Arch. and Struct.-Commercial Plan Check Corrections
It is the responsibility of the applicant to satisfy the requirements (clearances) of each of the departments listed in this document.
Normally, each section will stamp your plans indicating their approval.
To view your plan check status and the latest correction list on the Internet, please visit: http://www.ocplanning.net and click on
'Plan Check Status' Link.
Please note that Planning and Development Services (PDS) Public Counter Hours are open Monday thru Friday
from 7:30 a.m. to 5:00 p.m. except holidays.
Project Number:RW130061
Submittal Date:Jun 06, 2013
CBC Edition: 2010
Plan Check Date: 6/20/2013 9:20 AM
Description:Site retaining walls
and site perament
RW/shoring/caisson/GB/laggin
g system for new
SFD.
Job Address
29 AVALON VISTA
NEWPORT COAST, CA
Owner Address
Mark Moshayedi
14 Channel Vista
Newport Coast CA
1st Plan Check 2/22/13 Current - 1st Recheck
Plan Checked By
Edmund Lee
Edmund.Lee@ocpw.ocgov.com
(714) 667-8872
Contact Address
Sheila Patterson-Wright
139 Avenida Navarro
San Clemente CA92672-1
949-492-8586
949-492-8586 FAX
swright@toalengineering.com
Page 1 of 8
RW130061
OBTAIN CLEARANCES (approvals) from:
Current Planning/Zoning (714) 834-2626
GENERAL INFORMATION
Application for which no permit is issued within 180 days following the date of application shall expire by limitation.
An extension of 180 days may be granted upon written request showing circumstances beyond the control of the applicant
have prevented action being taken. In order to renew action for an application after expiration, the applicant
shall resubmit plans and pay a new plan check fee.
Valid Worker´s Compensation Certificate or Owner-Builder Verification is required prior to issuance of building
permits.
Major corrections shall be made on the original tracing and new prints submitted.
The correction list is available on the Internet at http://pdsd.oc.ca.gov (Click on the services tab, then the
Plan Check Processing link).
A grading permit is required. Retaining walls permit will not be issued until Grading permit is issued.
The Civil Engineer or Architect who is responsible for the project shall sign final approved sets of plans.
Note on this correction sheet the location of the completed correction on your plans.
Site Retaining Wall and site perament RW/shoring/caisson/GB/lagging system will be approved until geotechnical
report & grading permit is approved and release.
Page 2 of 8 6/20/2013 9:20 AM
RW130061
NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) NOTES
Notes must be shown as worded, on the title sheet of the plan
1. In the case of emergency, call___________________at Work Phone #___________________or Home Phone #_________
__________.
2. Sediment from areas disturbed by construction shall be retained on site using structural controls to the maximum
extent practicable.
3. Stockpiles of soil shall be properly contained to minimize sediment transport from the site to streets, drainage
facilities or adjacent properties via runoff, vehicle tacking, or wind.
4. Appropriate BMP's for construction-related materials, wastes, spills shall be implemented to minimize transport
from the site to streets, drainage facilities, or adjoining properties by wind or runoff.
5. Runoff from equipment and vehicle washing shall be contained at construction sites unless treated to reduce
or remove sediment and other pollutants.
6. All construction contractor and subcontractor personnel are to be made aware or the required best management
practices and good housekeeping measures for the project site and any associated construction staging areas.
7. At the end of each day of construction activity all construction debris and waste materials shall be collected
and properly disposed in trash or recycle bins.
8. Construction sites shall be maintained in such a condition that an anticipated storm does not carry wastes or
pollutants off the site. Discharges of material other than stormwater only when necessary for performance and
completion of construction practices and where they do not: cause or contribute to a violation of any water quality
standard; cause or threaten to cause pollution, contamination, or nuisance; or contain a hazardous substance in
a quantity reportable under Federal Regulations 40 CFR Parts 117 and 302.
9. Potential pollutants include but are not limited to: solid or liquid chemical spills; wastes from paints, stains,
sealants, glues, limes, pesticides, herbicides, wood preservatives and solvents; asbestos fibers, paint flakes
or stucco fragments; fuels, oils, lubricants, and hydraulic, radiator or battery fluids; fertilizers, vehicle/equipment
wash water and concrete wash water; concrete, detergent or floatable wastes; wastes from any engine/equipment
steam cleaning or chemical degreasing and superchlorinated potable water line flushing.
During construction, permittee shall dispose of such materials in a specified and controlled temporary area on
-site, physically separated from potential stormwater runoff, with ultimate disposal in accordance with local,
state and federal requirements.
10. Dewatering of contaminated groundwater, or discharging contaminated soils via surface erosion is prohibited.
Dewatering of non-contaminated groundwater requires a National Pollutant Discharge Elimination System Permit from
the respective State Regional Water Quality Control Board.
11. Graded areas on the permitted area perimeter must drain away from the face of slopes at the conclusion of each
working day. Drainage is to be directed toward desilting facilities.
12. The permittee and contractor shall be responsible and shall take necessary precautions to prevent public trespass
onto areas where impounded water creates a hazardous condition.
13. The permittee and contractor shall inspect the erosion control work and insure that the work is in accordance
with the approved plans.
14. The permittee shall notify all general contractors, subcontractors, material suppliers, lessees, and property
owners: that dumping of chemicals into the storm drain system or the watershed is prohibited.
15. Equipment and workers for emergency work shall be made available at all times during the rainy season. Necessary
materials shall be available on site and stockpiled at convenient locations to facilitate rapid construction of
temporary devices when rain is imminent.
16. All removable erosion protective devices shall be in place at the end of each working day when the 5-Day Rain
Probability Forecast exceeds 40%.
Page 3 of 8 6/20/2013 9:20 AM
RW130061
17. Sediments from areas disturbed by construction shall be retained on site using an effective combination of
erosion and sediment controls to the maximum extent practicable, and stockpiles of soil shall be properly containted
to minimize sediment transport from the site to streets, drainage facilities of adjacent properties via runoff,
vehicle tracking, or wind.
18. Appropriate BMPs for construction-related materials, wastes, spills or residues shall be implemented and retained
on site to minimize transport from the site to streets, drainage facilities, or adjoining property by wind or
runoff.
Page 4 of 8 6/20/2013 9:20 AM
RW130061
Arch. and Struct.-Commercial Plan Check Corrections
Sheet Comments By
Plot Plan
E. Lee1 In your responses, please refer to the alpha-numeric reference numbers that are
shown at the start of each of the following correction items.
Pending E. Lee2 Response sheet item number shall match with proiveded outstanding list for consistency.
Pending E. Lee3 No response & requested info not found from the plan.---- See sheet SWP, and color
comment. Please add & refined the scope of shoring/caisson/lagging/rw wall/grade
beam & retaining walls work based on site proposed & permit application description.,
(b) No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
and GB application.----- a complete retaining wall types, height to bottom of footing,
length, setback, backfill or earthslope, etc. shall add to the sheet when resubmittal.
(c) RW wall detail matrix not found--- No retaining wall A, B,C schedule, and full
description found from sheet SWP, (d) OK-- Each new proposed RW wall shall have
a specific detail reference at a specific location or section, please clarify &
revise current sheet SWP detail reference, (e) OK-- Please provide a separate wall
type legend for the building bearing perimeter wall or /and basement wall in term
of proposed group of RW wall, wall type index is identical and confused.
Pending E. Lee4 Please (a) OK--- reprint sheet 3 for shoring, caisson & lagging, which is not legible
to read, (b) No response & requested info not found from the plan.---- Add proposed
shoring, caisson & lagging scope of work description to the plan, including wall
height, length, grad beam size, length, each caisson size, depth etc., (c) OK--
please clarify where is the grid lines A to J reference from? which is not found
from sheet SWP?
Pending E. Lee5 No response & requested info not found from the plan. No civil drawings found in
the package, please be be advised this permit is separate from civil dramings and
GB application.----- Show clearly property line with exact dimensions adjacent to
retaining wall.
Pending E. Lee6 No response & requested info not found from the plan. No civil drawings found in
the package, please be be advised this permit is separate from civil dramings and
GB application.----- Show existing and proposed contours/spot elevations to indicate
general site slope and drainage pattern.
Pending E. Lee7 No response & requested info not found from the plan. No civil drawings found in
the package, please be be advised this permit is separate from civil dramings and
GB application.----- On site plan delineate all projecting wall elements, and show
distance to property line, or adjacent structures.
Pending E. Lee8 No response & requested info not found from the plan. No civil drawings found in
the package, please be be advised this permit is separate from civil dramings and
GB application.----- All site & various height of retaining walls shall be shown
on the issued Grading Plan. Please provide
this issued Grading Plan for verification. If this issued Grading Plan does not
show these retaining walls, please revise to show these walls and resubmit.
Page 5 of 8 6/20/2013 9:20 AM = Indicates line item not Cleared.
RW130061
Arch. and Struct.-Commercial Plan Check Corrections
Sheet Comments By
Pending E. Lee9 No response & requested info not found from the plan. No civil drawings found in
the package, please be be advised this permit is separate from civil dramings and
GB application.----- Complete attached County retaining wall , etc. form matrix
which shall comply with proposed construction document. Once confirmed, please scan
to the plan title sheet when resubmittal.
General requirements:
Pending E. Lee10 In your responses, please refer to the alpha-numeric reference numbers that
are shown at the start of each of the following correction items. (b) Response sheet
item number shall match with proiveded outstanding list for consistency.
Pending E. Lee11 No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
and GB application.----- Clearly identify new retaining walls length & height information
on the site
plan. Provide a complete elevation view for the retaining walls, indicate specific
elevation information at top of wall, finished grade elevation, at point of height
change location, from the lowest adjacent grade within 5 feet or 10 feet from the
proposed site. (b) Clarify any catch basin or drain box behind the retaining wall
along the line?
Pending E. Lee12 Provide a copy of permit from the California Division of Industrial Safety for
excavations or trenches over 5 ft
vertical cuts. Note on the plans: "A copy of CALOSHA permit shall be submitted
to Building Inspector prior to excavation."
Pending E. Lee13 No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
and GB application.----- See plan, please indicate property line, basement wall
lines location, setback distance away from the shoring elements.
Pending E. Lee14 Requested name and ink signature not found from sheet SWN-2.---- For projects
requiring special inspection and/or structural observation, Form 00-01 and/or 00
-02 shall be completed by the architect, engineer, or owner and scan on the 1st
sheet of plans (the site plan). If no special inspection and/or structural observation
are required, the architect or engineer needs to include a note on the Site Plan
to indicate that it is not required.
NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM
Pending E. Lee15 No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
and GB application.----- Include "National Pollutant Discharge Elimination System
Notes" on first sheet of plans. (This information is provided in the beginning of
this document) , see sheet 1, please filled-out required information at top of form.
Pending E. Lee16 No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
Page 6 of 8 6/20/2013 9:20 AM = Indicates line item not Cleared.
RW130061
Arch. and Struct.-Commercial Plan Check Corrections
Sheet Comments By
and GB application.----- Provide Erosion and Sediment Control(ESCP) plan. Show gravel
-sandbag location, detail and minimum 10´ x 10´ concrete washout areas to the site
plan. This is separate from Civil drawing and GB application. (a) Add & scan the
entire BMP, ESCP-Small Area Checklist form to the plan when resubmittal.
Site Retaining Wall and site perament RW/shoring/caisson/GB/lagging system:
Pending E. Lee17 (a) Response sheet item number shall match with proiveded outstanding list for
consistency.,(b) Clarify & response to each color comment from the design calculation
and plan.
Pending E. Lee18 Soil report shall be review and approved by the County geologist prior to permit
approval & issurance.
Pending E. Lee19 No response & requested info not found from the plan.-- Geotechnical engineer
to review, approve, ink stamp and signed on SWP & SWD series of sheets and details
when resubmittal.
Pending E. Lee20 No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
and GB application.----- All retaining walls & shoring/caisson/lagging/GB/RW proposed
improvement shall be shown on the approved Grading Plan (GB120111 still under reviewed
and not approved yet) . Please provide this approved Grading Plan for verification.
If this approved Grading Plan does not show these retaining walls, please revise
to show these items and resubmit for recheck.
Pending E. Lee21 Retaining walls permit will not issue until (a) geotechnical report obtain approval,
(b) grading permit has been approved & issued.
Pending E. Lee22 No response & requested info not found from the plan.---- See design calculation
for the permanent shoring pages and soil report recommendation p. 32, (a) clarify
& revise passive resistance for caisson of 450 plf instead of 900 plf used in the
design process, (b) add and incorporate soil report recommendation of lateral creep
loading of 1000 plf of the embedment in the creep zone into the design calculation,
please revise, (c) reflect this information to sheet SWN-1, (d) Identify creep zone
depth and dimension to the detail sheet of SWD3.
Pending E. Lee23 No response & requested info not found from the plan.---- See geotechnical report
p. 28-303, (a) please clarify and add add seismic load effect to each type of RW
wall design per geotechnical report recommendation, (b) re-design RW recommendation
and reflect to the detail sheets.
Pending E. Lee24 No response & requested info not found from the plan.---- Surcharge loads on retaining
walls design formula is not a part of CRC or CBC or from provided geotechnical report,
please clarify and provide background document, ( it were shown on the city & county
of LA building codes before, not there anymore ) , Please certify and concurred
by the geotechnical engineer for that formula used.
Page 7 of 8 6/20/2013 9:20 AM = Indicates line item not Cleared.
RW130061
Arch. and Struct.-Commercial Plan Check Corrections
Sheet Comments By
Pending E. Lee25 Clearly identify new retaining walls on plans with their each RW #, length & height
and setback distance to the property line information on the site plan & constructoion
section. Provide a complete elevation view for the retaining walls, indicate specific
elevation information at top of wall, finished grade elevation, at point of height
change location, from the lowest adjacent grade within 5 feet or 10 feet from the
proposed site. (b) Clarify any catch basin or drain box behind the retaining wall
along the line per approved soil report.
Pending E. Lee26 On site plan delineate all projecting shoring wall elements, and show distance
to property line, or adjacent structures.
Pending E. Lee27 No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
and GB application.----- All site & various height of shoring walls or related caisson
or pile shall be shown on the issued Grading Plan. Please provide this issued Grading
Plan for verification. If this issued Grading Plan does not show these retaining
walls, please revise to show these walls and resubmit.
Pending E. Lee28 Not Found--- Final set of plan, design calculation shall be stamped and wet signed
by Civil Engineer and Geotechnical Engineer.
Pending E. Lee29 No response & requested info not found from the plan. No civil drawings found
in the package, please be be advised this permit is separate from civil dramings
and GB application.----- Daylight setback dimension or information shall matched
with approved soil report. Please add to each elevation and section view of the
plan.
Page 8 of 8 6/20/2013 9:20 AM = Indicates line item not Cleared.