the Eastman Kodak Company, Kodak
Park, Rochester, New York. The Kodak system was put on-line in 1972 and
during its shakedown phase underwent some modifications. Since that time,
operation has been continuous. The Kodak installation was a trailblazing
operation in which many of the material handling problems associated with
suspension firing were identified and solved by the efforts of Eastman Kodak,
its engineers, and equipment suppliers. It is worthy to note, however, that
the principal manufacture of suspension -fired RDF units, Combustion
Engineering, Inc., has itself prepared bids on a number of refuse -to -energy
projects on the basis of performance -type specifications which do not have
mandatory equipment criteria. Combustion Engineering has found, through its
own analysis, that mass -fired and. spreader stoker operated units offer more
attractive economics than the suspension -fired unit.
CMI-ENCON COMBINATION
Energy Conversion Systems, Inc., a subsidiary of the large CMI heavy equipment
manufacturing company, is building and marketing a waste -to -energy system
which combines several technologies. One such facility is near completion in
Oklahoma City, another is planned in Ventura County, California, and seven
such facilities have been proposed for Orange County to handle all solid
wastes. CMI-ENCON has proposed to build and operate such a facility in
Newport Beach.
The ENCON technology processes municipal wastes through several recovery and
sorting mechanisms similar to refuse derived fuel processing. The
unrecoverable and lighter fraction that comprises 80 percent of the refuse is
digested with raw waste water to produce a gas which is cleaned to pipeline
quality methane (980 Btu per cubic foot). Sludge from the digestion process
is dewatered and incinerated in a rotary furnace to produce steam or
electricity. The Southern California Edison Company appears to have a great
degree of confidence in the system and is actively participating in the
development of the facility in Ventura, California. SCE also participated in
ENCON's proposal to the Orange County Board of Supervisors to invest over $500
million to build and operate seven such facilities to handle all of the
County's solid waste.
Because the system is so new, there is little operating experience available
to assess performance. However, some general observations can be made. The
system appears to require greater acreages than other systems, but the
buildings are somewhat lower in height. The sorting and separating
pretreatment appears to be complicated and to require some hand sorting. All
the constituent parts of the system have been tested, but the results of
intermingling and upsizing are still unknown. For instance, the gas producing
digesters have been successfully operated only at 50 gallon and 2000 gallon
sizes. The process requires 7,000,000 gallon size units which have not yet
been built or successfully operated. Energy efficiencies and sales revenues,
although purportedly guaranteed, have yet to be demonstrated. New operating
data on this system is expected on a continuing basis over the coming years.
I
I
I
11
1
CHAPTER IV ENERGY MARKETS
The conversion of refuse to energy will be cost effective only if the energy
can be sold. Therefore, this chapter identifies available markets for energy
and recovered materials, the product requirements, and the expected prices.
ELECTRICITY
Measured in kilowatt hours (kwh), electricity can be produced by refuse -fired
steam turbine generators. Typical municipal waste incinerated at a 70 percent
heat recovery rate in- a facility available 310 days per year can produce
electricity at an average rate of approximately 475 kwh per ton. Thus, a
typical day of Newport Beach collected refuse (125 tons) can produce
approximately 60,000 kwh of electricity each day. This is equivalent to the
power used by 7500 homes. This power can be used by the owner/operator of the
producing plant or sold to the utility.
Regulations implementing the Federal Public Utilities Regulatory Policy Act
(PURPA), and a California Public Utilities Commission (CPUC) decision require
that utilities pay the full "avoided cost" or "marginal cost" for power
purchased from all "qualifying small power production facilities." A waste to
energy facility would qualify as both a cogenerator and as a solid waste plant.
Any electricity produced could be sold to the Southern California Edison
Company (SCE) under the above -referenced requirements. SCE has developed a
rate schedule to conform with these regulations which has been submitted to
the CPUC for approval.
The purchase price SCE will pay is divided into an energy payment and a
capacity payment. The energy payment is equal to the "avoided cost of fuel"
and the capacity payment is equal to SCE's defrayed cost of building new
generating capacity. Tables IV-1 and IV-2 provide SCE's payment schedule for
energy and capacity respectively. After the capacity payment of $/KW/year
from Table IV-2 is established, it remains unchanged throughout the life of
the contract.
The energy payment is dependent on the time of day, day of the week, and month
of the year. These payments, however, can be presented for an average
continuous generation rate. The capacity payment can be calculated on the
same basis as follows:
Capacity Payment (cents/KW-hour) _ $/KW/year (Table 3-2)
365 days/yr x 24 hr/day
IV-1
Using the rates presented in Table IV-1, and the amount shown in Table IV-2,
for a 20-year contract beginning in 1983, the total payment would be:
Total Payment = 5.4 cents/KW-hour +
1.22 cents/KW-hour (CAP) = 6.62 cents/KW-hour
8CE is an excellent energy market. They will purchase any and all electricity
produced and will enter into a contract from 1 to 30 years in length. Since
SCE is a large utility, they can be expected to remain in business for the
duration of any proposed waste -to -energy project.
Table IV-1
SCE's Energy Payment Schedules
On -Peak 5.9 cents/KW-HR
Mid -Peak 5.4 cents/KW-HR
Off -Peak 5.2 cents/KW-HR
Time Weighted Average 5.4 cents/KW-HR
1Rates effective November 1, 1982, to January 31, 1983
Table IV-2
SCE's Capacity Payment Schedules
$/KW/Year (Based on 100% On -Line Factor)
First
Year of Contract Term Years
,
Delivery 1 5 10 15 20 30
1983 24 47 75 93 107 127
1984 24 64 90 108 123 145
r
1985 24 84 108 126 142 165
1986 92 109 129 147 164 189
1Rates effective September 17, 1982
Future avoided costs of electricity are uncertain. Avoided costs decreased
during 1982. Each quarter both energy and capacity payments vary according to
a complex formula involving fuel costs, interest rates, outages, and many
other items. The oil glut and the availability of natural gas during 1982
contributed to falling prices. Historical rates are presented on Table IV-3.
,
Past projections of exponentially rising energy costs are being reconsidered.
Despite coming deregulation, natural gas prices are not expected to rise
dramatically, The forecasts of Southern California Edison for avoided costs
reveal a moderate rise in nominal costs from 50-60 per KWH in 1982 to 84-96
,
IV-2
'I
1
1
II
per KWH in 1991. In real 1982 values, however, SCE forecasts a drop to
approximately 4C in 1991. Considering the current unpredictability of the
national economy, all forecasts of avoided costs are speculative.
Newport Beach used nearly $800,000 of electricity in 1981-82 for street
lighting, water pumping, and other municipal services. This electricity is
metered at approximately 170 locations. A City -owned waste -to -energy facility
could provide this electrical requirement, but connection and transmission
costs might be prohibitive.
Table IV-3
SOUTHERN CALIFORNIA EDISON'S
PUBLISHED AVOIDED COST
ENERGY PAYMENTS (cents/KWH)
ON -PEAK
NEAR -PEAK
OFF-PEAK
RATES
RATES
RATES
February - April 1980
4.0
4.0
3.9
May - July 1980
4.7
4.7
4.6
August - September 1980
5.0
5.0
4.9
October 1980 - January 1981
5.0
5.0
4.9
February - April 1981
5.9
5.5
5.3
May - July 1981
6.6
6.0
5.8
August - September 1981
7.7
7.1
6.9
October 1981
7.7
7.1
6.9
November - December 1981
8.0
7.3
7.1
January - April 1982
8.0,
7.3
7.1
May - July 1982
5.3
4.9
4.7
August - October 1982
5.6
5.2
5.0
November 1982 - January 1983
5.9
5.4
5.3
STEAM
Sale of steam can be more profitable than the sale of electricity because
efficiency is increased by the elimination of the interim turbine generator.
Steam markets in the Newport Beach area, however, are few.
Measured in pounds by temperature and pressure (psig), steam can be used for
heating, cooling, or industrial processes. Typical municipal waste
incinerated at 70 percent heat recovery rate can generate steam at a rate of
approximately 600 1Bs at 400-600 psig and 400-600OF of steam per ton. A
typical day of Newport Beach collected trash (125 tons) therefore could
produce 750,000 1Bs of steam per day.
The sale price of steam is directly related to the price for the fuel used to
generate steam. Steam generated by a waste -to -energy facility is often sold
at a discount from oil or gas generated steam as an inducement to the user.
Oil and natural gas are the primary fuels used to produce steam in the Newport
Beach area. Natural gas in November, 1982, was selling at approximately $0.56
per term (100,00 Btu). At that price, steam costs approximately $5.68 per
1,000 iBs. Fuel oil in November, 1982, was selling at approximately $36 per
IV-3
barrel. At that price, steam cost approximately $6.57 per 1,000 pounds.
These costs are exclusive of maintenance, operating, and water treatment
costs.
Rapidly depleted during transmission, steam energy must be sold to customers
relatively close to the producing facility to ensure profitability.
Construction of steam transmission lines can also be very expensive.
Potential steam customers are, therefore, dependent on the location of the
waste -to -energy facility.
Almost any large building or group of buildings that require heating and
cooling could be a steam user with the appropriate equipment. Any shopping
center or industrial area could be built or converted to use steam. Three
potential steam customers were located in Newport Beach and are discussed
below.
Mobil Oil Corporation
Mobil oil uses large amount of steam to extract oil from its leases on the
Banning property in west Newport. Natural gas purchased from the Southern
California Gas Company and digester gas purchased from the sewage treatment
plant in Huntington Beach is burned to produce approximately 41,000 1Bs per
hour of steam at 600 psig and 4890F. The fuel equivalent value of this steam
ranges between $2.0 million and $2.4 million per year.
Contacts within Mobil Oil Corporation have indicated a willingness to consider
use of steam from a waste -to -energy facility to "... provide significant cost
savings and environmental improvements." The existing lease for oil
extraction expires in 1994, but representative of both the oil company and the
property owner have indicated the possibility of extending the lease term.
Hoag Memorial Hospital
Hoag Hospital operates two natural gas fired boilers to produce steam for both
heating and cooling. Amounts of steam are relatively low averaging 6-16,000
1Bs per hour at 80 psig and 3500F. Steam usage increases during the night
and during the winter. Natural gas usage can vary from 35,000 therms in
August to 80,000 therms in January. Natural gas usage in 1982 is estimated
at 643,000 therms, and 95 percent of that amount is used to produce steam. At
a price of $0.56 per therm, the fuel equivalent price of the steam used at
Hoag Hospital in 1982 is approximately $342,000. This figure does not include
maintenance, operation, or water treatment.
Hoag Hospital has retained the ANCO Engineering Company to study cogeneration
and other energy savings techniques. The study will resume in April, 1983,
after winter historical data is collected.
Hughes Aircraft Company
The Hughes facility near the City Yard on Superior Avenue operates two natural
gas fired boilers to produce steam primarily for cooling. Each boiler
produces up to 6900 iBs per hour at low temperature and low pressure. Steam
is required 24 hours per day, and usage rises when the weather is warmer.
The 1981 cost for natural gas to fuel the boilers was approximately $95,000.
IV-4
I
' METHANE GAS
' The market for high quality methane gas is very good. "Pipeline quality" gas
can be distributed and sold to any user of natural gas purchased from the
utility. Southern California Edison has indicated a strong willingness to buy
gas from a waste -to -energy process.
Anaerobic digestion of municipal "waste to produce methane gas requires the
addition of raw waste water. One ton of typical refuse combined with 1,000
gallons of waste water can produce approximately 72 therms of gas. (1 Therm
equals 100,000 BTU). The selling price of natural gas in November, 1982, was
approximately $0.56 per therm. A typical day of Newport Beach collected
refuse (125 tons) has the potential of producing 9000 therms of gas each day.
This equivalent to the space heating and cooking requirements for 4500 homes.
REFUSE DERIVED FUEL
The market for fuel derived from the processing of refuse is virtually
non-existent near Newport Beach. Refuse derived fuel (RDF) processing is
described in Chapter III. RDF has been used as a supplement to coal in
specially converted boilers in other parts of the nation. Because of air
pollution restrictions, no coal is burned in the South Coast Air Basin.
Southern California Edison investigated the possibility of converting their
oil and natural gas fired boilers to RDF and found that it would require
complete rebuilding and would, therefore, be prohibitively expensive. RDF may
be burned profitably in a dedicated boiler to produce electricity or steam,
but there is no currently available market for RDF by itself.
SOIL AMENDMENTS
Composting of municipal waste produces a low nutrient mulch suitable as a soil
amendment or conditioner. More nutritive amendments such as manure and sludge
are abundant and competiyely eliminate this market in an increasingly non
' agricultural area such as Orange County. Shipping compost to other areas is
also uneconomical.
DESALINATED WATER
Electricity generated from incinerating wastes can power a reverse osmosis
' (RO) desalination plant. RO is currently used by the Orange County Sanitation
District in Fountain Valley to treat waste water before it is injected into
the ground.
' A study, published in July 1982, indicates that advances in RO technology and
use of brackish water in place of sea water can produce good economics. Sea
water typically contains 35,000 parts per million (ppm) total dissolved solids
(tds), but brackish water used in the study contains only 1,000 to 4,000 ppm
tds. Long life membranes in the RO process, which reduce operating costs, are
also considered in the study. The study suggests that one ton of typical
municipal refuse can produce enough electricity to desalinate 60,000 gallons
of brackish water to drinking quality. Therefore, a typical day of Newport
Beach collected refuse (125 tons) could desalinate 7.5 million gallons per day
or 2,737.5 million gallons per year.
1 •
' IV-5
The Water Department of Newport Beach purchases approximately 18,000 acre feet
of water each year from the Metropolitan Water District. The City paid
$140.00 for each acre foot in November, 1982. One acre foot equals 325,851
gallons. Therefore, the 2,737.5 million gallons which could be desalinated,
using the trash collected by the City, would equal 8,400 acre feet and would
be worth $1,176,150. Such economics are dependent, however, on an adequate
supply of brackish water and the acceptability of desalinated water by the
City's consumers.
SECONDARY MATERIALS MARKET
in orange County, there are 49 organizations which accept secondary materials
for recycling. Included in this number are 20 recyclers which accept more
than one type of material, 5 paper recyclers, 1 glass recycler, 3 plastic
recyclers, and 20 metal salvagers. The types of organizations doing recycling
include large firths operating on a brokerage basis, smaller buy-back
operations, and local drop-off center.
Secondary materials markets in Orange County are subject to substantial
fluctuations, and are currently depressed due to the world-wide economic
recession. Recycled paper markets were much stronger during the 1970's. In
particular, the formerly strong international demand for recycled paper from
the U.S. has dropped off sharply in the last year. The ferrous metals market
remains quite stable, except for a very weak market for bimetal and tin cans
(the main ferrous component captured by resource recovery programs). The
nonferrous market is also relatively weak at present, as are the glass and
plastic markets. It should be noted, however, that an improvement in the
general economy would probably be reflected in improved markets for secondary
materials.
Recent (March 1982) prices paid for recovered materials in Orange County are
indicated in Table IV-4.
IV-6
Table IV-4
MARKET PRICES FOR RECOVERED MATERIALS
IN ORANGE COUNTY
(MARCH 1982)
Market Price Range
WASTE MATERIAL (dollars/ton)
Newsprint
10-30
Cardboard
15-25
Computer Paper and Cards
120-160
White Paper
40-80
Colored Paper
30-40
FERROUS SCRAP
16-20
NONFERROUS METALS
Aluminum
400-550
Copper
1000-1300
Brass
400-700
GLASS
Clear Glass
20-40
Color -sorted Glass
30-40
Mixed -color Glass
10
IV-7
CHAPTER V LEGAL AND ADMINISTRATIVE REQUIREMENTS.
A waste -to -energy facility is a major public work, requiring permits and
approvals from a variety of institutions and requiring extensive contractual
and financial assurances. Many risks and potential liabilities require
careful consideration. This chapter summarizes the various institutional
requirements confronting a waste -to -energy facility.
WASTE STREAM GUARANTEES
Both the quantity and composition of MSW must be guaranteed for the projected
life of the project. Accurate accounting of existing and projected volumes is
essential. Potential problems are many.
The City of Newport Beach, in effect, owns the MSW it collects, but greater
volumes may be necessary to provide economies of scale. If additional volumes
are needed from commercial haulers, firm and long term, so-called "put or
pay," contracts would need to be negotiated.
Typically, waste products attain greater value when they are in demand.
Private haulers most likely will demand some cost saving in exchange for
guaranteed deliveries of MSW. Local ordinances to force delivery to
waste -to -energy facilities have been met with anti-trust suits. Competitive
waste -to -energy or resource -recovery facilities are also a real possibility,
and delivery of the requisite amount of MSW must be guaranteed.
Volumes may decrease due to recycling efforts. Metals, glass, and paper, in
particular, may be more profitable for consumers to recycle in the future. Al
waste -to -energy facility, depending on materials removed from the waste
stream, would be adversely affected.
Composition of MSW can drastically alter waste -to -energy efficiencies.
Insufficient heating values, excessive moisture, toxic or explosive
characteristics, oversized items, and other properties can wreak havoc on a
waste -to -energy facility.
To prevent this, several precautions must be taken. A sampling survey is
conducted to estimate the caloric or BTU content of collected wastes. This
data helps predict energy efficiencies and resource recovery rates. Many
precautions are necessary in the design and operation of the facilities to
prevent damage to the equipment and prevent human exposure to hazardous
materials. However, unexpected arrival of dangerous materials at the facility
can increase operating expenses.
V-1
In summary, accurate accounting of existing and projected waste volumes and
composition, coupled with contractual guarantees are required to assure an
adequate waste stream to the facility.
MARKET GUARANTEES
Purchase of the energy or recovered material must be reasonably assured for
the life of the project. The financial stability of the purchaser and the
competitive position of the product must be examined. Special equipment
purchases, additional operating expenses, and compatibility between production
and use rates are important considerations. Electricity and natural gas sales
to large utilities pose less of a problem than sale of steam or recovered
materials to private industry.
As noted in Chapter IV, future energy prices are subject to much speculation
and will be affected by many, as yet unknoym, factors. Steam and recovered
materials' markets can be affected to a much greater extent than electricity
or natural gas markets by economic conditions and substitute fuels. Demand
for recovered materials has been low during the economic recession of
1981-82. Fuel and energy prices also declined in that period. Future
fluctuations may cause similar or more pronounced effects.
Accordingly, one of the most important requirements for a waste -to -energy
facility is a reasonably assured market for its products.
SITE GUARANTEES
More waste -to -energy facilities have been negated because of siting problems
than for any other reason. In California, well -planned,
environmentally -sensitive, and financially -secure projects have been denied by
referendum in Brisbane, Gardena, and Berkeley. Resident opposition is
threatening many others across the nation. Many communities have spent much
time and money planning a facility only to find that they have no acceptable
site.
in addition to all the formal permits and technical conditions, a suitable
site requires approval by local communities. Aesthetics and truck traffic
appear to generate the most objections, even though many other problems are
cited. (See Chapter VII Environmental Impacts). Waste -to -energy facilities
often are opposed in the same manner as landfills. Consequently, finding a
suitable site and gaining the necessary approvals are required early in the
planning process.
PROCUREMENT
Procurement of a waste -to -energy facility consists of two principal
decision -making stages which address the approach and the procedure to be
utilized. The approach dictates how the responsibilities for the project
engineering, design, construction, start-up and operation will be assigned
between the public and private sectors. The procedure determines which method
will be employed to select the private contractors.
V-2
A/E Approach
The most conventional approach is to retain an Architect/Engineer to plan and
design the project. The A/E, acting as agent for the agency, prepares
equipment and system specifications to be let out for public bidding.
Following bid evaluation, the same, or a different A/E, is retained to
supervise construction of the project in order to ensure the use of proper
materials, supplies, equipment, etc. Upon completion of construction, the A/E
assists in plant start-up and testing and may be required to prepare operating
manuals for the facility. Once the facility has passed acceptance testing,
operational responsibility becomes that of the procuring agency who might
either operate the facility itself or contract out its operation to a private
firm.
The A/E approach offers the advantage of allowing for complete definition of
exactly what is to be constructed before any construction is initiated.
Through the design review process, both the owner of the facilities and the
A/E have the opportunity to make modifications and corrections based on review
of detailed final construction drawings. Because the work is well defined,
construction bidding is often highly competitive. An additional advantage is
that during construction, the A/E can exercise some measure of control on the
quality of construction by approval or disapproval of shop drawings and by
on -site inspection control.
The primary disadvantage of the conventional approach is that this procedure
normally takes longer than other methods and may in fact result in a higher
total project cost in spite of savings achieved due to competitive
construction bidding. It may also be argued that it is a disadvantage to have
separate design and construction responsibilities and thereby separate
liability for the problems associated with the final product.
Turnkey Approach
In a turnkey approach, a single contractor is retained to design, construct,
and start-up the facility. The turnkey contractor selects the equipment and
supplies to be used and may either design and construct the facility itself or
subcontract portions of the work. In either case, the contractor assumes sole
responsibility for the project. Upon completion of construction and start-up
and successful testing, the project is accepted by the procuring agency who
then assumes responsibility for full-scale operation.
The primary advantages of this approach are: 1) allowance for a shorter total
completion time frame and potential corresponding cost savings to the owner,
2) potential cost savings in design due to diminished necessity for detail, 3)
more expedient resolution of problems encountered during construction, and 4)
placement of a singular responsibility for the adequacy of the completed
product.
Full Service Approach
In a full service approach, a single contracting entity assumes responsibility
for the design, construction, and operation of system facilities. The
advantages and disadvantages associated with the design and construction
phases are the same as for the turnkey approach. The additional advantage to
the owner is that the systems vendor has clear operational performance
responsibility and must make the system operate effectively.
V-3
The disadvantage of this procedure, with total performance dependency upon a
single entity, is that it does not allow for the possible savings in
competitive bidding relative to operational service contracts.
The full service approach is presently the most popular development method for
waste -to -energy facilities. Several large system vendors, mainly representing
established European mass -burning technologies, are offering their facilities
on a full service basis.
Private Approach
An extension of the full service approach is to permit a private party to
plan, design, build, and operate the facility like any other business. The
procuring agency simply participates like any other paying customer.
Typically, a jurisdiction would only enter a "put or pay" type contract for
its wastes at a specified tipping fee. This is the only approach where the
procuring agency would not participate in the financing arrangements.
Competitive Sealed Bidding Procedure
Competitive sealed bidding, also known as Formal Advertising, is the most
commonly used method for acquiring supplies, services, and construction for
public use. Use of this method requires the preparation and issuance of an
Invitation for Bids (IFB) containing detailed specifications and a purchase
description of the desired item or service. Upon receipt of bids, judgmental
factors may only be used to determine if the item or service being offered
satisfies the requirements of the IFB. No change in bids is permitted once
they have been opened (with limited exceptions). once bid evaluation is
completed, award is made solely on an objective basis to the lowest responsive
bidder.
Competitive Negotiation Procedure
The use of the competitive negotiation method of procurement is generally
reserved for those situations where the item or service desired requires
extensive discussions with offerors to determine the fairness and
reasonableness of offers. Also known as competitive sealed proposals, this
process is used generally to create a marketplace where price is ultimately
established by bargaining between the procuring agency and a number of
qualified offerors. Under this procedure, a Request for Proposals (RFP), as
opposed to an IFB, is issued containing general system and performance
specifications and indicating the evaluation criteria to be used (pricing
being only one), and the relative importance of each. The contents of
proposals received are not publicly disclosed and information contained in any
proposal is not divulged to competing offerors. This process differs from
competitive sealed bidding in two major respects: first, judgmental factors
are used to determine not only compliance with the requirements of the RFP,
but also to evaluate competitive proposals. The effect of this is that the
quality of competing proposals may be compared and trade-offs made between the
price and quality of offers; second, discussions are permitted after the
submittal of proposals, and changes in proposals may be made to arrive at
final offers which are most responsive to the procuring agency's needs. Award
is made, after negotiations, to the offeror whose proposal is most
advantageous to the agency based upon price and other evaluation factors.
V-4
Two -Step Formal Advertising Procedure
The two-step formal advertising procedure was developed by the Federal
Government and is used chiefly in situations where the complexity of the
system or service desired precludes the preparation of detailed specifications
by the procuring agency. This procedure incorporates features of both the
competitive sealed bidding and competitive negotiation methods and involves
the issuance of two solicitation documents. In Step One, an RFP is issued
requesting the submittal of unpriced technical proposals. Discussions are
conducted separately with all offerors to ensure complete understanding by the
procuring agency of what is being offered and to enable offerors to change
proposals so as to render them responsive to the RFP. All offerors whose
proposals are accepted, either as submitted or following modifications based
on these discussions, are then issued an IFB in Step Two. Thereafter, the
procedure is identical to that in competitive sealed bidding with award of the
contract to the responsible bidder whose bid is most advantageous to the
procuring agency.
Sole Source Negotiation Procedure
Sole source negotiation involves no competition and is used when the procuring
agency determines that there is only one source for the desired supply,
service, or construction item. A proposal is made in response to an RFP, the
terms and conditions of the contract are negotiated, and award is made.
CONSTRUCTION AND OPERATION GUARANTEES
Like many other large operating industrial plants, a waste -to -energy facility
is subject to construction delays, cost overruns, and system failures.
Unexpected inflation, labor strikes, delivery delays, productivity losses, and
equipment failures are possible. Many waste -to -energy facilities have been
dramatic failures and have resulted in large financial losses.
To prevent or minimize such problems, a variety of guarantees and -insurances
are required. Appropriate warranties and indemnifications can be required of
each party in the procurement process, as shown on Table V - 1.
V-5
TABLE V - 1
RISK SHARING UNDER ALTERNATIVE PROCUREMENT APPROACHES
Full Private
A & E Turnkey Service Owner
Completion of Project Construction
Within Specified Time Frame E C C C
Construction Cost Overruns PA C C C
Satisfaction of Acceptance Test E C C C
Changes in Laws and Regulations
Requiring Additional
Capital Investment PA PA PA C
Operating and Maintenance Costs PA PA PA C
System Performance During
Operation PA PA PA C
E = Engineer
C = Contractor
PA = Public Agency
FINANCING OPTIONS
Each of the following financing alternatives are discussed in this section:
° Conventional Revenue Bonds
° Industrial Development Bonds
° Lease Revenue Bonds
° Leveraged Leasing
• Private Debt and Equity
Conventional Revenue Bonds
Revenue bonds are debt securities that may be issued by local government
entities. They are payable solely from revenues derived from operating
facilities that have been acquired or constructed with the proceeds from the
bonds. The taxing power of the local government entity is not pledged or
committed to pay debt service on the bonds nor do the bonds represent a charge
against the issuer's General Fund. Regardless of who the issuer might be, the
bonds would be secured by a pledge or assignment of all tipping fees and
energy sales revenues from the operation of the project so as to benefit the
bondholders. A key consideration of a conventional revenue bond financing is
the control over the waste stream. Revenues would be secured by a convenant
to set rates and backed by various reserve funds to protect against shortfalls
in the project revenues or unexpected maintenance costs.
V-6
Several other issues should be considered with the conventional revenue bond
alternative. From a tax standpoint, financing the facility through the
issuance of revenue bonds will result in the loss of all potential tax
benefits associated with the project because the City, as the owner, is a
tax-exempt entity and thus unable to claim investment tax credits or
depreciation deductions. Regarding accounting rules, the debt incurred by
conventional revenue bond financing need not be capitalized and fully
disclosed in the issuer's financial statements, if the issuer's credit is not
pledged as support. Revenue bonds pay tax free interest and are usually sold
somewhat below prevailing rates.
Industrial Development Bonds
Industrial development bonds differ from other types of municipal securities
in that they are backed solely by a taxable entity such as an industrial
corporation and not by any governmental unit. The proceeds of the bonds are
used to finance facilities constructed for the business operations of these
taxable entities. There are, however, certain activities that are considered
exempt from taxation under Section 103(4)(b) of the Internal Revenue Code,
including the financing of solid waste disposal facilities with revenue bonds.
These bonds are normally termed "Solid Waste Disposal Revenue Bonds," and are
typically issued by an agency or other political subdivision for the purpose
of financing a facility which will benefit the local area.
The California Pollution Control Financing Authority (CPCFA) is the only
entity in California authorized to issue industrial development bonds for a
resource recovery project. Bonds issued by CPCFA are limited obligations of
the Authority, payable only from payments made by the private company for whom
the financing has been arranged. The source of payments is tipping fees and
revenues from energy sales. They are secured by liens, guarantees or other
arrangements, and may be used in connection with leveraged leases or project
financing. The only application of these bonds regarding Newport Beach would
be in connection with a full service procurement approach, using a "put or
pay" contract with the City.
A major issue concerning solid waste disposal revenue bonds is the extent to
which a project qualifies for tax-exempt financing. Since the basic IRS rule
states that the project will be exempt up to the point where the refuse has
been converted into a marketable product having value. Non -qualifying
equipment must not exceed 10 percent of the cost of the project. Such
non -qualifying equipment typically includes electricity -turbine generators,
steam condensers, and steam lines.
Tax benefits associated with the project may be claimed by the taxable entity
which uses the project. These credits would normally include rapid
depreciation and the standard investment tax credit of 10 percent of all
qualified property and an additional energy tax credit of 5 .percent. Under
leveraged leases, full tax benefits would be made available to equity
investors. In the event that the City is deemed a substantial user of the
project, no investment tax credit would be available.
Industrial Development Bonds are generally considered to be debt obligations
of the entity involved in the financing. For accounting purposes, the bonds
are included as long-term debt of the CPCFA.
V-7
Lease Revenue Bonds
Lease Revenue Bonds are issued by a public agency to finance the cost of
constructing a facility to be leased to a public entity such as the City.
These bonds are secured solely by annual rental payments equal to at least the
principal and interest on the bonds. This type of financing allows the bonds
to obtain the credit backing of the lessee public entity which is usually
about one level beneath the public entity's general obligation credit rating.
There are several major advantages to lease revenue bond financing. Voter
approval is usually not required, for example, and lease payments made by the
lessee are not considered debt counted against statutory debt limitations. In
addition, a lower interest rate than the rate on conventional revenue bonds is
obtainable because the lessee's credit is utilized. The lessee will also
typically have greater flexibility in the imposition of rates and charges, but
this income need not provide additional debt service coverage as required when
using conventional revenue bond financing.
Proposition 4 could impact on the financing; however, it is assumed that this
is unlikely and that the receipt of lease payments from the lessee is probably
not includable as "proceeds of taxes." The payment of lease rentals will not
likely be funded from within the lessee's "appropriation limit," if lease
payments are derived from "proceeds of taxes." This means that the lessee
entity could use revenues from operation of the facility to pay rentals,
without a charge against its "appropriation limit," but use of tax revenues
for that purpose would be charged against the "appropriation limit."
Under current accounting practices, lease payments are treated as an operating
expense of the lessee. Lease revenue bonds do not represent a debt of either
issuer or the lessee.
Advantages:
° Bonds obtain the credit backing of the lessee
° Lower annual costs of the project
° Voter approval not needed
° Lease payments not considered debt of the lessee
° No need for additional debt service coverage
Disadvantages:
° May be subject to interest rate limitations
° Use of tax revenues by lessee to make rental
payments is charged against appropriations
limit
Leveraged Leasing
A leveraged lease is a form of "true leasing" where the lessor is considered
to be the owner of the asset for tax purposes, and the tax benefits are
magnified by leveraging his investment in the asset through the sale of debt.
This creates an additional tax benefit in the form of an interest deduction.
It also improves the lessor's yield or rate of return by increasing the total
amount of tax benefits for each dollar of the lessor's investment.
V-B
A leveraged lease financing of a waste -to -energy facility would be a complex
transaction involving numerous parties. The lessee would be a tax -paying
entity acting as a full service contractor, a subsidiary of a full service
contractor, or a participant in a joint venture of the contractor and some
tax-exempt entity such as the City. The lessor would probably be a trust
formed by one or more "equity participants" which would be corporations, such
as commercial banks, with a large capacity for tax benefits. Other parties to
the transaction would include the purchasers of the bonds, their trustee, the
CPCFA, and the trustee of the owner trust.
Many variations of leveraged leasing are available for a waste -to -energy
project. Construction expenditures can be financed, for example, by requiring -
the equity participants to acquire title to the project at or near the
beginning of construction. They would then be able to claim progress payments
on investment tax credits and construction period interest deductions. This
would result in lower rental costs to the lessee. Additionally, the lessee
may be permitted to defer all payments of rent and, therefore, all financing
charges, until completion of the construction period. Another variation might
be longer or shorter lease terms which cede the investment tax credit to the
lessee and capitalize construction period interest from the beginning of
construction.
In leveraged leasing, matters of tax law are especially critical. In most
large leveraged leasing transactions, rulings are sought from the IRS to the
effect that the benefits will be available. In all cases, qualified legal
counsel is generally required. Although guidelines have been issued by the
IRS, for properly issuing leverage lease bonds, it should be noted the
interpretation of these guidelines is difficult and may become problematic.
It is also important to note that the project must not be a "limited use
property," that an additional tax issue will be presented if the lessee is a
highly capitalized corporation, and if a full service approach is selected, it
will be necessary for the contractor's legal staff to analyze whether the
lessee can consummate this type of financing.
Regarding accounting procedures, it should be anticipated that any potential
lessee will have the goal of limiting the impact of the financing of the
project on its financial statements. whether the lease is a capital lease or
an operating lease will be the critical factor. A capital lease is one which
is determined by a measurement of the present value of the facility rentals.
If this amount exceeds 90 percent of the asset value, the lease will be,
considered a capital lease and treated as capitalized debt. If the amount is
less than 90 percent, the lease will be an operating lease and subject to
"off -balance sheet" accounting. The rate used to discount the rentals is
generally the lessee's incremental borrowing rate or the "implicit rate used
by the lessor," whichever is lower.
Private Debt and Equity
This alternative assumes a private company would invest funds to build and
operate a facility like any other operating plant and expect a suitable return
from energy sales and tipping fees. Although possible, this method is
unlikely because the potential returns are much less than those associated
with leveraged leasing.
V-9
PERMITS
A variety of permits from several institutions will be required to construct
and operate a waste -to -energy facility. The exact requirements will depend on
the location and the design of the facility. Permits which may be required
for a facility in Newport Beach are discussed in this section.
City of Newport Beach Permits
A waste -to -energy facility would be classified as a medium or heavy industrial
land use for which there are no provisions in the City's plans or ordinances.
Specifically, the M-1 District of the Zoning Code prohibits "incineration or
reduction of garbage, sewage, ... or refuse." Accordingly, the following
items would be required within the City:
° General Plan Amendment
° Local Coastal Plan Amendment
° Zoning Text and Map Amendment
° Use Permit
° Building Permit
° CEQA Documentation
Air Pollution Permits
Every type of waste -to -energy facility will require some sort of Air Pollution
permit, and the incineration types will require the most difficult to obtain
permits.
The siting of a mass burning waste -to -energy project in the South Coast Air
Basin would require air pollution review by the U.S. Environmental Protection
Agency, the California Air Resources Board, and the South Coast Air Quality
Management District. The applicable standards are complicated and subject to
discretionary review. Difficult standards dealing with Best Available Control
Technology and emission offsets will confront a waste -to -energy system. Many
air pollution control devices have not yet been proven over long periods on
waste -to -energy facilities. Air pollution control and construction occurs
concurrently with final design. It is anticipated that air pollution control
equipment will be a large and expensive portion of any waste -to -energy
facility in the South Coast Air Basin.
It is also anticipated that final permits will not be secured until a system
is on-line and its performance is verified. This creates the possibility that
a waste -to -energy facility could be built and then shut down for failure to
control air pollution. This has occurred on occasion in other parts of the
nation.
Air emissions are described in Chapter Sr Environmental Impacts, and detailed
descriptions of air pollution control permit requirements are contained in
several documents on file in the City Manager's office. Air pollution permits
for a Waste -to -energy facility will be required as early as possible in the
development process. A Permit to Construct must be followed by a Permit to
Operate. Specifications and negotiations to obtain these permits will require
special consultants.
V-10
Ash Disposal Authorization
Any ash residues from incineration of NSW currently are classified as a
hazardous waste by the California Department of Health Services. Disposal in
a Class I or II - 1 landfill, plus special handling procedures are required.
The closest hazardous waste disposal site is the BKK facility in West Covina.
Efforts are underway to change these regulations. The composition and
leaching properties of MSW ash residue are being analyzed. It is anticipated
that separate analysis of the ash from each waste -to -energy facility will be
required, and that an Ash Disposal Authorization will need to be obtained from
the Regional Water Quality Control Board and the Orange County Health Care
Agency.
Solid Waste Facility Permit
Issued by the California Solid Waste Management Board through the Orange
County Solid Waste Enforcement Agency, this permit would require conformance
with the Orange County Solid Waste Management Plan. This plan currently
encourages waste -to -energy facilities. A finding by the Orange County Waste
Management Commission would be required to confirm consistency of a Newport
Beach waste -to -energy facility with the County Plan. The Solid Waste Facility
Permit would require conformance with all State health and safety standards.
V-11
II
7
CHAPTER VI ECONOMIC FEASIBILITY
Waste -to -energy economics can be simply expressed as follows:
Capital Costs Recovered Energy Disposal
+ = and Materials + Fee
Operating and Income Income
Maintenance
Costs
The disposal fee is the key to economic feasibility. The tipping fee, as it
is called, is similar to landfill dumping fees and is the price paid for
disposing of waste. For Newport Beach, an economically feasible
waste -to -energy facility must have a tipping fee which reduces the City's
current and projected disposal costs as described in Chapters I and II. This
chapter examines the economics of each waste -to -energy technology to determine
its economic feasibility for Newport Beach.
COMPOSTING
The economics of composting promise little advantage to Newport Beach. There
is little market for the material and only small savings would be realized in
hauling and dump fee costs. The capital and operating costs of a composting
operation would exceed the minor cost savings. For these reasons, detailed
consideration of this technology is not included in this report.
ANAEROBIC DIGESTION
The economics of anaerobic digestion to produce methane gas are promising.
Natural gas is readily marketed, and pilot scale plants have demonstrated good
production rates from MSW. Detailed economic consideration of this technology
is included later in this chapter with discussion of the CMI-ENCON technology.
PYROLYSIS
The economics of pyrolysis are not attractive. No system has been operated
successfully, and large financial losses have been experienced in the
development process. Detailed consideration of this technology is, therefore,
not included in this report.
VI-1
REFUSE DERIVED FUEL (RDF)
The economics of producing RDF for sale as a supplement to conventional fuels
have been successful in some areas of the nation. However, as shown in
Chapter IV, Energy Markets, there are no opportunities for use of RDF by
itself in Southern California. However, the use of RDF in dedicated furnaces
or boilers to produce steam and electricity is possible in Newport Beach.
Consequently, economic consideration of RDF is limited to its use in a
dedicated facility. The following data is derived from the feasibility report
for the SERRF project in Long Beach, California which plans a MSW fired
spreader stoker unit.
Construction Costs For RDF
The building and equipment costs for a Newport Beach -sized RDF facility
(175-250 TPD) are difficult to determine because all such existing or planned
facilities are much larger. Many economics of scale would be lost on a
small-scale facility.
The SERRF project (South East Resource Recovery Facility) in Long Beach,
California expects that the 1985 costs for their plant construction and
engineering will cost approximately $90,000 for each ton per day (TPD) of
capacity. The capacity of SERRF is 900 TPD. A similar, but downsized
facility, for Newport Beach is expected to cost $130,000 for each ton per day
of capacity.
Land Costs For RDF
An RDF facility for Newport Beach would require approximately ten acres of
land. The preprocessing equipment, the storage areas, and the several loading
areas demand considerable ground area. Costs for suitable land in Newport
Beach are estimated at $325,000 per acre. Accordingly, land costs for an RDF
facility might total $3.25 million.
Operating And Maintenance Costs For RDF
The experience of many RDF facilities is that the preprocessing equipment is
prone to failure and breakdown, and the O&M have been very high. However, the
few successfully operating plants and the plans for such plants demonstrate
operating and maintenance costs including labor at approximately $8,000 per
year for each ton per day of capacity.
Revenue From RDF
Sales of both energy and recovered material provide revenue from a RDF
facility. The pre-treatment and separation of refuse before incineration
increase the energy recovery efficiency above overall mass burning rates. The
materials and dollar flows for a typical RDF facility producing electricity
and steam are as follows.
VI-2
II
One RDF
Ton __> Processing Line Boilers
MSW �z
Ferrous Residue Electricity Steam Ash to
Metals to Land- 433 Kwh 500 lbs. Land-
$0.80 fill $36.00 $3.00 fill
($1.04) ($0.53)
RDF FACILITY YIELDS $38.23 PER TON MSW
Summary Of RDF Economics
Assuming a 200 TPD facility, the economics of an RDF unit are calculated on
Table VI-1. A conventionally financed 200 TPD RDF unit would require a
tipping fee of approximately $40 per ton. No groups or companies are
currently offering to finance or construct RDF units using unconventional
financing methods. Therefore, even assuming a large margin of variability in
the figures on Table VI-1, the $40 per ton fee for RDF units indicates that
this technology is not economically feasible for Newport Beach.
TABLE VI - 1
ECONOMICS OF A 200 TPD RDF UNIT
(1982 FIGURES)
ITEM
Construction $26,000,000
Land 3,250,000
Interest during construction
(3 yr. @ 10&) 8,775,000
TOTAL $38,025,000
ANNUAL COSTS
Debt Service (25 years) $ 4,146,000 (@ 10%)
O & M 1,600,000
TOTAL $ 5,746,000
REVENUE
Energy and Material Sales $ 2,791,000
Tipping Fees 2,955,000 (@ 40.47/ton)
TOTAL $ 5,746,000
VI-3
MASS BURNING STOKER UNITS
The economics of the large European -type stoker units are very similar to
those of the RDF units. Most operating and planned stoker units have large
capacities averaging 700 TPD for those generating steam and 1,200 TPD for
those generating electricity. Economics of scale are lost on smaller units.
Construction costs for mass burning units are somewhat less than RDF-fired
units because no preprocessing equipment is necessary. However, energy
recovery efficiency is somewhat lower and residue handling costs are greater.
The following economic data is derived from a variety of recent studies and
bids on large mass burning stoker units.
Construction Costs For Stoker Units
Recent bids and plans for large capacity stoker units indicate that
construction and engineering costs have averaged $50,000 to $80,000 for each
ton per day of capacity. The higher end of the range reflects expensive air
pollution controls which would be necessary in California. A similar, but
downsized, 200 TPD unit for Newport Beach is expected to cost $110,000 for
each top per day of capacity.
Land Costs For Stoker Units
A 200 TPD stoker unit would require approximately five acres of land. Less
storage and loading areas are needed for this type unit than for RDF units.
The five acres provide for truck queuing areas and employee parking. Suitable
land in Newport Beach is estimated to cost $325,000 per acre, and a five -acre
site might cost $1,625,000.
Operating And Maintenance Costs For Stoker Units
Successfully operating units and those units that are planned to be successful
demonstrate or forecast annual 0&M costs at $6,500 annually for each ton per
day of capacity.
Revenue From Stoker Units
Sales of energy and possibly recovered ferrous metal provide revenue from
stoker units. For each ton of refuse, stoker units produce approximately 475
Kwh of electricity and approximately 88 pounds of ferrous metal for sale. The
materials and dollar flows of a typical stoker unit producing both steam and
electricity are as follows:
One
Ton Stoker Unit/ %sh
MSW Boiler �Residue�
Electricity Steam Ferrous Landfills
475 Kwh 500 lbs. 88 lbs. 412 lbs.
$31.45 $3.00 $0.80 ($1.44)
A stoker unit would yield approximately $33.81 in revenue for each ton of MSW.
vI-4
J
Summary Of Stoker Unit Economics
Assuming a 200 TPD facility, the economics of a stoker unit are calculated on
Table VI-2. A conventionally financed 200 TPD stoker unit would require a
tipping fee of approximately $30 per ton. No groups or companies are
currently offering to finance or construct stoker units using unconventional
financing methods. Therefore, even assuming a large margin of variability in
the figures on Table VI-2, the $30 per ton fee for stoker units indicates that
this technology is not economically feasible for Newport Beach.
TABLE VI - 2
ECONOMICS OF A 200 TPD STOKER UNIT
(1982 Figures)
Item
Construction $22,000,000
Land 1,625,000
Interest During Construction
(3 yr. @ 10%) 7,088,000
Total Capital $30,713,000
Annual Costs
Debt Service (25 yrs. @ 10%) $ 3,350,000
0 & M 1,300,000
Total $ 4,650,000
Annual Revenue
Energy and Material Sales $ 2,468,000
Tipping Fees
(@ $29.89/ton) 2,182,000
Total $ 4,650,000
MODULAR CONTROLLED - AIR UNITS
The economics of this type technology are not attractive to Newport Beach.
Even though construction costs are relatively low, the energy recovery
efficiency and burnout ratio of modular units are poor. Additionally, no
modular unit has successfully produced electricity. The information presented
below is based on manufacturer's expectations.
VI-5
I
Construction Costs For Modular Units
Most modular units in operation were relatively inexpensive to build.
However, no modular units built to date have produced electricity or have been
required to install expensive air pollution equipment. Consequently, even
though cost of units now in operation cost only $10,000 to $20,000 per ton per
day capacity, recent estimates for electricity -producing units of the type
needed in Newport Beach indicate that construction costs will average $45,000
per ton per day capacity.
Operation And Maintenance Costs For Modular Units
Modular units require extensive maintenance and supplemental fuels.
Consequently 0&M costs for modular units of the type required are higher than
what might be expected and are estimated to average $9,000 annually for each
ton per day of capacity.
Land Costs For Modular Units
Approximately eight acres would be required for a 200 TPD modular unit.
Because a tipping floor, instead of a pit, and at least two and possibly four
incineration units are needed, this technology would require more space than a
stoker unit. At $325,000 per acre, land costs might total $2,600,000.
Revenue From Modular Units
Sales of energy and possibly recovered ferrous metal would provide revenue
from modular units. A system recently investigated for Modesto, California
would produce 242 Xwh of electricity and 1400 lbs. of steam for each ton of
MSW. The material and dollar flows for such a system are as follows:
Ton Modular
MSW ---> Incinerator �46 Boiler
0 -4 lir 4
Ferrous Ash to Steam Electricity
88 lbs. Landfill 1400 lbs. 242 Kwh
$0.80 712 lbs. $8.40 $16.02
$2.50
A modular unit would yield $22.72 in revenue for each ton of MSW.
Summary Of Modular Unit Economics
Assuming a 200 TPD facility, the economics of a modular unit are calculated on
Table VI-3. A conventionally financed, 200 TPD modular unit would require a
tipping fee of nearly $24.00 per ton. An alternate calculation assuming no
land cost and no interest during construction still yields a fee of over
$15.00 per ton. No groups or Companies are currently proposing to finance or
construct modular units using unconventional financing methods. Therefore,
even assuming a large margin of variability in the figures presented on Table
VI-3, the $24 per ton fee for modular units indicates that this technology is
not economically feasible for Newport Beach.
VI-6
TABLE VI - 3
ECONOMICS OF A 200 TPD MODULAR UNIT
(1982 Figures)
Item
Construction $ 9,000,000
Land 2,600,000
Interest during Construction
(2 yrs. @ 10%) 2,320,000
Total Capital $13,920,000
Annual Costs
Debt Service (25 yrs. @ 10%)
O & M
0
Annual Revenues
Energy and Materials
Tipping Fees
VI-7
$ 1,518,000
1,800,000
Total $ 3,398,000
$ 1,659,000
1,739,000
(@ $23.82/ton)
Total $ 3,398,000
Alternate
$9,000,000
-0-
-0-
$9,000,000
$ 981,400
1,800,000
$2,781,400
$1,659,000
1,122,400
(@ $15.38/ton)
$2,781,400
CMI-ENCON
The economics of this technology are very good because of the private,
unconventional financing arrangements. In December, 1982, the City received a
proposal from CMI-ENCON supported by Southern California Edison to finance,
construct, and operate a waste -to -energy facility. Detailed economic data is
presented in the proposal document. A summary of some of that information is
presented here.
CMI-ENCON proposed a beginning tipping fee of $4.57 based on a 250 TPD
facility. The City would guarantee delivery of MSW and wastewater on a
put -or -pay basis and provide the land. The City might have to fund some sewer'
connections and would provide reimbursable funds for the permitting process.
On the basis of projections and guarantees, the technology may be economically
feasible for Newport Beach.
Construction Costs For CMI-ENCON
The capital cost cited in the proposal for buildings and equipment is
$35,159,300. This translates to over $140,000 for each ton per day of
capacity.
Land Cost For CMI-ENCON
The proposal cites a need for thirteen acres for a 250 TPD plant, but the City
is to provide this land at a "nominal" base rate. In other words, the City
provides the land at virtually no cost to CMI-ENCON. Using the $325,000 per
acre figure mentioned for other technologies, the City would need to provide
land worth approximately $4,225,000.
Operation And Maintenance Costs For CMI-ENCON
The proposal cites first -year operating expenses of $3,328,600 not including
tailings disposal. However, this figure includes only $100,400 for property
tax, and considering the $350000,000 investment, this figure should be over
$350,000. 0&M costs are therefore estimated at $3,500,000 per year. This
equates to $14,000 annually for each ton per day of capacity.
Revenues From CMI-ENCON
Sales of natural gas, electricity, and recovered materials provide revenues
from this technology. The energy efficiencies cited in the proposal reflect
optimal performance and may be overly optimistic. However, system guarantee
insurance is provided. Also, the proposal uses energy and recovered
materials' prices that are higher than 1982 rates. The differing rates and
their effect on revenues are presented on Table VI-4. The differences in sale
prices could change tipping fees by almost $8 per ton.
VI-8
TABLE VI - 4 .
CMI-ENCON REVENUES PER TON MSW
CMI-ENCON
Item •
Amount
1982 Price
Price
Gas
93 therms
at $0.56
at $0.5816
($5.70/MCP with
1 MCP = 9.8 therms)
Electricity
355 Kwh
at $0.0662
at $0.077
Ferrous
.0545 tons
at $18
at $35
Non -Ferrous
.0075 tons
at $500
at $650
Ash to
Landfill
.148 ton
at ($7)
at ($7)
Net Revenue per Ton
(Amount x Price)
$79.28
$87.17
Summary Of CMI-ENCON Economics
Despite the detailed costing information contained in it, the CMI-ENCON
proposal is still a generalized offer to build and operate a facility in
exchange for free use of land, a guaranteed waste stream, and a tipping fee of
approximately $5.00 per ton. On that basis alone, the CMI-ENCON technology
has the potential to be economically feasible for Newport Beach.
However, many unanswered questions remain. The City must provide thirteen
acres of land somehow. Energy prices will need to rise somewhat to fulfill
CMI-ENCON projections.- The location must be pinpointed to determine the
City's cost to extend sewer lines to the site. All costs and revenues must be
precisely calculated at an early time because a difference of only a few
percentage points within a $10 million annual budget can make or break the
financial feasibility of the project for the City.
VI-9
a
O'CONNOR COMBUSTOR
The economics of this technology are promising because of private financing
arrangements. A project team has been assembled to plan, engineer, construct,
and operate a facility using the O'Connor Rotary Combustor, and preliminary
economic figures have been generated. The O'Connor proposal is contained in a
separate document.
Construction Costs for O'Connor Combustor
The O'Connor proposal cites four different plant configurations to produce
steam and/or electricity in various combinations. The total construction
costs including interest payments during construction range between
$19,775,913 and $21,227,461. The average cost of $20,431,210 for a 200 TPD
facility yields construction costs of $102,156 for each ton per day of
capacity.
Lana Costs for O'Connor Combustor
The O'Connor System would require approximately four acres, and the proposal
assumes the use of City land at no cost. Using the $325#000 per acre figure,
the City would need to provide land worth approximately $1.3 million.
Operation and Maintenance Costs for O'Connor Combustor
The O'Connor proposal cites first year 0 & M costs ranging from $1,906,584 to
$1,948,214. These figures yield average annual 0 & M costs of $9,637 per ton
per day of capacity.
Revenues from O'Connor Combustor
Sales of electricity, steam, and possibly ferrous metals provide revenue from
this technology. The material and dollar flows of the O'Connor System are
very similar to stoker and RDF units (see pp VI-3 and VI-4) and would be
expected to yield revenue of approximately $35,00 per ton of MSW at 1982
energy prices.
However, the proposal submitted by O'Connor cites various combinations of
steam and electricity output levels and cites various energy prices to
calculate revenues ranging between $42 and $68 per ton. This results from the
use of energy prices which are significantly higher than the 1982 prices cited
in Chapter IV as shown below:
VI-10
I
r
.1
1982
O'Connor
Item
Price
Price
Electricity
6.624/Kwh
9.15�/Kwh
Steam
(natural gas
equivalent)
56C/therm
80�/therm
The O'Connor proposal also adds to revenues the earnings on operating revenues
which amounts to approximately $337,000 per year. Accordingly, depending on
the assumptions used, revenues from the O'Connor system can range from
approximately $35 to more than $68 per ton of MSW received.
Summary of O'Connor Economics
The O'Connor proposal cites four different scenarios with tipping fees ranging
from $15.24 per ton to a profit of $13.69 per ton. These figures are subject
to verification of various assumptions and forecasts. Nevertheless, the
proposal indicates a generalized offer to build and operate a facility in
exchange for free use of land, a guaranteed waste stream, and a tipping fee
which has the potential to be lower than what the County will charge. On that
basis, the O'Connor technology has the potential to be economically feasible
for Newport Beach.
The same unanswered questions relating to the CMI-ENCON technology also
pertain to the O'Connor technology.
VI-11
I
CONCLUSIONS ON ECONOMIC FEASIBILITY
From the foregoing analysis it appears that until cost or revenue factors
change substantially, a facility attractive to Newport Beach must be privately
financed. Debt service accounts for a large portion of tipping fees, and
private owners would be able to reduce those costs by tax leveraging.
Consequently, only those technologies supported by private enterprise are
considered economically feasible.
There is no indication that cost or revenue factors will change soon. Energy
demand and prices are falling. Many waste -to -energy and cogeneration
facilities are being planned which when built will further reduce energy
prices using the "avoided costs" concept. Hauling costs appear to have
stabilized for some time due to lower fuel costs and lower increases in labor
rates. Interest rates may be falling to some extent but are not expected
within the next few years to fall below 8 percent to 10 percent.
Consequently, the 1982-83 cost/revenue factors cited above are expected to
prevail for two or three years.
The tipping fees projected for conventionally financed facilities are much too
high for favorable consideration. Cost/revenue factors would need to be
dramatically altered to lower a $30 to $40 tipping fee to where it is
competitive with a $7 to $10 fee. Even the $4.57 fee proposed by CHI-ENCON is
only marginally attractive when considering the other costs and risks to the
City. Only private financing offers the potential for an attractive facility.
Also, substantial ,financial risks would confront the City. It must be kept in
mind that the City seeks to save only a few hundred thousand dollars per year;
and, a discrepancy of only a few percentage points on the $5 million to $10
million annual budget required for a facility can make or break the economics.
Many cities have lost millions of dollars on poor performing facilities. The
willingness of private capital to assume such risks indicates a reliable and
desirable system.
The only systems offering complete private financing at this time are
CMI-ENCON and O'Connor Combustor.
VI-12
CHAPTER VII ENVIRONMENTAL IMPACTS
A waste -to -energy facility will require an extensive Environmental Impact
Report on a specific project at a specific site. This chapter provides a
brief summary of the major environmental issues.
DESCRIPTION OF THE PROJECT
The most feasible type of facility for Newport Beach would be either the
massburning O'Connor Combustor or the CMI-ENCON combination. Either of these
technologies would process 200 TPD to 250 TPD on a seven -day -per -week basis.
That means that 280 TPD to 350 TPD would be delivered each weekday. (Some
weekend deliveries may occur in summer for beach cleaning.) Descriptions and
illustrations of these two technologies are presented in Chapter III.
LOCATION OF THE PROJECT
Potential sites exist throughout the City. The O'Connor technology requires
only three acres and conceivably could be located just about anywhere in the
City. The CMI-ENCON facility requires thirteen acres and a supply of waste
water. An open area such as that in West Newport would be the most likely
location for the CMI-ENCON technology.
ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
Air Quality
A waste -to -energy facility will produce various atmospheric pollutants. These
include carbon dioxide (CO ), carbon monoxide (CO), hydrocarbons (Hu),
nitrogen oxides (NO ), hydroc9loric acid (HCL), dioxin, and a variety of heavy
metals attached to particulates. The amounts of each pollutant vary with each
technology.
Generally, the CMI-ENCON process is expected to produce less air pollutants
for three basic reasons. First, the pretreatment will sort out
obviously hazardous items. Second, the biological process will convert many
of the constituent elements (carbon, hydrogen, oxygen, and sulfur) to natural
gas, and the chemical process will filter out impurities. Third, the thermal
process uses a controlled air principle to minimize formation of atmospheric
pollutants.
VII-1
The amounts of atmospheric pollutants released from waste -to -energy facilities
are subject to much controversy. Some facilities have been shut down for
failure to meet applicable standards. Technology has improved, however, and
recent operating results are promising. Amounts of major pollutants such as
CO2, CO, HC, NOx, and SO can be measured and controlled fairly well. Trace
amounts of toxic heavy meals, HCL and dioxin, receive the most notoriety even
though tests have shown that concentrations amount to less than one percent of
allowable uptake levels.
Mitigation measures may allow an actual reduction in regional air pollutants.
In -plant control technologies such as scrubbers, precipitators, and bag houses
can eliminate 50 percent to 99 percent of all emissions. Additionally,
offsets from decreased hauling times, decreased landfill emissions, and
decreased electrical power generation emissions can amount to more than plant
emissions resulting in a net loss of air pollutants. The most stringent
regulations including New Source Review and Best Available Control Technology
will be applicable to the project. The AQMD will issue only a conditional
Permit to Operate which will require constant performance monitoring. Should
the facility fail to meet operating standards, it would be closed down.
Vehicle Traffic
The project will attract a variety of refuse -carrying vehicles and will
generate traffic from employee and ash residue vehicles. Approximately 50 to
80 assorted refuse -carrying vehicles will visit the site each weekday. These
load packer, dump, and pickup type vehicles will therefore account for 100 to
160 trips per weekday. The number of employees required is ten per shift for
CMI-ENCON and'four per shift for O'Connor which respectively would generate 60
and 24 vehicle trips per day. Additionally, two loads of ash in 20-ton
transfer vehicles and approximately one load per day of recovered materials
will need to be hauled away from the site and, therefore, will generate
another six vehicle trips per day. Except for the changing of one shift, most
vehicle trips will occur during regular working hours on weekdays. The number
of vehicle trips will total approximately 130 to 230 on weekdays and 30 to 70
on weekend days.
Mitigation of traffic impacts can be achieved by designating specific access
roads and off -site employee parking. Depending on the location of the
project, traffic impacts in other parts of the City should be eliminated.
Noise
Vehicle and equipment noise will be generated by the project. Dumping and
pretreatment equipment will produce various noises throughout the day.
Turbine generators, induced draft fans, and incinerators will produce constant
noise.
Most of this noise will be mitigated by enclosing all processes within
buildings which may include sound -absorbing insulation. Sound levels at
operating plants have been limited to 55 to 60 dB(A) measured at the property
line.
V11-2
I
1
I
Odor and Dust
No odors or dust are expected to be released from the buildings which are kept
at a slight negative air pressure by pulling process air from within.
Vectors
Because pits and tipping floors are periodically cleaned completely, neither
vermin nor insects have been problems at operating facilities.
Aesthetics
The project is an industrial process using heavy equipment with various
stacks, towers, and outlets. The site is visited by large, noisy, and often
dirty vehicles. The treatment and processing of trash and sewage is an
exceptionally displeasing neighbor.
Mitigation of aesthetic impacts have been achieved by enclosing all process
within attractive buildings which are further shielded by attractive
landscaping. The height of buildings and stacks can be limited by use of
subterranean elevations and careful equipment design.
Safety
A waste -to -energy facility presents various fire, explosion, and break -down
hazards. MSW occasionally contains smoldering embers or lighted cigarettes
which cause fires. Also, MSW occasionally contains explosives or ammunition
which can be sparked by incineration or shredding processes causing
explosions. Major breakdowns and spills are possible because of earthquakes
or equipment failure.
Mitigation of these hazards take several forms. Worker safety is promoted
through a variety of protective and shielding devices. Automatic sprinkler
systems control fires. Explosion vents and shields are designed into all
susceptible equipment. Earthquake damage is minimized through structural
designs, and spillages are controlled by troughs, moats, and drains. All
industrial health and safety regulations will apply to such a facility.
VII-3
i
r
APPENDIX A
CALCULATIONS FOR MSW DISPOSAL
COST REDUCTION ALTERNATIVES
II
II
I!
II
II
It
It
MILEAGE BETWEEN COLLECTION AND DISPOSAL POINTS
s
To:
From:
City Yard
Coyote
HB Tran
Bee
Canyon
Station
Canyon
City Yard
—
9.3
8.9
17
Mon.
1.3
9.3
9.4
18.2
�o
v
L
a
Tue.
.6
8.5
8.6
17.3
c
0
w
Wed. (1)
2.7
6.6
10.1
14.6
0
U
>.
Wed. (2)
3.2
5.8
11.8
14.9
ra
c
Thur. (1)
4.8
4.2
10.4
13.1
Thur. (2)
4.8
7.5
12.5
15.8
Fri.
5.8
5.5
12.4
15.1
A-1
TYPICAL WORKDAYI REFUSE VEHICLE
MILEAGE TO ALTERNATIVE DISPOSAL SITES
COYOTE CANYON FROM
DAY OF WEEK COLLECTION POINT
Vehicle
Type
Mon
Tues
W(1
W(2)
Th(1
Th(2)
Fri
Avg
Change
29 yd
19.9
18.4
18.6 .3
18.31.6
20.6
19.48
-0-
16 yd
38.5
35.4
31.89.9
26.76.E
31.6
33.6
-0-
BEE CANYON
29 yd
36.5
34.9
34.55.1
34.97.E
37.9
36.1
+16.6
16 yd
72.9
69.5
6!3 54.9
61.19.2
68.1
68.0
+34.4
HUNTINGTON BEACH TRANSFER STATION
29 yd
19.E
:18.1
21.73.1
24.16.2
27.1
22.47
+3.0
16 yd
38.4
35.3
41.45.1
44.91,8
51.9
43.49
+9.9
NEWPORT BEACH CITY YARD
29 yd
2.6
1.2
5.4
9.6
11.6
6.8
-12.7
.4
.6
16 yd
5.2
2.4
10.82.8
20.20.2
23.2
13.6
-20.0
COYOTE CANYON
Vehicle
Tvi3e
Mon
Tues
Th(2)
Avg
'Change
38 yd
19.9
--
21.6
20.472
-0-
10 yd
38.5
35.4
--
36.95
-0-
BEE CANYON
38 yd
36.5
--
37.E
1
136.87z
+16.4
10 yd
72
171.25
+34.3
HUNTINGTON BEACH TRANSFER STATION
38 yd
19.E
1 --
1
1 26.2
21.8
1.33
10 yd
38.4
35.3
--
36.85
- .01
NEWPORT BEACH CITY YARD
38 yd
2.6
--
9.6
4.93
-15.54
10 yd
5.2
2.4
--
3.80
-33.15
-'Assumes 1 trip/day by 38 yd and 29 yd and 2 trips/day by 10 yd and 16 ydj
A-2
2Wei ghted 2/3 toward Mon. J
LABOR COSTS FOR HAULING MSW PER MILE
Vehicle
Type
29 yd
16 yd +
10 yd
38 yd
Other Field
Main Div.
Utility
Dept.
W3 P-
Crew
1 lead
(+ 15%)
1 lead
1 crew
1 EOII
1 lab.
1 lab
(E step)
1 UT. SR.
or
1 UT. Const.
Sp.
1 G/G
or
1 TTI
Annual
Salary
w/40% fringe
$35,400
$59,900
$49,320
$25,700
$29,500 y
(Average)
$26,360
$/Hour
at 2,000/
Year
$17.7
$29.95
$24.66
$12.83
$14.75
$13.18
A-3
ANNUAL COST
DIFFERENTIAL TO HAUL
NSW
TO BEE CANYON
Annual.
Miles
�
$/mile
Times
Beyond
Total
Total
Total$
Vehicle
(Table
Mileage
Coyote
Annual
Hours
Annua
Type
I-4)
Incurred
Canyon
Miles
@25mph
Costil
Qen'1 Ser
29 yd
2.04
1512
+16.6
25,099
1004
51,20
16 yd
1.99
2226
+34.4
76,574
3063
152,38 1
10 yd
1.67
102
+34.3
3,499
140
5,843
38 yd
2.01
144
+16.4
2,362
94
4,74
Other
1.51
1608
+16.6
2,669
107
4,03
Utility
1.89
280
+16.6
4,648
186
8178
PBR
1.53
624
+16.6
10,358
414
15,848
Toil
2�
i
�i
REQUIRED NEW VEHICLES AND COSTS
BASED ON TOTAL HOURS
Anmyal Cnet
Vehicle
Number
Needed
Capital
Cost
Labor
Vehicle
0&M
Total
29 yd
1
900000
35,400
17,000
52,400
16 yd
2
140,000
119,800
34,000
153,800
Total
3
$2301000
$206,200
ANNUAL COST DIFFERENTIAL TO HAUL MSW
TO HUNTINGTON BEACH TRANSFER STATION
Annual
Miles
$/mile
Times
Beyond
Total
Vehicle
(Table
Mileage
Coyote
Annual
Type
I-4)
Incurred
Canyon
Miles
Gen'l Ser
29 yd
2.04
1512
+3.0
4,536
16 yd
1.99
2226
+9.9
22,037
10 yd
1.67
102
-.1
-10
38 yd
2.01
144
+1.33
191
Other
1.51
1608
+3.0
4,824
Utility
1.89
280
+3.0
840
PBR
1.53
624
+3.0
1,872
REQUIRED NEW
BASED ON
Number
Cap
Vehicle
Needed
C
16 yd
1
$7(
Total
Hours
@25mph
Total
Annual
Cost
181' 9,253
881 43,854
-1
-17
8
385
193
7,284
34
1,588
75
2,864
Total
$65,211
ANNUAL COST DIFFERENTIAL TO HAUL MSW
TO CITY YARD
Annual
$/mile
Times
Vehicle
(Table
Mileage
Type
I-4)
Incurred
Gen'1 Ser
29 yd
2.04
1512
16 yd
1.99
2226
10 yd
1.67
102
38 yd
2.01
144
Other
1.51
1608
Utility
1.89
280
PBR
1.53
624
Miles
Beyond
Total
Total
Total
Coyote
Annual
Hours
Annua
Canyon
Miles
@25mph
Cost
-12.7
-19,202
- 768
-39,173
-20.0
-44,520
-1781
-88,59
-33.15
- 3,381
- 135
- 5,64
-15.54
- 2,238
- 89
- 4,49
-12.7
-20,422
- 817
-30,83
-12.7
- 3,556
- 142
- 6,72
-12.7
- 7,925
- 317
-12,12
Total (Savings)
- 18
VEHICLES AND COSTS SAVINGS
BASED ON TOTAL HOURS
Annilml Gnat
Number
Vehicle Saved
Capital
I Cost
I Labor
Vehicle
I 0&M
I Total
16 yd 2
$140,000
$119,800
$34,000
$153,800
A-6