On July 28, 2022, the Zoning Administrator held a noticed public hearing on the required
annual review of the Development Agreement between the City of Newport Beach and
the Irvine Company for North Newport Center. The Zoning Administrator found that the
Irvine Company was in good faith compliance with the terms of the North Newport
Center Development Agreement. The approved minutes of the July 28, 2022 meeting
are available online at the following link:
http://newportbeachca.gov/ZoningAdministrator.
Given this determination, the Development Agreement remains in effect and the North
Newport Center Development Agreement is not presently in default.
Should you have any questions regarding the 2021 Annual Review of the North Newport
Center Development Agreement or this letter, please contact me at (949) 644-3312.
Sincerely,
Joselyn Perez, Associate Planner
January 2022
North Newport Center
Zoning Implementation and Public Benefit Agreement
Annual Report
Year 2021 (January 2021-December 2021)
Prepared for:
City of Newport Beach
Planning Division
Contact: Jim Campbell
(949) 644-3210
Submitted by:
Irvine Company
550 Newport Center Drive
Newport Beach, CA 92660
Contact: Jeff Davis
(949) 720-2409
Prepared by:
CAA Planning, Inc.
30900 Rancho Viejo Road, Suite 285
San Juan Capistrano, CA 92675
Contact: Shawna Schaffner
(949) 581-2888
Annual Report – 2021(January 2022) iii
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Contents
Introduction ............................................................................................................................................... 1
Figure 1 – Sub-Areas in North Newport Center Planned Community ............................................. 1
Summary Table – North Newport Center as of December 31, 2021 ............................................... 2
Development Summary ............................................................................................................................. 2
Fashion Island .................................................................................................................................. 5
Block 100 .......................................................................................................................................... 5
Block 400 .......................................................................................................................................... 5
Block 500 .......................................................................................................................................... 5
Block 600 .......................................................................................................................................... 5
Block 800 .......................................................................................................................................... 5
San Joaquin Plaza ............................................................................................................................. 6
Public Benefits ........................................................................................................................................... 7
Public Benefits Table ........................................................................................................................ 7
Ongoing Obligations and Public Benefits ................................................................................................ 16
City Concurrence ..................................................................................................................................... 18
Annual Report Distribution ...................................................................................................................... 18
4.4 Circulation Enhancements to Public Right of Way – Completed 2013 .............................................. 19
4.9 B. Fashion Island Water Quality Enhancements – Fashion Island Parking Areas .............................. 20
Fashion Island Non-Development Water Quality Treatment – Completed 2014 ......................... 20
Compliance to Date, Section 4.9, Paragraph B – Development Agreement ................................. 20
Annual Report – 2021(January 2022) 1
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Introduction
The purpose of the 2021 Annual Report (AR) for North Newport Center is to provide an accurate record of the
development that has occurred within North Newport Center during 2021. The North Newport Center Planned
Community Development Plan (NNCPC) as approved in 2007 included the following sub-areas: Fashion Island,
Block 500, Block 600 and San Joaquin Plaza. The NNCPC was subsequently amended in November 2009 to include
portions of Blocks 100, 400, 800 and an open space parcel from the Newport Village Planned Community. The
NNCPC was amended again in 2011 to expand Block 800 to include the Pacific Mutual Financial Center.
Subsequently in 2012, the NNCPC was amended to increase the allowable residential development intensity by
a total of 94 units and allocating the 94 units plus the 430 residential units already allocated to the MU-H3
portions of the NNCPC solely to San Joaquin Plaza. In connection with the amendment to the NNCPC, an amend-
ment to the Zoning Implementation and Public Benefit Agreement DA2007-002 (Development Agreement) was
approved. The Development Agreement amendment included the incorporation of portions of Blocks 100, 400,
the open space parcel in Newport Village, Block 800 in its entirety, as well as the additional 94 residential units.
In 2015, the NNCPC was amended for a fourth time to allow for a transfer of development intensity from outside
the NNCPC, to include a portion of Block 500, and to update various regulations. This AR contains several tables
that show development within North Newport Center as a whole and development by sub-area. The tables
provide a comprehensive review of the development within North Newport Center in terms of existing
development, maximum development (allowed by the General Plan) and development that has occurred during
2021. The tables break down each sub-area of North Newport Center individually and track the area developed
by land use, as applicable. A map that depicts the sub-areas within the NNCPC covered by this AR is shown as
Figure 1.
Figure 1 – Sub-Areas in North Newport Center Planned Community
Annual Report – 2021(January 2022) 2
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Summary Table – North Newport Center as of December 31, 2021
Sub-Area Entitlement Existing Development
Development
during 2021 Remaining Entitlement
Fashion Island
1,523,416 1,470,097 – 53,319
680 theater seats 450 theater seats – 230 theater seats
or 3,720 s.f. 1
Block 100 121,114 121,114 – 0
Block 400 91,727 88,173 – 3,554
Block 500 623,525 622,622 – 903
Block 600 1,605,899 2 1,310,899 – 0
295 hotel rooms 295 hotel rooms – 0
Block 800 286,166
245 residential units
286,166
245 residential units
– 0
San Joaquin Plaza 95,550 95,550 – 0
524 residential units 524 residential units – 0
All numbers in this table are shown in square feet (s.f.) unless otherwise indicated.
1 The remaining entitlement is 230 seats, which has a gross floor area equivalent of 3,720 s.f. (16.1765 s.f./seat x 230 seats).
2 The General Plan entitlement figure includes allocations for hotel square footage, which is not represented in the Existing Development or Remaining Entitlement columns.
Development Summary
Annual monitoring of development is required by Development Agreement 2007-002 between the City of
Newport Beach and Irvine Company as part of the North Newport Center Project which is in effect until 2032.
Below is a list of permits that were issued within North Newport Center between January and December 2021.
Not included in the list are accessory permits such as those for signs, cell sites, ADA upgrades, mechanical
equipment or elevator repairs, or repairs and upgrades within the Villas at Fashion Island and The Colony
residential developments. Note that the City bases the building permit gross floor area (g.f.a.) calculations on
the Building Code definition and not the entitlement g.f.a. on the definition contained in the NNCPC,
4th Amendment, which is slightly different from the Building Code and excludes support uses (Section II.3). There
were no permits issued or finalized in 2021 that resulted in changes to the gross floor area entitlement.
Annual Report – 2021(January 2022) 3
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Date Sub-Area Summary of Action
Feb 2019
Feb 2020
Feb 2021
Mar 2021
Mar 2021
Apr 2021
Apr 2021
Apr 2021
Jun 2021
Jul 2021
Jul 2021
Aug 2021
Aug 2021
Aug 2021
Sept 2021
Sept 2021
Sept 2021
Nov 2021
Nov 2021
Nov 2021
Nov 2021
Fashion Island
(Final)
(Final)
(Final)
(Issued)
(Issued)
(Final)
(Final)
(Final)
(Issued)
(Final)
(Issued)
(Final)
(Final)
(Issued)
(Issued)
(Final)
(Final)
(Issued)
(Final)
(Issued)
(Issued)
811 Newport Center Drive (X2019-0035)
957 Newport Center Drive (X2019-4026)
1065 Newport Center Drive (X2020-0413)
1083 Newport Center Drive (X2020-2759)
1083 Newport Center Drive (X2020-2760)
579 Newport Center Drive (X2021-0086)
579 Newport Center Drive (X2021-0087)
579 Newport Center Drive (X2021-0088)
1071 Newport Center Drive (X2021-0913)
1083 Newport Center Drive (X2021-1082)
363 Newport Center Drive (X2021-0558)
1083 Newport Center Drive (X2021-1082)
579 Newport Center Drive (X2021-1492)
453 Newport Center Drive (X2021-1995)
1083 Newport Center Drive (X2021-1689)
811 Newport Center Drive (X2021-1880)
1117 Newport Center Drive (X2021-2285)
415 Newport Center Drive (X2021-0595)
811 Newport Center Drive (X2021-2261)
453 Newport Center Drive (X2021-2786)
259 Newport Center Drive (X2021-3085)
Jan 2020
Oct 2021
Nov 2021
Nov 2021
Block 400
(Issued)
(Issued)
(Issued)
(Issued)
450 Newport Center Drive (X2019-2818)
450 Newport Center Drive (X2021-2001)
450 Newport Center Drive (X2021-2843)
450 Newport Center Drive (X2021-2976)
Annual Report – 2021(January 2022) 4
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Date Sub-Area Summary of Action
Mar 2021
May 2021
Apr 2021
Sept 2021
Oct 2021
Oct 2021
Block 500
(Final)
(Final)
(Final)
(Final)
(Issued)
(Issued)
520 Newport Center Drive (X2020-1998)
2071 San Joaquin Hills Road (X2020-2556)
2071 San Joaquin Hills Road (X2020-2542)
520 Newport Center Drive (X2021-2378)
500 Newport Center Drive (X2021-2522)
500 Newport Center Drive (X2021-2523)
Jan 2020
Jan 2020
Apr 2020
Apr 2020
Jan 2021
Jun 2020
Jun 2020
Jun 2020
Jul 2020
Jun 2021
Jun 2021
Jan 2021
Sept 2020
Oct 2020
Dec 2020
Dec 2020
Feb 2021
Feb 2021
Jun 2021
Jul 2021
Jul 2021
Jul 2021
Aug 2021
Sept 2021
Sept 2021
Oct 2021
Oct 2021
Block 600
(Issued)
(Issued)
(Issued)
(Issued)
(Final)
(Issued)
(Issued)
(Issued)
(Issued)
(Final)
(Final)
(Final)
(Issued)
(Issued)
(Final)
(Final)
(Final)
(Final)
(Issued)
(Issued)
(Issued)
(Issued)
(Final)
(Final)
(Final)
(Issued)
(Issued)
610 Newport Center Drive (X2019-3833)
660 Newport Center Drive (X2019-4140)
610 Newport Center Drive (X2020-0675)
660 Newport Center Drive (X2019-3900)
620 Newport Center Drive (X2020-1070)
610 Newport Center Drive (X2020-0743)
610 Newport Center Drive (X2020-0382)
610 Newport Center Drive (X2020-0561)
660 Newport Center Drive (X2019-4107)
660 Newport Center Drive (X2020-1519)
660 Newport Center Drive (X2020-1520)
610 Newport Center Drive (X2020-1838)
610 Newport Center Drive (X2020-1997)
650 Newport Center Drive (X2020-1333)
650 Newport Center Drive (X2020-1334)
650 Newport Center Drive (X2020-1335)
620 Newport Center Drive (X2020-1946)
620 Newport Center Drive (X2020-0456)
660 Newport Center Drive (X2021-0914)
610 Newport Center Drive (X2020-0561)
610 Newport Center Drive (X2020-0743)
660 Newport Center Drive (X2019-3833)
660 Newport Center Drive (X2021-2000)
610 Newport Center Drive (X2021-2499)
620 Newport Center Drive (X2021-1950)
660 Newport Center Drive (X2021-2273)
660 Newport Center Drive (X2021-2274)
Jul 2021
Aug 2021
Oct 2021
Nov 2021
Block 800
(Issued)
(Issued)
(Issued)
(Issued)
840 Newport Center Drive X2021-1591)
880 Newport Center Drive X2021-1537)
840 Newport Center Drive X2021-2474)
840 Newport Center Drive X2021-2977)
Feb 2020
Jul 2021
Aug 2021
Aug 2021
San Joaquin Plaza
(Final)
(Issued)
(Issued)
(Issued)
888 San Clemente Drive (X2019-3920)
888 San Clemente Drive (X2021-0583)
888 San Clemente Drive (X2021-1590)
888 San Clemente Drive (X2021-1948)
The tables below show development within North Newport Center by sub-area. All numbers are shown in gross
square feet unless otherwise indicated. The tables are intended to track development annually and provide a
comprehensive listing of development by land use. The “Demolished” column reflects the final square footage
demolished, not the square footage stated in a demolition permit. Similarly, the “Built” column reflects the
square footage provided in a Certificate of Use and Occupancy and not the square footage stated in a building
permit. There were no permits issued or finalized in 2021 that resulted in changes to the gross floor area
entitlement.
Annual Report – 2021(January 2022) 5
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Fashion Island
Entitlement
January 2021
Existing
Development
January 2021
Recovered Demolished
Permitted
(Demo/New) Built
Tracking
Number
Existing
Development
December 2021
Entitlement
December 2021
Land Use
Regional Commercial 1,523,416 1,519,223 49,126 1,470,097 1,523,416
Theater Seats 680 450 450 680
Block 100
Entitlement
January 2021
Existing
Development
January 2021
Transferred/
Converted Demolished
Permitted
(Demo/New) Built
Tracking
Number
Existing
Development
December 2021
Entitlement
December
2021
Land Use
Office/Commercial 121,114 121,114 121,114 121,114
Block 400
Entitlement
January 2021
Existing
Development
January 2021
Recovered Demolished
Permitted
(Demo/New) Built
Tracking
Number
Existing
Development
December 2021
Entitlement
December 2021
Land Use
Office/Commercial 91,727 91,727 3,554 88,173 91,727
Block 500
Entitlement
January
2021
Existing
Development
January 2021
Transferred/
Converted Demolished
Permitted
(Demo/New) Built
Tracking
Number
Existing
Development
December 2021
Entitlement
December 2021
Land Use
Mixed Use Horizontal
3 (MU-H3) 623,525 622,622 622,622 623,525
Residential Units 0 0 0 0
Block 600
Entitlement
January 2021
Existing
Development
January 2021
Transferred/
Recovered Demolished
Permitted
(Demo/New)
Built/
C of O
Tracking
Number
Existing
Development
December 2021
Entitlement
December 2021
Land Use
Mixed Use Horizontal
3 (MU-H3) 1,310,8993 1,310,899 1,310,899 1,310,899*
Residential Units 0 0 0 0
Hotel Rooms 295 295 295 295
3 Reflects only Office Entitlement.
Block 800
Entitlement
January 2021
Existing
Development
January 2021
Transferred
/Converted Demolished
Permitted
(Demo/New) Built
Tracking
Number
Existing
Development
December 2021
Entitlement
December
2021
Land Use
Office/Commercial 286,166 286,166 286,166 286,166
Residential Units 245 245 245 245
Annual Report – 2021(January 2022) 6
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
San Joaquin Plaza
Entitlement
January
2021
Existing
Development
January 2021
Transferred/
Converted Demolished
Permitted
(Demo/New) Built
Tracking
Number
Existing
Development
December 2021
Entitlement
December 2021
Land Use
Mixed Use Horizontal
3 (MU-H3) 95,550 95,550 95,550 95,550
Residential Units 524 524 524 524
Annual Report – 2021 (January 2022) 7
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Public Benefits
The Public Benefits Table below lists all of the public benefits resulting from Development Agreement No. DA2007-002 entitled The Zoning Implementation
and Public Benefit Agreement (Agreement) between the City of Newport Beach and Irvine Company Concerning North Newport Center and the Amendment
to the Agreement approved in August 2012 (herein referred to as the Development Agreement). Public benefits are listed in Section 4 of the development
agreement. Items that have been completed in previous reporting years are shown as Year Complete. Items completed in the current year are shaded.
Traffic fair-share fees and in-lieu park fees are the sole remaining Development Agreement obligations.
Public Benefits Table
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
In-Lieu Park Fees for Renovation of Oasis Senior Center and for Park Uses
Section 4.1 Paragraphs 1-2 Regardless of whether a subdivision map is approved for any or all of the residential units, and prior to and as a condition to City’s issuance of the First Residential Building Permit (but in no event earlier than the Effective Date)
Landowner shall pay to City the greater of (i) the sum of $3,733,333.33 (which is 1/3 of the total Park Fees to be paid to City under this Agreement) (the “Initial Park Fee”) or (ii) the applicable Per Unit Park Fees (if the First Residential Building Permit includes more than one hundred forty-three (143) residential units).
Landowner’s payment of the Initial Park Fee shall entitle Landowner to a credit against payment of the Per Unit Park Fees for the first one hundred forty-three (143) residential units to be developed on the Property.
Total payment as of December 31, 2014: $3,733,333.33
Responsible party: Irvine Company
Completed Date: November 3, 2014
Section 4.1 Paragraph 2 Prior to and as a condition to City’s issuance of a building permit for development of the one hundred forty-fourth (144th) residential unit on any portion of the Property located in Newport Center Block 500, Newport Center Block 600, or San Joaquin Plaza
Landowner shall pay to City the sum of $17,364.11 (the difference between the Initial Park Fee and the total Per Unit Park Fees for 144 residential units)
Total payment as of December 31, 2014: $17,364.11
Responsible party: Irvine Company
Completed Date: November 3, 2014
Annual Report – 2021 (January 2022) 8
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
In-Lieu Park Fees for Renovation of Oasis Senior Center and for Park Uses
Section 4.1 Paragraph 2 Prior to and as a condition to City’s issuance of each subsequent building permit for residential development within that portion of the Property
Landowner shall pay to City the sum of $26,046.51 per unit (“Per Unit Park Fees”)
* Less $5,600,000.00 paid on 3/10/09 per Section 4.1, Paragraph 4 (See Page 6 of Annual Report)
Number of units as of December 31, 2014: 286
Per unit: $26,046.51 *
Total payment: $1,849,302.56
Responsible party: Irvine Company
Completed Date: November 3, 2014
In-Lieu Park Fees for Renovation of Oasis Senior Center and for Park Uses
Section 4.1 Paragraph 3 If Landowner sells any residential unit developed within the Property to a third-party purchaser in other than a bulk sale of all of the units in a single residential building
Landowner shall pay to City at the time of such sale of an individual residential unit the then-applicable park fee for such unit as may be in effect at that time within the City of Newport Beach, less a credit for the amount of the Per Unit Park Fee paid prior to that time.
Please see Section 4.1, paragraph 3 for additional information regarding Landowner’s obligation to pay fees and memorandums to be recorded against the title of each unit.
Number of units sold as of December 31, 2021: (units) 0
Park fee per unit: $
Total payment: $ 0
Responsible party: Irvine Company
Completed
Annual Report – 2021 (January 2022) 9
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
In-Lieu Park Fees for Renovation of Oasis Senior Center and for Park Uses
Section 4.1 Paragraph 4 If, on the date that City awards a contract for renovation of the Oasis Senior Center, the total sum of both the Initial Park Fee and the Per Unit Park Fees paid by Landowner to City to date is less than the sum of $5,600,000
Within five (5) days after City’s award of the contract, Landowner shall pay to City the difference (“Park Fee Advancement”). Landowner’s payment of the Park Fee Advancement shall entitle Landowner to a credit against the Initial Park Fee (if not paid by the time the Park Fee Advancement is paid) and against the next Per Unit Park Fees that otherwise would be due and payable to City until the entire credit is exhausted. After such credit is exhausted, prior to and as a condition to City’s issuance of each subsequent building permit for residential development of any portion of the Property located in Newport Center Block 500, Newport Center Block 600, or San Joaquin Plaza, Landowner shall continue to pay the Per Unit Park Fees as residential building permits are issued.
Date that City awards a contract for renovation of the Oasis Senior Center 3/10/2009
Check below if answer is “yes.”
The total sum of both the Initial Park Fee and the Per Unit Park Fees paid by Landowner to City is less than the sum of $5,600,000 (as of date above)
If box above is checked, then Landowner shall pay to City “Park Fee Advancement” in the amount of: $5,600,000
No initial park fees paid. Lump sum payment to City: $5,600,000
Responsible party: Irvine Company
Completed Date: 3/10/ 2009
In-Lieu Park Fees for Renovation of Oasis Senior Center and for Park Uses
Section 4.1 Paragraph 5 Not specified City shall earmark $5,600,000 of the Park Fees to be paid by Landowner (one-half of the total Park Fees) as a matching challenge grant to apply toward contributions to the renovation of the Oasis Senior Center.
Responsible party: City of Newport Beach
Completed date: Early 2009 (prior to construction)
In-Lieu Park Fees for Renovation of Oasis Senior Center and for Park Uses
Section 4.1 Paragraph 5 Not Specified City shall apply any Park Fees not spent by City on the renovation of the Oasis Senior Center to any park use as determined by City. Landowner acknowledges that the actual amount of funds raised through the matching challenge may be less than $5,600,000 and that the amount raised shall not affect the amount of Park Fees payable by Landowner to City.
Responsible party: City of Newport Beach
Completed date: Early 2009 (prior to construction)
Public Benefit Fee Section 4.2 Paragraph 1 Not specified Landowner shall pay to City the sum of $27,090,000 as set forth in Section 4.2 (“Public Benefit Fee”), of the Development Agreement.
Payment in the sum of $27,090,000 paid in full as of November 3, 2014
Responsible party: Irvine Company
Completed (7/26/11 and 11/3/14 as indicated below)
Annual Report – 2021 (January 2022) 10
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Section 4.2 Paragraph 1 Prior to and as a condition to the issuance of the First Building Permit – 650 Newport Center Drive
Landowner shall pay to City the sum of $13,545,000, which is one-half of the Public Benefit Fee (“Initial Public Benefit Fee”).
Payment: as of July 26, 2011 $13,545,000
Responsible party: Irvine Company
Completed
Section 4.2 Paragraph 1 Upon the issuance of building permits for the 430 residential units authorized for development within the Property.
The balance of the Public Benefit Fee shall be paid to City. The amount payable by Landowner to City for each such residential unit shall be the sum of $31,500.
Building permits have been issued for 430 residential units as of November 3, 2014
Total payment (balance of the Public Benefit Fee): $13,545,000
This equates to $31,500 per unit for 430 units.
Total payment as of November 3, 2014
Responsible party: Irvine Company
Completed
Fair Share Traffic Fees Section 4.3 Paragraph 1 The Property is subject to City’s Fair Share Traffic Contribution Ordinance, which requires the payment of certain fair share traffic fees for development (“Fair Share Traffic Fees”).
The City is in the process of considering updates and amendments to its Fair Share Traffic Contribution Ordinance and its Fair Share Traffic Fees and that as a result of such updates and amendments the Fair Share Traffic Fee charged by City may be increased (the “Initial Fee Increase”).
Notwithstanding any other provision set forth in the Development Agreement to the contrary, Landowner agrees that Landowner and the Property shall be subject to the modified Fair Share Traffic Contribution Ordinance including the increased fees payable pursuant to the Initial Fee Increase. This applies to square footage that was newly entitled under this agreement.
Please see Section 4.3 of the Development Agreement for additional detailed information pertaining to fees.
Fair Share Traffic Fees paid for 2021: $ None Required
Responsible party: Irvine Company
Annual Report – 2021 (January 2022) 11
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Circulation Enhancements to Public Right of Way
Section 4.4 Paragraph 1 “Circulation Enhancement Contribution” to reimburse City for City’s expenses incurred for the design and construction of one or more of the circulation improvements listed in Section 4.4 of the Development Agreement, as determined by the City’s Director of Public Works, should City choose to approve the circulation enhancements after its environmental review and approval process and in compliance with CEQA. Please refer to Section 4.4, paragraph 1 of the Development Agreement for the list of circulation enhancements.
Landowner shall contribute to City the sum of Two Million Five Hundred Thousand Dollars ($2,500,000.00) (“Circulation Enhancement Contribution”).
Check below if answer is “yes.” The City choses to approve, design and construct one or more of the circulation enhancements listed in Section 4.4 of the Development Agreement Date: See note below Note: See page 19 for additional information. If box above is checked, then Landowner shall contribute up to $2,500,000.00 based on actual costs requested by the City and the amount spent by Irvine Company on those projects the City agreed could be built by Irvine Company. Responsible party: Irvine Company
Completed Date: 12/31/13
Circulation Enhancements to Public Right of Way
Section 4.4 Paragraph 2 Landowner shall pay the Circulation Enhancement Contribution to City from time to time after the Effective Date, within thirty (30) days after receipt of written request for reimbursement from City, with any balance to be paid to City on the date that is sixty (60) months after the Effective Date (the Effective Date is January 18, 2008) regardless of whether City has incurred the cost for the foregoing improvements. Alternatively, Landowner and City may mutually agree upon arrangements for Landowner to use the Circulation Enhancement Contribution to construct the foregoing improvements subject to City’s approval.
Landowner shall pay the Circulation Enhancement Contribution to City from time to time after the Effective Date and Landowner will pay any balance to the City up to a maximum contribution of $2,500,000.00 less the cost for any improvements constructed by Landowner. Contributions shall be paid by Landowner upon receipt of invoices from the City.
Indicate payment(s) below (if applicable): Amount paid by Landowner to City for Circulation Enhancement Contribution as of December 31, 2013 $1,905,803 Date that is 60 months after the Effective Date: January 18, 2013 Amount of balance paid by Landowner to City as of ___________ (date) Responsible party: Irvine Company
Completed
or
Check this box if Landowner and City mutually agree for Landowner to use contribution to construct improvements.
Date: ________________ Amount used to construct improvements as of December 31, 2013: $676,222 Responsible party: Irvine Company
Completed
Annual Report – 2021 (January 2022) 12
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Dedication of Public
Rights of Way
Section 4.5
Paragraph 1
At such time as City provides legal descriptions
for the public rights of way, which descriptions
shall be consistent with the design of the
circulation improvements for said public right of
way.
Landowner shall provide an offer of dedication to City for
the additional public rights of way necessary for
circulation improvements on the north side of San Miguel
Drive between MacArthur Boulevard and Avocado
Avenue and on Avocado Avenue between San Nicolas
Drive and San Miguel Drive.
Please see Section 4.5 of the Development Agreement
for additional information.
Responsible party: Irvine Company
Completed
No longer applicable due to dedication of Avocado parcel on October 17, 2008, as described in Section 4.6 Paragraph 1 below. Avocado parcel dedication documented in 2008 Annual Report.
Dedication of Public Rights of Way Section 4.5 Paragraph 1 At such time as City provides legal descriptions for the public rights of way, which descriptions shall be consistent with the design of the circulation improvements for said public right of way.
Landowner shall convey the public right of way to City (through the recordation of an offer of dedication without any restrictions or qualifications) free and clear of all recorded and unrecorded monetary liens, any delinquent property taxes or assessments, and all tenancies, lessees, occupants, licensees, and all possessory rights of any kind or nature.
In addition, upon the conveyance, there shall not be any violation of any law, rule, or regulation affecting the public right of way or its use, including any environmental law or regulation, and Landowner shall be responsible for causing said condition to be satisfied.
Check this box if the Landowner has recorded an offer of dedication to the City without any restrictions or qualifications.
Responsible party: Irvine Company
Completed
No longer applicable due to dedication of Avocado parcel on October 17, 2008, as described in Section 4.6 Paragraph 1 below. Avocado parcel dedication documented in 2008 Annual Report.
Open Space Dedication Section 4.6 Paragraph 1 Landowner shall dedicate to City (through the recordation of a grant deed) the open space parcel in Newport Center comprised of approximately 3.18 acres of land area, bounded on the north by the Orange County Transportation Authority site, the east by MacArthur Boulevard, the south by San Miguel Drive, and the west by Avocado Avenue (“Open Space Parcel”),within thirty (30) days after the earliest of the following: (i) City has awarded a construction contract for the construction of City Hall at any location within the City or (ii) the option to purchase the Option Site has terminated as provided in Section 4.8.1 of Development Agreement No. DA2007-002.
Landowner shall convey the Open Space Parcel for open space or public facilities purposes, to City free and clear of all recorded and unrecorded monetary liens, any delinquent property taxes or assessments, and all tenancies, lessees, occupants, licensees, and all possessory rights of any kind or nature.
Check below if the answer to (i) or (ii) is “yes.”
(i) City has awarded a construction contract for the construction of City Hall at any location within the City
Date: Not Applicable
(ii) the option to purchase the Option Site has terminated as provided in Section 4.8.1 of Development Agreement No. DA2007-002.
Date: May 27, 2008
Within 30 days after the earliest of one of the two events listed above, Landowner shall dedicate to City (through the recordation of a grant deed) the open space parcel in Newport Center comprised of approximately 3.18 acres of land area
Check this box once the grant deed has been recorded.
Date: October 17, 2008
Annual Report – 2021 (January 2022) 13
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Open Space Dedication Section 4.6 Paragraph 1 Not specified Landowner shall, at its sole cost and expense, cause a title company selected by City to issue to City an owner’s policy of title insurance for the Open Space Parcel with liability in an amount reasonably determined by City (but not exceeding the fair market value of the Open Space Parcel) showing fee title to the Open Space Parcel vested in City, free and clear of the liens, rights, and encumbrances referred to in Section 4.6 of Development Agreement No. DA2007-002.
Check this box once Landowner, at its sole cost and expense, has caused a title company selected by City to issue to City an owner’s policy of title insurance for the Open Space Parcel
Date: October 17, 2008
Responsible party: Irvine Company
Retrofit Sprinkler Systems Section 4.9 Paragraph A The Newport Center Drive system retrofit shall be completed by June 2008. Landowner shall retrofit the existing sprinkler systems in the Newport Center Drive parkways and medians to low flow technology with the following specifications:
(1) The control system must monitor and adjust itself not less than daily, using either evapotranspiration rates for the Corona del Mar microclimate or soil moisture levels monitored at enough locations in the irrigation area as to cover each soil and slope type in Newport Center.
(2) The control system must adjust to rain conditions to limit or eliminate watering during rain events.
(3) The sprinkler heads must eliminate overspray onto roads, sidewalks, and other hardscape either by using highly targeted heads that only water the plant material or by using a sprinkler-like wicking system, such as the
Jardinière system
(4) The performance of the sprinkler systems must be monitored on a regular basis. Landowner agrees to install flow meters to detect line and/or sprinkler head breaks when wireless flow meter technology is proven and commercially available.
Check each box below upon implementation of the corresponding low flow technology listed to the left.
(1)
(2)
(3)
(4)
Check this box once the Newport Center Drive system retrofit is completed.
Date: November 1, 2008
Responsible party: Irvine Company
Annual Report – 2021 (January 2022) 14
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Retrofit Sprinkler Systems Section 4.9 Paragraph A The Fashion Island retrofit shall be completed in phases in conjunction with the water quality enhancements in Section 4.9B of the Development Agreement.
Landowner shall retrofit the existing sprinkler systems in the landscape areas within Fashion Island to low flow technology with the following specifications:
(1) The control system must monitor and adjust itself not less than daily, using either evapotranspiration rates for the Corona del Mar microclimate or soil moisture levels monitored at enough locations in the irrigation area as to cover each soil and slope type in Newport Center.
(2) The control system must adjust to rain conditions to limit or eliminate watering during rain events.
(3) The sprinkler heads must eliminate overspray onto roads, sidewalks, and other hardscape either by using highly targeted heads that only water the plant material or by using a sprinkler-like wicking system, such as the
Jardinière system
(4) The performance of the sprinkler systems must be monitored on a regular basis. Landowner agrees to install flow meters to detect line and/or sprinkler head breaks when wireless flow meter technology is proven and commercially available.
Check each box below upon implementation of the corresponding low flow technology specification listed to the left.
(1)
(2)
(3)
(4)
Check this box once the Fashion Island retrofit is completed
Date: December 2009
Sprinkler retrofit is 100% complete.
Responsible party: Irvine Company
Fashion Island Water Quality Enhancements
Section 4.9 Paragraph B Not specified Landowner commits to expend a minimum of $1 million to enhance the water quality treatment (which could include bio-filtration, media filtration or other technology) of those surface parking areas of Fashion Island which are not otherwise included within the new development or redevelopment projects.
Landowner has full discretion as to the treatment methods utilized and improvement phasing, to ensure that the improvements integrate with the water quality treatment plans of the new development areas.
For the year 2014, indicate the amount expended to enhance the water quality treatment of those surface parking areas in Fashion Island:
For 2014 $47,300
Cumulative Total – see page 20 for additional information $1,030,674
Completed
The amount spent above is as of December 31, 2014.
Responsible party: Irvine Company
Annual Report – 2021 (January 2022) 15
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Fashion Island Water Quality Enhancements
Section 4.9 Paragraph B Annually. The first report is due by January 18, 2009 (one year after the Effective Date of January 18, 2008).
Landowner agrees to make annual reports to the City regarding the progress of these enhancements including the work performed and the amount expended.
Check this box when the 2014 Annual Report is submitted to the City. Date: January 16, 2015
Maintenance was conducted on the water quality treatment systems. See page 20 for additional information for year 2014.
Responsible party: Irvine Company
Cooperation of Landowner if City Hall Constructed on Property North of Library
Section 4.10 Paragraph 1 If City elects to construct a new City Hall on the property located on the east side of Avocado Avenue, north of the Central Library
Landowner shall cooperate in good faith with City to implement any necessary land use regulations, including zoning amendments, and to release and terminate the use restrictions contained in the deed for the property to allow for and accommodate construction of a new City Hall on that site.
Check this box if the City elects to construct a new City Hall on the site north of the Central Library.
Check this box once Landowner has cooperated in good faith with the City and has released and terminated the use restrictions contained in the deed for the property. Date: May 20, 2008
Responsible party: Irvine Company
Dedication of Lower Castaways Section 4.11 Paragraph 1 Upon issuance of the First Building Permit Landowner shall dedicate to City the Lower Castaways site for municipal or municipally sponsored uses allowed under the General Plan’s Recreational Marine Commercial designation, such as park, marine educational facility, marine research and conservation facility, or marine and harbor dependent service and support uses and other similar uses in furtherance of the Tidelands Trust.
Check this box once the first building permit has been issued. Date: Not Applicable
Check this box once the Lower Castaways site has been dedicated to the City Date: October 17, 2008
Responsible party: Irvine Company
Dedication of Lower Castaways Section 4.11 Paragraph 1 Not specified The property shall have a deed restriction in favor of Landowner which shall restrict the City’s use of the property to such uses (listed in the row above), and allow the City to contract with a for profit or non-profit entity to operate certain municipal facilities or to use the property in furtherance of such uses; provided that the City may not transfer the property, by sale or long-term lease to any private, for-profit company for any commercial boat marina.
Check this box once a deed restriction has been issued in favor of the Land-owner for the Lower Castaways site Date: October 17, 2008
Responsible parties: Irvine Company and the City of Newport Beach
Annual Report – 2021 (January 2022) 16
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Ongoing Obligations and Public Benefits
The table below lists ongoing obligations from Irvine Company and additional public benefits resulting from Development Agreement No. DA2007-002
referenced above and as amended in August 2012. Ongoing obligations and public benefits listed in the table below are from various sections of the
Development Agreement, not including Section 4, Public Benefits.
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Implement and Document Compliance with AHIP
Section 3 Implementation schedule:
* Certificate of use and occupancy for 100th market rate unit / one-third of required units. * Certificate of use and occupancy for 200th market rate unit / one-third of required units. * Certificate of use and occupancy for 300th
market rate unit / one-third of required units.
Affordable housing agreement will be executed and recorded for designated affordable units in The Bays apartment complex before the point where a certificate of use and occupancy is issued for the related market rate units.
TIC must implement and document compliance with the Affordable Housing Implementation Plan (“AHIP”) as amended and adopted in August 2012.
Check the appropriate box once an affordable housing agreement has been executed and recorded for each phase below.
Affordable Housing Agreement Executed: August 5, 2015 Recorded: September 15, 2015
100th market rate unit Date: October 6, 2017
200th market rate unit Date: October 6, 2017
300th market rate unit Date: October 6, 2017
Responsible party: Irvine Company
Pubic Benefit Fee Section 6 (Amendment) A fee shall be paid for the 431st unit and all subsequent units at the time the building permit is issued
A total of $63,000.00 per unit for the additional 94 units approved in 2012 shall be paid. The total payment is $5,922,000.00
Building permit issuance for units
431 through 524.
Date: November 3, 2014
Payment: $5,922,000.000
Responsible party: Irvine Company
Public Benefit Fee for Parks Section 7 (Amendment) Prior to issuance of each building permit a Public Benefit Fee for parks shall be paid on or before July 1, 2013.
TIC shall pay $26,046.51 per unit for each of the additional 94 residential units added to the NNCPC. Amount paid by TIC to City for Public Benefit Fee for Parks: $2,448,371.94
Date: July 1, 2013
Responsible party: Irvine Company
Complete*
*Amount was paid on or before July 1, 2013
but not reported in the 2013 Annual Report
Annual Report – 2021 (January 2022) 17
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires August 2032
Type of Fee,
Contribution or
Dedication
Development
Agreement
Reference Timing/Milestone Payment/Contribution/Dedication Status
Development of Option Site with 72,000 Square Feet of office use
Sections 6.7 and 7.1 TPO approval and compliance with the fair share traffic fee requirements must occur before TIC can develop the Option Site.
Since the City will not be developing the Option Site with 72,000 square feet:
TIC must conduct a traffic analysis, provide traffic mitigation in compliance with the Traffic Phasing Ordinance (“TPO”), pay the applicable Fair Share Traffic Fees, and obtain TPO approval from the Planning Commission (appeal goes to City Council) before it can develop the Option Site with 72,000 square feet of office use.
Check this box when TPO approval and compliance is attainted
Date: August 7, 2008
Responsible party: Irvine Company
Complete Construction of a Third Eastbound Left Turn Lane at the Intersection of MacArthur Blvd. and San Joaquin Hills Road
Section 7.3 No later than the earlier of: (1) the date the City issues the certificate of occupancy for any new development under the First Building Permit (but specifically excluding the building permit for the Parking Structure), or (2) the date that is 60 months after the Effective Date.
60 months after the Effective Date is January 18, 2013 (60 months after January 18, 2008).
Complete construction of a third eastbound left turn lane at the intersection of MacArthur Boulevard and San Joaquin Hills Road (within the existing right of way except for any needed dedication at the southwest corner).
Check this box once lane construction is complete
Date: October 2012
Responsible party: Irvine Company
Reimbursement for Bayside Walkway Connection
Section 8 (Amendment) Payment by Landowner to City within 90 days after receipt of written notice that contract for project construction has been awarded.
No more than $200,000.00 reimbursement for actual costs for plans, specifications, permits and/or construction.
Amount paid by Landowner to City: $152,257.22
Date: July 5, 2014
Responsible party: Irvine Company
Complete
Annual Review of Compliance with Code Sections
Section 14 First annual review (including an updated tracking chart of built intensity and provision of public benefits) must take place by January 18, 2009 (one year after the Effective Date of January 18, 2008).
The parties must conduct annual review of compliance with California Government Code sections 65865 and 65865.1 and City of Newport Beach Municipal Code §15.45.070.
TIC must document the current status of its entitlement use (i.e., a tracking chart of built intensity) and its provision of the public benefits identified in Section 4 of the Development Agreement.
Check this box once the first annual review has taken place
Date: January 16, 2009
(City Council approval February 24, 2009)
Responsible party: Irvine Company
Annual Report – 2020 (January 2021) 18
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires 2032
City Concurrence
By signing below, the City acknowledges its concurrence with the information presented in the Annual Report.
City Acknowledgement
Signature Date
Title
Annual Report Distribution
A complete Annual Report for North Newport Center shall be completed and distributed no later than January
18 following each prior year to the individuals listed below.
City of Newport Beach
100 Civic Center Drive
Post Office Box 1768
Newport Beach, California 92658-8915
Attn: City Manager
City of Newport Beach
100 Civic Center Drive
Post Office Box 1768
Newport Beach, California 92658-8915
Attn: City Attorney
Irvine Company
550 Newport Center Drive
Newport Beach, California 92660-0015
Attn: Jeff Davis
Latham & Watkins LLP
600 West Broadway, Suite 1800
San Diego, California 92101-3375
Attn: Christopher W. Garrett
Annual Report – 2020 (January 2021) 19
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires 2032
4.4 Circulation Enhancements to Public Right of Way – Completed 2013
Section 4.4 of the North Newport Center Zoning Implementation and public Benefit Agreement requires that individual enhancement projects be established through
discussion with the City of Newport Beach Director of Public Works. The table below lists the individual projects resulting from those discussions and the actual or estimated
cost for individual project components as of December 31, 2013. Projects 1-4 were completed in 2012. Project 5 was completed in 2013. As shown in the table, the total
Irvine Company contribution through a combination of direct construction costs and reimbursement to the city exceeded the established maximum requirement of
$2,500,000.
North Newport Center – Circulation Enhancements to Public Right of Way
Transportation Improvements Program
Completed December 31, 2013
Project Estimated Project Cost1
Potential CEC
Contribution
Cumulative CEC Total Potential Contribution
(Maximum Contribution
Limited To $2,500,000)2
Remaining CEC
Commitment
1. San Miguel Widening and Intersection Improvements (MacArthur to west of Avocado)
including:
- Signal modifications at MacArthur and Avocado
- Relocation of NW corner entry monument and pine tree replacement
(Complete 2012)
Contract Cost = $ 1,355,6503
CIOSA Funding = $ 450,330
Remaining Cost = $ 905,320
City Reimbursement = $ 905,320
Additional Costs = $ 42,8884
Total Contribution = $ 948,208 $948,208 $1,551,792
2. Upgrade Existing Newport Center Traffic Signals (City Project No. C3002009)
including:
- Interconnection of Signals
- Traffic Signal @ Anacapa/Newport Center Drive (Partial)
- Signal Modifications @ San Miguel/Newport Center Drive (Complete)
(Complete 2012) $920,9645 $910,4836 $1,858,691 $641,309
3. Newport Center Drive Parking Revisions
(Complete 2012) $90,000 $90,0007 $1,948,691 $551,309
4. Add fourth leg to Center Drive intersection with Newport Center Drive and signalize
(Complete 2012) $300,0008 $354,4969 $2,303,187 $196,813
5. Operational Improvements to streets adjacent to Blocks 500 and 600 of Newport
Center Drive (Santa Rosa Revisions - Built by Irvine Company)
(Complete 2013) $240,828 $278,83810 $2,582,02511 -0-
1 As established in Section 4.4 of the 2011 North Newport Center Annual Report
2 Per North Newport Center, “Zoning Implementation and Public Benefit Agreement” – Section 4.4 (December 18, 2007)
3 Excluding City contributions of $125,000 (City Hall costs for Farallon City Hall site entry)
4 Direct costs to Irvine Company incurred outside of City Contract
5 Based on Contract awarded (6/14/11) including $51,000 of contingencies
6 Per Tony Brine’s September 13, 2013 e-mail
7 Per $90,000 final cost, consisting of $51,200 in contractor costs (per 9/13/13 e-mail from Tony Brine) and $38,800 spent by Irvine Company on project development and design
8 Per Irvine Company documentation
9 Per final contract costs provided by Irvine Company
10 Per Irvine Company’s final project cost for design and construction
11 The total amount paid/contribute by Irvine Company, therefore, exceeds the Maximum Contribution by $85,025.
Annual Report – 2020 (January 2021) 20
North Newport Center Zoning Implementation and Public Benefit Agreement – Expires 2032
4.9 B. Fashion Island Water Quality Enhancements – Fashion Island Parking Areas
Fashion Island WQMP Master Plan and Treatment - A master treatment plan has been created for all parking
lot surface areas in Fashion Island, taking into consideration timing of development phasing, maximizing
treatment potential for non-development areas and implementing construction efficiencies for cost
minimization.
Technical oversight on treatment design and selection to meet State Water Quality Treatment requirements
utilizing bio-retention, media filtration and other technology was provided by Stantec Civil Engineering, NMG
Soil Engineering and Geosyntec Engineering, a leading bio-retention engineering company.
The proposed treatment plan when fully implemented would treat 95% of the parking lot surface areas and 95%
of building and hardscape areas. The treatment design will include four bio-retention systems and six media
cartridge vault systems designed to treat a total tributary area of 1,687,617 square feet of surface parking area,
including 1,539,099 square feet of Non-Development area. An additional 1,283,180 square feet of retail building
area, including 1,096,658 square feet of Non-Development area, will be treated as a result of utilization of
existing storm line systems. Nineteen percent of non-development tributary area will be treated by bio-retention
systems with the remaining 81% treated by media cartridge vault. Additional water quality improvements will
occur in future years.
The following tables identify the Non-Development Water Quality Treatment from 2008 through December 31,
2014, and the compliance to date with Section 4.9, Paragraph B of the Development Agreement. Water quality
treatment costs in 2014 include maintenance of the water quality treatment systems.
Fashion Island Non-Development Water Quality Treatment – Completed 2014
Location/Name
Tributary
Area (sf)1
Non-
Development
Area (sf)2
Installation
Cost
Operational
Cost Total Cost
Total Cost
2008
Total Cost
2009
Total Cost
2010
Total Cost
2011
Total Cost
2012
Total Cost
2013
Total Cost
2014
1 Bldg. B
and C 299,623 174,240 $121,709 - $121,709 - - - - $121,709 -
3 PS2
Frontage 324,251 16,273 $10,932 - $10,932 - $10,932 - - - -
3 Bldg. D 58,735 4,000 $88,748 - $88,748 - - - - $88,748
4 PS2 160,453 102,727 $99,020 - $99,020 - $99,020 - - - -
5,6 Center
Drive 406,642 349,787 $217,957 - $217,957 - - - - $217,957 -
7,8 Eastside 871,133 432,234 $282,158 $250 $282,408 $112,961 $169,447 - - - -
Maintenance - - - - - - - $34,000 $34,000 $47,300 $47,300 $47,300
Total $731,776 $250 $732,026 $112,961 $279,399 $34,000 $34,000 $386,966 $136,048 $47,300
1 This figure represents the total area treated and includes Development and Non-Development areas.
2 This figure represents only the Non-Development parking lot surface areas treated.
Compliance to Date, Section 4.9, Paragraph B – Development Agreement
Commitment Existing Enhancement
2014
Enhancement
Commitment
To-Date Remaining Commitment
$1,000,000 $983,374 $47,300 $1,030,674 $0