CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
March 26, 2024
Agenda Item No. 4
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Michael J. Sinacori, Assistant City Engineer949-644-3342
msinacori@newportbeachca.gov
TITLE: Underground Utility Assessment District No. 111, Underground
Utilities District No. 22 Phase 2 & 3, & Utility Undergrounding for
McFadden Alleys and Court Street — Notice of Completion for
Contract No. 7833-1 (21 A11)
ABSTRACT -
On August 25, 2020, the City Council awarded Contract No. 7833-1 for the Underground
Utility Assessment District No. 111, Underground Utilities District No. 22 Phase 2 & 3, &
Utility Undergrounding for McFadden Alleys and Court Street project to Asplundh
Construction Corp. The project replaced existing overhead utilities with a new
underground system. The work is now complete and staff requests City Council
acceptance and close out of the contract. In addition, this Council action reconciles
revenue and expenditures for additional requested work by Verizon and Crown Castle.
RECOMMENDATIONS:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code;
c) Release Faithful Performance Bond one year after acceptance by the City Council;
d) Authorize staff to proceed with the final Verizon additional work and increase project
contingency from $3,500,000 to $3,595,003 (approximately 51.6 percent of the
contract award) to cover the additional cost of the requested additional work; and
e) Approve Budget Amendment No. 24-058 recognizing $31,872.75 in contribution
revenue from Crown Castle to Account No. 13501-561007-21A11 and $159,250.85 in
increased expenditures in Account No. 13501-980000-21A11 (UUD22-1 CIP
Expenditures for GL) from multiple utility companies.
4-1
Underground Utility Assessment District No. 111, Underground Utilities District No. 22
Phase 2 & 3, & Utility Undergrounding for McFadden Alleys and Court Street —
Notice of Completion for Contract No. 7833-1 (21A11)
March 26, 2024
Page 2
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$6,969,777.79
$10,564,781.14
10% or less
+51.6%
+49.4%
+2.2%
Allowed Contract Time +
220
Actual Time
0
Approved Extensions (days) =
Under (-) or Over (+)
The Underground Utility Assessment District No. 111 (AD 111), Underground Utilities
District No. 22 Phase 2 & 3 (UUD22), & Utility Undergrounding for McFadden Alleys and
Court Street project is the third City of Newport Beach managed and constructed utility
undergrounding project that undergrounded overhead power, telephone and cable
facilities on the Balboa Peninsula. AD 111 is the area between 31st Street and 23rd Street,
on the east and west side of Balboa Boulevard. UUD22 Phase 2 & 3 is the Balboa
Boulevard area between 36th Street and 20th Street including portions of the McFadden
Alleys and Court Street (Attachment A).
The contract specifically provided for traffic control, water pollution control, trenching,
construction of vaults, vents, pull boxes, handholes, installing conduit, and associated
items necessary such as backfilling, pavement restoration, resurfacing and replacement
of concrete improvements for the conversion of existing overhead electrical power,
telephone and cable television services to underground locations.
The project included the partners of Southern California Edison (SCE), AT&T, Spectrum,
Crown Castle, ExteNet Systems and MCI Business for the UUD22 Phase 2 and 3 work
on Balboa Boulevard. During construction, ExteNet Systems requested additional work,
which it funded. Change orders for the base contract work were minimal and this extra
work was absorbed within the City Council authorized 10% contingency.
On February 13, 2018, the City Council approved the "Enhanced Services and Priority
Communications Zone Master License Agreement" with Verizon Wireless. In June 2021,
ExteNet Systems and MCI Business (both Verizon Subsidiaries) requested additional
work to continue their efforts on the Balboa Peninsula for the small cell system and
backbone fiber optics network that these two companies were completing as part of their
Master License Agreement. In an effort to reduce staff permitting and review efforts, and
to better coordinate with other UUD22 project work in the area, additional ExteNet and
MCI Business funded improvements were authorized (October 14, 2021) and installed
(between 12th Street and Medina Way), increasing the total contract cost to $8,698,386.99
(or 24.8 percent above base).
4-2
Underground Utility Assessment District No. 111, Underground Utilities District No. 22
Phase 2 & 3, & Utility Undergrounding for McFadden Alleys and Court Street —
Notice of Completion for Contract No. 7833-1 (21A11)
March 26, 2024
Page 3
In 2022, these two companies requested additional work extending their systems to
complete their fiber optics networks on the peninsula to Peninsula Point. On
December 13, 2022, the City Council authorized increasing the contingency to
$3,500,000 (approximately 50 percent of the contract award) to cover the costs of the
additional work that included power upgrades to several micro cell towers already
installed and operational.
Although there were minimal issues during construction, the project proved to be
challenging due to the amount of work, and coordination needed between contractors,
utility companies, City staff, and other City projects along Balboa Boulevard. Some of the
issues involved water main breaks and service leaks, trench excavation, and additional
paving efforts for Balboa Boulevard.
The contracted work has now been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original bid amount: $6,969,777.79
Actual Cost of Bid Items Constructed: $6,747,132.31
Total Change Orders: $3,817,648.83
Final Contract Cost: $10,564,781.14
Seventeen change orders totaling $3,817,648.83 in increased contract costs and
approximately $222,000 in base contract savings were approved as part of the project.
The change orders addressed costs for the abovementioned work including costs for
median restoration, concrete replacement, street light improvements at Balboa Pier, bike
racks, benches, irrigation improvements, and deep -lift pavement repairs.
With the completion of the project, staff is requesting a budget amendment appropriating
$159,250.85 to cover final costs (change orders 15 through 17) related to the additional
work on the peninsula that has been paid for in advance by Verizon. With this
authorization, the final contract cost is $10,564,781.14, approximately 51.6 percent above
the original bid amount.
A summary of the project schedule is as follows:
Estimated Start of Construction per Annual Baseline Schedule September 14, 2020
Actual Start of Construction Per Notice to Proceed September 11, 2020
Extended Contract Completion Date Inclusive of Extra Work December 1, 2023
Actual Substantial Construction Completion Date October 1, 2021
The project was substantially completed to the satisfaction of the Public Works
Department by October 1, 2021, but additional work for Verizon's small cell system and
fiber optic network (UUD22 Phase 4 & 5) extended the contract completion date to
December 1, 2023. The remaining change order work requested by Verizon will not be
completed unless authorized by City Council and the contingency increased as noted
above.
4-3
Underground Utility Assessment District No. 111, Underground Utilities District No. 22
Phase 2 & 3, & Utility Undergrounding for McFadden Alleys and Court Street —
Notice of Completion for Contract No. 7833-1 (21A11)
March 26, 2024
Page 4
FISCAL IMPACT:
Upon approval of the proposed budget amendment, sufficient funding will be available for
the closeout of this contract. Funding for the additional $159,250.85 was provided by
Verizon and does not add financial burden to the resident driven undergrounding project.
A significant portion of the increased expenditures for the overall project, approximately
$2.9 million, was provided by ExteNet Systems and MCI Business (both Verizon
subsidiaries) and did not require any additional assessment district funding. The following
funds were expensed:
Account Description
AD111 Utility Construction
UUD22-1 CIP Expenditures for GL
General Fund
ENVIRONMENTAL REVIEW:
Account Number
66002-941032
13501-980000-21 A11
0108012-851010
Total:
Amount
$2,347,855.09
$8,198,960.85
$17,965.20
$10,564,781.14
On August 25, 2020, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(d) (conversion of overhead
electrical utility distribution lines where the surface is restored to the condition existing
prior to the undergrounding) of the CEQA Guidelines, California Code Regulations,
Title 1, Chapter 3, because it will not have an adverse effect on the environment.
� Eel I [el I' Eel
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
Attachment B — Budget Amendment
ATTACHMENT A
0
m
0
H
ASSESSMENT DISTRICT 111, UNDERGROUND
UTILITY DISTRICT 22 - PHASES 2 (BALBOA) & 3
LOCATION MAP
STREET
2
-1
7-
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7833-1 3/26/24
4-5
ATTACHMENT B
;cam.
City of Newport Beach
BUDGET AMENDMENT
2023-24
BA#: 24-058
Department: Public Works
ONE TIME: ❑ Yes ❑ No
Requestor: Theresa Schweitzer
Approvals
❑ CITY MANAGER'S APPROVAL ONLY
Finance Director: a4m Date 311ZI2.`F
0 COUNCIL APPROVAL REQUIRED City Clerk: Date
EXPLANATION FOR REQUEST:
Accept and recognize additional revenue and appropriate expenses as it relates to the Assessment District No. 111 and ❑ from existing budget appropriations
Underground Utilities District No. 22 Phases 2 & 3, Conctract No. 7833-1 (Project# 21A11). 0 from additional estimated revenues
0 from unappropriated fund balance
REVENUES
Fund #
Org
Object
Project
Description
Increase or (Decrease) $
135
13501
561007
21A11
CONTRIBUTIONS FUND CIP - 20A CONTRIBUTIONS
31,872.75
Subtotal
$ 31,872.75
EXPENDITURES
Fund #
Org
Object
Project
Description
Increase or (Decrease) $
135
13501
980000
21A11
CONTRIBUTIONS FUND CIP - CIP EXPENDITURES FOR GL
159,250.85
Subtotal
$ 159,250.85
FUND BALANCE
Fund #
Object
Description
Increase or (Decrease) $
135
300000
CONTRIBUTIONS FUND - FUND BALANCE CONTROL
(127,378.10)
Subtotal
$ (127,37B.10)
Fund Balance Change Required
i o