CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
March 26, 2024
Agenda Item No. 7
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Seimone Jurjis, Assistant City Manager/Community Development
Director - 949-644-3232, sjurjis@newportbeachca.gov
PREPARED BY: Benjamin M. Zdeba, AICP, Principal Planner - 949-644-3253,
bzdeba@newportbeachca.gov
TITLE: Budget Amendment No. 24-059: Allocate Additional Funds for the
Comprehensive General Plan Update (CIP Project No. 20M11)
ABSTRACT:
The City Council initiated the comprehensive review and update of the General Plan in
2019, assigning the project with the identifier 20M11 in the Capital Improvement Program
(CIP). The project has been in progress since then, with an early focus on the Housing
Element and Circulation Element, both adopted in late 2022. City staff is currently working
with Dudek, Inc. for consulting services on the comprehensive review and update for the
remainder of the General Plan, which is expected to be completed in late 2025.
For the City Council's consideration is a budget amendment to appropriate $750,000 in
increased expenditure appropriations from the General Fund unappropriated fund
balance to General Fund Account No. 01201928-980000 for the General Plan Update.
This budget amendment will ensure that there is adequate funding to offset future
expenses incurred prior to FY2024-25.
RECOMMENDATIONS:
a) Determine this action is exempt from the California Environmental Quality Act (CEQA)
pursuant to Sections 15060(c)(2) and 15060(c)(3) of the CEQA Guidelines because
this action will not result in a physical change to the environment, directly or indirectly;
and
b) Approve Budget Amendment No. 24-059, transferring $750,000 from the
unappropriated General Fund balance to the General Fund CIP and appropriating it
into Account No. 01201928-980000-20M11 for the General Plan Update (Project
No. 20M11).
DISCUSSION:
Beginning in 2019, the City Council initiated a comprehensive review and update of the
Newport Beach General Plan. The project was identified as number 20M11 in the Capital
Improvement Program (CIP) with a budget allocation of $2,238,000 between Fiscal Year
(FY) 2019-20 and FY2022-23.
7-1
Budget Amendment No. 24-059: Allocate Additional Funds
for the Comprehensive General Plan Update (CIP Project No. 20M11)
March 26, 2024
Page 2
It is notable that $452,000 of the initial budget allocation was put toward community
engagement and outreach. $1,217,461 was put toward preparation of the 6t" Cycle
Housing Element, Circulation Element, Land Use Element and Environmental Impact
Report (EIR). An amendment for an additional $395,310 is discussed further below.
State Grants Received
Given the heightened focus on the Housing Element and the initial upfront cost involved,
the City Council authorized submission of grant applications to the State Department of
Housing and Community Development (HCD) in 2019 and 2020. The City received
awards in the amounts of $310,000 from the SB 2 Planning Grants Program and $300,000
from the Local Early Action Planning (LEAP) Grants Program for a total of $610,000 to
help defray a portion of the City's costs.
CIP Allocation and Kimley-Horn Amendment
On June 13, 2023, the City Council adopted the FY2023-24 through FY2028-29 CIP,
which provides an allocation of $1,022,000 for FY2023-24. Additionally, the City Council
authorized execution of Amendment No. One to the Professional Services Agreement
(PSA) with Kimley-Horn & Associates, Inc. (Kimley-Horn) for consulting services on the
Housing, Land Use and Circulation Elements, and EIR. This Amendment increased the
total not -to -exceed contract amount by $395,310 to $1,612,771. The increase was due to
the additional cost in preparing the 6t" Cycle Housing Element, and the EIR required for
the City to implement the Housing Element, as required by State law.
Comprehensive General Plan Update with Dudek
Shortly thereafter on June 27, 2023, the City Council authorized a PSA with Dudek, Inc.
(Dudek) for consulting services for the comprehensive General Plan update in a
not -to -exceed amount of $1,478,030, with an expiration date of December 31, 2025. The
PSA was executed, and the workplan kicked off in July 2023. The compensation to Dudek
is not proposed to increase through this budget amendment.
Additional Allocation Needed
Considering Amendment No. One to Kimley-Horn's PSA and Dudek's work on different
pieces of the General Plan Update, the $1,022,000 CIP allocation is nearing exhaustion
prior to conclusion of FY2023-24.
The PSA expenditures and budget allocations described above are summarized in
Table 1 on the following page.
(the balance of this page left intentionally blank)
7-2
Budget Amendment No. 24-059: Allocate Additional Funds
for the Comprehensive General Plan Update (CIP Project No. 20M11)
March 26, 2024
Page 3
Table 1, PSA Expenditures by Consultant and CIP Budget Allocation
Kearns & West — Housing Element Outreach
PSA Total Amount $452,000
Total Amount Expended $452,000
PSAAmount Remaining (Feb. '24) $0
CIP Budget Amount Remaining (FY23-24) $0
Current CIP Budget Shortfall N/A, fully expended
Kimley-Horn & Associates — Housing, Circulation Element, Land Use Element, and E/R
PSA Total Amount $1,612,771 (with Amendment No. One)
Total Amount Expended $1,408,9230)
PSAAmount Remaining (Feb. '24) $203,848
CIP Budget Amount Remaining (FY23-24) $203,848
Current CIP Budget Shortfall N/A, fully encumbered
Dudek — Comprehensive General Plan Update of the Remaining Elements
PSA Total Amount $1,478,029
Total Amount Expended $464,645
PSAAmount Remaining (Feb. '24) $1,013,384
CIP Budget Amount Remaining (FY23-24) $130,703
Current CIP Budget Shortfall ($882,681)
(1) The City received SB 2 and LEAP Grants in the amount of $610,000 to help offset a portion of the costs
incurred for preparation of the 6"' Cycle Housing Element.
With invoices received from Dudek for work through January 2024, there remains
$130,703 in the CIP budget account to cover invoices through the end of FY2023-24.
Given a current monthly spending rate of approximately $65,000, the current CIP budget
account likely has enough funds to cover invoices through March 2024.
As demonstrated in Table 1 above, an additional $882,681 is needed to complete the
General Plan Update. Staff is requesting $750,000 through a budget amendment. The
remainder of funds needed will be addressed next year through the regular budget
process. The General Plan Update is a long-term project that spans multiple budget
cycles with an expected completion time of late 2025.
FISCAL IMPACT:
The budget amendment transfers $750,000 from General Fund unappropriated fund
balance to the General Fund CIP (Fund 012). All expenditures will be expensed to the
General Fund Account No. 01201928-980000-20M11. The appropriation utilizes a portion
of the FY2023-24 General Fund operating surplus. A General Fund operating surplus of
$7.7 million is currently projected based on the second quarter financial report.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this action is not subject to the California
Environmental Quality Act (CEQA) pursuant to Sections 15060(c)(2) (the activity will not
result in a direct or reasonably foreseeable indirect physical change in the environment)
and 15060(c)(3) (the activity is not a project as defined in Section 15378) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential for resulting in physical change to the environment, directly or indirectly.
7-3
Budget Amendment No. 24-059: Allocate Additional Funds
for the Comprehensive General Plan Update (CIP Project No. 20M11)
March 26, 2024
Page 4
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Budget Amendment No. 24-059
7-4
Attachment A
Budget Amendment No. 24-059
7-5
r �Rr
City of Newport Beach
�? BUDGET AMENDMENT
C"4 -FORK% 2023-24 BA#: 24-059
Department: Community Development
ONETIME: ❑ Yes ❑ No
Requestor: Seimone Jurjis
Approvals
❑ CITY MANAGER'S APPROVAL ONLY
Finance Director: Own ia� Date 3111124
21 COUNCIL APPROVAL REQUIRED City Clerk: Date
EXPLANATION FOR REQUEST:
To transfer anticipated savings from the General Fund unappropriated balance to the General Plan CIP Account for the ❑ from existing budget appropriations
General Plan Update multi -year project. ❑ from additional estimated revenues
❑ from unappropriated fund balance
REVENUES
Fund #
Org
Object Project
Description
Increase or (Decrease) 5
012
01299
691010
INTERFUND TRANSFERS - TRANSFER IN GENERAL FUND 750,000.00
Subtotal $ 750,000�00
EXPENDITURES
Fund #
Org
Object Project
Description
Increase or (Decrease) $
010
01099
991012
GENERAL FUND INTERFUND TRANSFR -TRANSFER OUT CIP FUN 750,000.00
012
01201928
980000 20M11
MISC & STUDIES - CIP EXPENDITURES FOR GL
750,000.00
Subtotal$ 1,500,000.00
FUND BALANCE
Fund #
Object
Description
Increase or (Decrease) $
O10
300000
GENERAL FUND - FUND BALANCE CONTROL
(750,000.00)
012
300000
GENERAL FUND CAPITAL PROJECTS
- FUND BALANCE CONTROL
SubtotalL $ (750,000.00)
Fund Balance Change Required
7-6