Loading...
HomeMy WebLinkAboutBig Canyon Phase 2A Council 050219Big Canyon Nature Park Replace Invasive Trees with Natives •Remove Brazilian Pepper Trees •Replace with Sycamores, Cottonwood and Willows June 2018 Phase 2A Concept Restoration Plan Pocket Sllide: Future Improvements: Phases 2B and 2C 1.Fresh water lake sediments impacted by selenium. 2.Fresh water lake is a mosquito breeding area. 3.Invasive trees and plants. 4.Plants and animals will migrate into canyon with rising sea levels. Schedule •February 2018 - NBC wins design grant for Phase 2A •NBC hires ESA for the construction documents •April 2019 - NBC wins construction grant for Phase 2A •June, 2019 – Agreement between NBC and City for City to manage construction. •July 2019 – Council considers awarding construction contract •September 1, 2019 – Construction commences •December 20, 2019 – Project substantially complete!