HomeMy WebLinkAbout09 - Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot Project (15T09) — Approval of Additional Construction Contingency Amendment to PSAQ SEW Pp�T
CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
July 23, 2024
Agenda Item No. 9
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Andy Tran, Senior Civil Engineer - 949-644-3315,
atran@newportbeachca.gov
TITLE: Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot Project
(15T09) — Approval of Additional Construction Contingency with
Reyes Construction (Contract No. 8020-6), and Approval of
Amendment No. Two to Professional Services Agreement with
Ardurra (Contract No. 8020-8) and Amendment No. Five to
Professional Services Agreement with Dokken Engineering (Contract
No. 8020-5)
ABSTRACT:
The Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot project is currently under
construction. As a result of several unforeseen field conditions, in addition to experiencing
an above normal amount of inclement weather over the past two winters, the project's
original completion date has been delayed. Additional construction contingency and
construction management and support services are also needed to address these
changed field conditions and delays.
RECOMMENDATIONS:
a) Determine this action is exempt from the California Environmental Quality Act (CEQA)
pursuant to Sections 15060(c)(2) and 15060(c)(3) of the CEQA Guidelines because
this action will not result in a physical change to the environment, directly or indirectly;
b) Approve Budget Amendment No. 25-005, transferring $805,874 from the
unappropriated FFP: Parks/Community Centers fund balance into Account
No. 56201-980000-15T09;
c) Increase the construction contract contingency by $500,000 to $1,342,000
(approximately 12.8% of the contract award amount) with Reyes Construction
(Contract No. 8020-6) to cover additional costs associated with unforeseen field
conditions;
d) Authorize payment of $54,583.54 from the CIP Storm Drain Repair Account
No. 01201926-980000-25D02 (Neighborhood Enhancement funds) to T.E. Roberts
under its existing on -call contract;
e) Approve Amendment No. Two to Professional Services Agreement with Ardurra
(Contract No. 8020-8) for construction oversight of the Superior Avenue
Pedestrian/Bicycle Bridge and Parking Lot project in the amount of $286,874 for a
total not -to -exceed amount of $1,537,020, and authorize the Mayor and City Clerk to
execute the amendment; and
9-1
Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot Project (15T09) —
Approval of Additional Construction Contingency with Reyes Construction, and Approval
of Amendment No. Two to Professional Services Agreement with Ardurra and
Amendment No. Five to Professional Services Agreement with Dokken Engineering
July 23, 2024
Page 2
f) Approve Amendment No. Five to Professional Services Agreement with Dokken
Engineering (Contract No. 8020-5) for additional design services for the Superior
Avenue Pedestrian/Bicycle Bridge and Parking Lot project in the amount of $19,000
for a total not -to -exceed amount of $2,121,499, and authorize the Mayor and City
Clerk to execute the amendment.
The Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot project is currently under
construction and is approximately 80% complete. Construction started on January 23,
2023, and the contractor was allowed 320 consecutive working days to complete the
work. This put the original completion date at May 3, 2024.
Thus far, there has been a total of 25 inclement weather -related delay days that disrupted
the project schedule. Additionally, staff has approved 34 additional working days to
complete the approved change order work. The contractor has also requested additional
working days beyond the current approved and extended contract completion date of
July 29, 2024. Staff is reviewing this request.
The City Council awarded the construction contract to Reyes Construction on
November 29, 2022. The contract amount was $10,518,759 and the approved
contingency was $842,000, which is approximately 8% of the awarded contract amount.
During the field sampling of the existing soil for the construction of the segmental wall,
the soil parameters were not as favorable as the in -situ samples that were analyzed by
the geotechnical engineer during design. As a result, the segmental wall design had to
be modified to account for the weaker than anticipated soil. A revised wall design was
required, which involved a significant amount of additional structural excavation and
backfill. Several change orders related to the segmental wall were negotiated and
approved. The additional cost for the revised segmental walls was approximately
$572,000. Staff is requesting to increase the construction contingency by $500,000 to a
total of $1,342,000 (approximately 12.8% of the awarded contract amount) with Reyes
Construction to account for the significant changes to the segmental walls due to
unforeseen poor soil conditions.
The project team also encountered unforeseen perched groundwater while trenching for
the proposed new storm drain system this spring. Since Reyes Construction does not
have the resources to handle groundwater, the contractor provided a quote for $190,000
to bring on a subcontractor to temporarily divert the groundwater so the storm drain
improvements could be completed. During these discussions, staff recognized that Reyes
Construction was unfamiliar with handling and constructing within high groundwater. Staff
met with one of the City's on -call contractors, T.E. Roberts, which is very familiar with
pipeline installation and handling groundwater. T.E. Roberts provided a quote for
$170,000 to temporarily divert the groundwater and to install the storm drain
improvements under its existing on -call contract.
9-2
Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot Project (15T09) —
Approval of Additional Construction Contingency with Reyes Construction, and Approval
of Amendment No. Two to Professional Services Agreement with Ardurra and
Amendment No. Five to Professional Services Agreement with Dokken Engineering
July 23, 2024
Page 3
Reyes Construction agreed to descope and credit the City for this work and to have
T.E. Roberts complete the storm drain improvements. T.E. Roberts' quote assumed
15 working days to complete the work. Unfortunately, there were three inclement weather
days while T.E. Roberts was completing the work. The rain worsened the groundwater
condition and made it much more difficult to complete the storm drain improvements.
T.E. Roberts was able to complete the work in 19 working days for a total cost of
$224,583.54. Payment for the original quote of $170,000 has been processed. Staff
requests City Council's authorization to pay the remaining $54,583.54 worth of work
required due to rain and added groundwater handling under the existing on -call contract
with T.E. Roberts.
City Council approved a Professional Services Agreement with Ardurra on March 22,
2022, for construction management services. Amendment No. One was approved to
extend the term of the agreement. The construction management fee of $1,250,146 is
largely tied to the anticipated construction duration, which was assumed to be
320 working days. The construction duration has been extended as described above.
Staff recommends approving Amendment No. Two to the Professional Services
Agreement with Ardurra in the amount of $286,874 for additional construction
management services. If approved, the total not -to -exceed amount would be $1,537,020.
The City approved a Professional Services Agreement and four amendments with
Dokken Engineering for preliminary design, permitting, final design, value engineering,
and construction support services for both the Superior Avenue Pedestrian/Bicycle Bridge
and Parking Lot project and the West Coast Highway and Superior Avenue Intersection
Improvement project. Additional construction design support services are needed to
address the numerous Requests for Information (RFIs) that have been submitted by
Reyes Construction. Some of the RFIs pertain to the design and can only be answered
by Dokken Engineering as the engineer of record. Staff recommends approving
Amendment No. Five to the Professional Services Agreement with Dokken Engineering
in the amount of $19,000 for additional construction support services. The total
not -to -exceed amount would be $2,121,499.
FISCAL IMPACT:
Upon approval of the proposed Budget Amendment, sufficient funding is available to
increase the construction contingency with Reyes Construction and to approve the
two amendments with Ardurra and Dokken Engineering. The additional payment
authorization for T.E. Roberts will be expended from the CIP Strom Drain Repair Account
No. 01201926-980000-25D02 (Neighborhood Enhancement funds) for storm drain
improvements.
9-3
Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot Project (15T09) —
Approval of Additional Construction Contingency with Reyes Construction, and Approval
of Amendment No. Two to Professional Services Agreement with Ardurra and
Amendment No. Five to Professional Services Agreement with Dokken Engineering
July 23, 2024
Page 4
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this action is not subject to the California
Environmental Quality Act (CEQA) pursuant to Sections 15060(c)(2) (the activity will not
result in a direct or reasonably foreseeable indirect physical change in the environment)
and 15060(c)(3) (the activity is not a project as defined in Section 15378) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential for resulting in physical change to the environment, directly or indirectly.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
Attachment B — Budget Amendment
Attachment C — Amendment No. Two with Ardurra
Attachment D — Amendment No. Five with Dokken Engineering
Rlk,
LID
SAN
\
NEWPORT
SUNSET RIDGE PARK \
CREST
ADDITIONAL
.o PUBLIC PARKING VILLA
BALBOA
Fo /
�F I
C1T� SUNSET VI —
PAR
PASSIVE
RECREATIONAL
AREA HOAG
� FsrC�gs LOWER HOSPITAL
CAMPUS
03 VILLAGE SHOPPING Y \
p CENTER > `�
rG JACK" N 1
/ O THE BOX % -...
SUPERIOR AVENUE PEDESTRIAN/BICYCLE
BRIDGE AND PARKING LOT
ATTACHMENT A - LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-8020
3/22/2022 9-5
ATTACHMENT B
F�EarPO^r
City of Newport Beach
Yy = BUDGET AMENDMENT
F� "P 2024-25 BA#: 25-005
Department: Public Works
ONETIME: 71 Yes ❑ No
Requestor: Trevor Smouse
Approvals
❑ CITY MANAGER'S APPROVAL ONLY
Finance Director: AWW •y Date
IV
COUNCIL APPROVAL REQUIRED City Clerk: Date
EXPLANATION FOR REQUEST:
To appropriate funds from the 513 FFP Fund to the 562 Parks and Community Center Fund forth e Lower Sunset View Park project ❑ from existing budget appropriations
(15T09). ❑ from additional estimated revenues
❑� from unappropriated fund balance
REVENUES
Fund a
Org
Object Project
Description
Increase or (Decrease) $
562
562
691513
PARKS & COMMUNITY CENTERS -TRANSFER IN FFP FUND
805,874.00
Subtotal $ 805,874.00
EXPENDITURES
Fund q
Org
Object Project
Description
Increase or (Decrease) $
513
51399
991562
INTERFUND TRANSFERS -TRANSFER OUT PARKS & COMM CTRS
805,874.00
562
56201
980000 15T09
PARKS & COMM CTR CIP - CIP EXPENDITURES FOR GL
805,874.00
Subtotall $ 805,874.00
FUND BALANCE
Fund #
Object
Description
Increase or (Decrease) $
513
300000
FACILITIES FINANCING
PLAN - FUND BALANCE CONTROL
(805,874.00)
562
300000
PARKS & COMMUNITY CENTERS - FUND BALANCE CONTROL
Subtotal $ (805,874.00)
No Change In Fund Balance
• o
ATTACHMENT C
AMENDMENT NO. TWO TO
PROFESSIONAL SERVICES AGREEMENT
WITH ARDURRA GROUP, INC. FOR
CONSTRUCTION MANAGEMENT/ENGINEERING SERVICES FOR THE
SUPERIOR AVENUE PEDESTRIAN/BICYCLE BRIDGE AND PARKING LOT
PROJECT AMENDMENT
THIS AMENDMENT NO. TWO TO PROFESSIONAL SERVICES AGREEMENT
("Amendment No. Two") is made and entered into as of this 23rd day of July, 2024
("Effective Date"), by and between the CITY OF NEWPORT BEACH, a California
municipal corporation and charter city ("City"), and ARDURRA GROUP, INC., a Florida
Corporation ("Consultant"), whose address is 1000 N.W. 57th Court, Suite 800, Miami,
FL 33126 with a local address of 3737 Birch Street, Suite 250, Newport Beach, CA 92660
and is made with reference to the following:
RECITALS
A. On March 22, 2022, City and Consultant entered into a Professional Services
Agreement ("Agreement") to provide various construction and engineering
management services for the construction of the Superior Avenue
Pedestrian/Bicycle Bridge and Parking Lot Project ("Project").
B. On December 7, 2023, City and Consultant entered into Amendment No. One to
the Agreement ("Amendment No. One") to extend the term of the Agreement to
March 22, 2027.
C. The parties desire to enter into this Amendment No. Two to increase the total
compensation due to a series of challenges and unforeseen issues requiring
additional services, value engineering, time impact analysis (TIA) reviews, and
efforts to resolve Project completion delays.
NOW, THEREFORE, it is mutually agreed by and between the undersigned parties
as follows:
1. COMPENSATION TO CONSULTANT
Exhibit B to the Agreement shall be supplemented to include the Schedule of
Billing Rates, attached hereto as Exhibit B and incorporated herein by reference. Exhibit
B to the Agreement, and Exhibit B to Amendment No. Two shall collectively be known as
"Exhibit B."
Section 4.1 of the Agreement is amended in its entirety and replaced with the
following: "City shall pay Consultant for the Services on a time and expense not -to -
exceed basis in accordance with the provisions of this Section and the Schedule of Billing
Rates attached hereto as Exhibit B and incorporated herein by reference. Consultant's
compensation for all Work performed in accordance with this Agreement, including all
9-7
reimbursable items and subconsultant fees, shall not exceed One Million Five Hundred
Thirty Seven Thousand Twenty Dollars and 00/100 ($1,537,020.00), without prior
written authorization from City. No billing rate changes shall be made during the term of
this Agreement without the prior written approval of City."
The total amended compensation reflects Consultant's additional compensation
for additional Services to be performed in accordance with this Amendment No. Two,
including all reimbursable items and subconsultant fees, in an amount not to exceed Two
Hundred Eighty Six Thousand Eight Hundred Seventy Four Dollars and 00/100
($286,874.00).
2. INTEGRATED CONTRACT
Except as expressly modified herein, all other provisions, terms, and covenants
set forth in the Agreement shall remain unchanged and shall be in full force and effect.
[SIGNATURES ON NEXT PAGE]
Ardurra Group, Inc. Page 2
IN WITNESS WHEREOF, the parties have caused this Amendment No. Two to be
executed on the dates written below.
APPROVED AS TO FORM:
CITY ATTORNEY'S OFFICE
Date: 7lFlZ01Y
CITY OF NEWPORT BEACH,
a California municipal corporation
Date:
By:
4-Aaron C. Harp ��r Will O'Neill
City Attorney Mayor
ATTEST: CONSULTANT: ARDURRA GROUP,
Date: INC., a Florida Corporation
Date:
By: By:
Leilani 1. Brown Lisa M. Penna, PE, F.ASCE, QSD
City Clerk Vice President
Date:
By:
Catherine Cahill
Chief Financial Officer and Treasurer
[END OF SIGNATURES]
Attachments: Exhibit B — Schedule of Billing Rates
Ardurra Group, Inc. Page 3
9-9
EXHIBIT B
SCHEDULE OF BILLING RATES
Ardurra Group, Inc. Page B-1 9_10
ESTIMATED FEE
Newport Beach Superior Avenue Pedestrian
Bicycle Bridge and Parking Lot
City of Newport Beach
June 14, 2024
Page 3 of 3
Estimated Fee
Professional Services for Construction Management! Engineering
Services
City of Newport
Beach
Superior Avenue Pedestrian 1611cycle
Bridge
and Parking Lot (RFP 8020-6)
City Project No.: 15T09;
Federal Project No. CML-5151
(031)
Start date of evaluation
4130/2024
WSWD Date of Completion
7/29/2024
Holidays Between Start and Completion
2
Net Working Days to Completion
63
Pending TIPS
TA 002
37
TA 003
17
Expected Working Days Remaining
117
Original Contract Amount
S 1.250.146.00
Invoiced to Date (through 4/3012024)
S 1,121.709A6
Current Remaining Budget (through
$ 128,436.54
413012024)
Construction
117
Working
TITLE
Est. Hours
Total
Days
Hourly
Extended Fee
, pay
Hours
Rate' 2
Principal-in-Charge/OA1QC
0,00
0
$230.00
$ -
Resident Engineer/ Construction
3,00
307
$230.00
$ 70,610.00
Manager
Resident Engineer! Construction
2.00
A4
$230.00
$ 10,120.00
Manager (Last Month}
Assistant Resident Engineer/
inspector' 4.1
8.00
848
$165,00
$ 139,920.00
Assistant Resident Engineers
400
88
S165.00
S 14,520.00
Inspector3,4,5 (Last Month)
Project Controls Engineer
0.25
29
$145.00
$ 4,241,25
Document Controls
4.00
468
$120.00
S 56,160.00
Labor Compliance Analyst
1
117
$120.00
S 14,040,00
Geotechnical Services - Soils and
$ 68,105,25
lVaterials Testing and Inspection,
Working
TITLE
Est. Hours
Total
Days
Hourly
Extended Fee
1 Day
Hours
Rate+
Principa-in-Charge I QA 1 QC
0.00
0
$230.00
$ -
Resident Engineer 1 Construction
4.00
60
$230.00
$ 13,800.00
Manager
Assistant Resident Engineer!
Inspector' d s
4.00
60
$165.00
$ 9.900.00
Labor Compliance
2.00
30
S145.00
$ 4,35000
Project Controls Engineer
0.25
4
$145.00
S 543.75
Document Controls
4.00
60
S120.00
S 7.200.00
Labor Compliance Analyst
r - ■
1
15
$120.00
1 $ 1.800.00
rrEM
Amount
I WAI C34nFdWQ rUU w �IVti@ VUc r■VJUGL a YIO,J IVUa
Remaining Budget Applied
Total Requested Amendment Mount $ 286,874.00
1960 East Grand Avenue I El Segundo, CA 90245 1 310-359. t 203 1 www.ardurro.corn
9-11
ATTACHMENT D
AMENDMENT NO. FIVE TO
PROFESSIONAL SERVICES AGREEMENT
WITH DOKKEN ENGINEERING FOR
SUPERIOR AVENUE OVERCROSSING AND PARKING LOT PROJECT FINAL
DESIGN AND ENGINEERING SERVICES AMENDMENT
THIS AMENDMENT NO. FIVE TO PROFESSIONAL SERVICES AGREEMENT
("Amendment No. Five") is made and entered into as of this 23rd day of July, 2024
("Effective Date"), by and between the CITY OF NEWPORT BEACH, a California
municipal corporation and charter city ("City"), and DOKKEN ENGINEERING, a California
corporation ("Consultant"), whose address is 110 Blue Ravine Road, Suite 200, Folsom,
CA 95630, and is made with reference to the following:
RECITALS
A. On November 19, 2019, City and Consultant entered into a Professional Services
Agreement ("Agreement") to provide final design and engineering services for the
Superior Avenue overcrossing and parking lot ("Project").
B. On January 14, 2020, the City adopted Resolution 2020-04 authorizing and
approving the submittal of a funding application ("Application") for an intersection
capacity enhancement project to the Orange County Transportation Authority
("OCTA") for funding under the Comprehensive Transportation Funding Program.
C. On May 11, 2020, OCTA approved the City's Application, in which the City received
funds to conduct environmental review and design services for the West Coast
Highway Widening and Pedestrian Bridge Project.
D. On August 25, 2020, City and Consultant entered into Amendment No. One to the
Agreement ("Amendment No. One") to reflect additional Services to include the
West Coast Highway Widening and Pedestrian Bridge Project (hereinafter
collectively referred to as the "Project") not included in the Agreement, and to
increase the total compensation.
E. On March 22, 2022, City and Consultant entered into Amendment No. Two to the
Agreement ("Amendment No. Two") to reflect additional Services to include the
West Coast Highway Widening and Pedestrian Bridge Project (hereinafter
collectively referred to as the "Project") not included in the Agreement, and to
increase the total compensation.
F. On November 29, 2022, City and Consultant entered into Amendment No. Three
to the Agreement ("Amendment No. Three") to reflect additional Services related
to project updates not included in the Agreement, as amended, to increase the
total compensation, update Consultant's Project Manager, amend the Ownership
of Documents section, and amend the insurance requirements.
9-12
G. On December 21, 2023, City and Consultant entered into Amendment No. Four to
the Agreement ("Amendment No. Four") to reflect additional Services not included
in the Agreement, as amended, to extend the term of the Agreement to November
19, 2024, to increase the total compensation, and to update Consultant's Project
Manager.
H. The parties desire to enter into this Amendment No. Five to reflect additional
Services not included in the Agreement, as amended, to extend the term of the
Agreement to December 31, 2025, and to increase the total compensation.
NOW, THEREFORE, it is mutually agreed by and between the undersigned parties
as follows:
1. TERM
Section 1 of the Agreement is amended in its entirety and replaced with the
following: "The term of this Agreement shall commence on the Effective Date, and shall
terminate on December 31, 2025, unless terminated earlier as set forth herein."
2. SERVICES TO BE PERFORMED
Exhibit A to the Agreement shall be supplemented to include the Scope of
Services, attached hereto as Exhibit A and incorporated herein by reference ("Services"
or "Work"). Exhibit A to the Agreement, Exhibit A to Amendment No. One, Exhibit A to
Amendment Two, Exhibit A to Amendment Three, Exhibit A to Amendment Four and
Exhibit A to this Amendment No. Five shall collectively be known as "Exhibit A." The City
may elect to delete certain Services within the Scope of Services at its sole discretion.
3. COMPENSATION TO CONSULTANT
Exhibit B to the Agreement shall be supplemented to include the Schedule of
Billing Rates, attached hereto as Exhibit B and incorporated herein by reference. Exhibit
B to the Agreement, Exhibit B to Amendment No. One, Exhibit B to Amendment No. Two,
Exhibit B to Amendment No. Three, Exhibit B to Amendment No. Four, and Exhibit B to
this Amendment No. Five shall collectively be known as "Exhibit B."
Section 4.1 of the Agreement is amended in its entirety and replaced with the
following: "City shall pay Consultant for the Services on a time and expense not -to -
exceed basis in accordance with the provisions of this Section and the Schedule of Billing
Rates attached hereto as Exhibit B and incorporated herein by reference. Consultant's
compensation for all Work performed in accordance with this Agreement, including all
reimbursable items and subconsultant fees, shall not exceed Two Million One Hundred
Twenty One Thousand Four Hundred Ninety Nine Dollars and 001100
($2,121,499.00), without prior written authorization from City. No billing rate changes
shall be made during the term of this Agreement without the prior written approval of City."
Dokken Engineering Page 2
9-13
The total amended compensation reflects Consultant's additional compensation
for additional Services to be performed in accordance with this Amendment No. Five,
including all reimbursable items and subconsultant fees, in an amount not to exceed
Nineteen Thousand Dollars and 00/100 ($19,000.00).
4. INTEGRATED CONTRACT
Except as expressly modified herein, all other provisions, terms, and covenants
set forth in the Agreement shall remain unchanged and shall be in full force and effect.
[SIGNATURES ON NEXT PAGE]
Dokken Engineering Page 3
9-14
IN WITNESS WHEREOF, the parties have caused this Amendment No. Five to be
executed on the dates written below.
APPROVED AS TO FORM:
CITY ATTORNEYS OFFICE
Date: `T/;- y
CITY OF NEWPORT BEACH,
a California municipal corporation
Date:
Bv:
✓Aaron C. Harp,'hr Will O'Neill
City Attorney , 4z Mayor
ATTEST: CONSULTANT: Dokken Engineering, a
Date: California corporation
Date:
By: By:
Lellani I. Brown John A. Klemunes Jr.
City Clerk President
Date:
By:
Cathy Chan
Secretary
[END OF SIGNATURES]
Attachments: Exhibit A — Scope of Services
Exhibit B — Schedule of Billing Rates
Dokken Engineering Page 4
9-15
EXHIBIT A
SCOPE OF SERVICES
Dokken Engineering Page A-1 9-16
June 21, 2024
Andy Tran, P.E.
City of Newport Beach Project Manager.
100 Civic Center Drive
Newport Beach, CA 92660
RE: City of Newport Beach — SUPERIOR AVENUE PEDESTRIANBICYCLE BRIDGE
AND PARKING LOT PROJECT
Mr. Tran:
Dokken Engineering (Dokken) was responsible for preparing the project's PS&E package. The project started
construction on 2023 with Dokken providing design support during construction services as stated on the
original scope and fee for this project. Dokken is pleased to submit Amendment 5 scope and fee to the City of
Newport Beach to provide additional design support during construction services for the Superior Avenue
Pedestrian/Bicycle Bridge and Parking Lot Project.
Task 19 Additional Design Support During Construction
Dokken shall continue providing construction support services including responses to RFIs as requested by
the City, review Contractor submittals, and as needed plan revisions,
Task 19 scope of work will be completed as described on this letter for a not -to -exceed additional fee of
$19, 000 ($1 S, 000 Dokken Engineering + S4,000 ADL Planning Associates, Inc).
If you have any questions or wish to discuss this scope and fee, do not hesitate to give me a call at (916) 858-
0643, or contact me by email at JKlemunes@dokkenengineering.com
Sincerely,
DOKKEN ENGINEERING
#Z� ldl;xt� X
John Klemunes, PE
Project Manager
1450 Frazee Road, Suite 100, San Diego, CA 92108 a Tele: 858 514-8377 ■ Fax: 858 5I4-8608 1 www.dokkenengincering.com
9-17
EXHIBIT B
SCHEDULE OF BILLING RATES
Dokken Engineering Page B-1 9_18
Task 19 scope of work will be completed as described on this letter for a not -to -exceed additional
fee of $19,000 ($15,000 Dokken Engineering + $4,000 ADL Planning Associates, Inc.).
9-19