HomeMy WebLinkAbout06 - Newport Beach Junior Lifeguard Building Project - NOC for Contract No. 7524-2 (19F13)Q �EwPpRT
CITY OF
s NEWPORT BEACH
`q44:09 City Council Staff Report
October 8, 2024
Agenda Item No. 6
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Peter Tauscher, Senior Civil Engineer - 949-644-3316,
ptauscher@newportbeachca.gov
TITLE: Newport Beach Junior Lifeguard Building Project — Notice of
Completion for Contract No. 7524-2 (19F13)
ABSTRACT:
On August 23, 2022, the City Council awarded Contract No. 7524-2 for the Newport
Beach Junior Lifeguard Building project to TELACU Construction Management, Inc.
(TELACU) of Orange. The work is now complete and staff requests the City Council
accept the work and close out the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project.
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded Contract
Final Total Contract
Total Contract
Percent Contract
Amount
Amount
Change Amount
Cost Change
$6,430,000.00
$6,762,462.79
$332,462.79
5.2%
Allowed Contract Time + Approved
294
Actual Time Used (Days)
349
Extensions (Days)
This project consisted of constructing the new Junior Lifeguard Building near the Balboa
Pier. The building replaced the temporary facilities that the Junior Lifeguard program
operated from for many years. The new building serves as a multi -functional space for
use by the Junior Lifeguard program and public, with programs and rentals offered
through the Recreation and Senior Services Department.
6-1
Newport Beach Junior Lifeguard Building Project —
Notice of Completion for Contract No. 7524-2 (19F13)
October 8, 2024
Page 2
The new facility is approximately 5,420 square -feet of usable interior space that includes:
• A 1,050-square-foot meeting room
• Secure interior and exterior storage rooms
• Staff offices and meeting rooms
• Men's and women's locker rooms
• A 1,350-square-foot deck area
• Public restroom facilities
The project also included landscaping and paving in the A Street and Balboa parking lots.
The contracted work has now been completed to the satisfaction of the Public Works
Department. A summary of the construction costs are as follows:
Original Bid Amount: $ 6,430,000.00
Actual Cost of Bid Items Constructed: $ 6,430,000.00
Total Change Orders: $ 469,962.79
Liquidated damages due to TELACU's tardy performance: $ (137,500.00)
Final Total Contract Amount: $ 6,762,462.79
The final total contract amount is $6,762,462.79, approximately 5.2% higher than the
original bid amount. The cost increase was primarily due to adding offsite work to the
project scope, which included upgrading the water system. After the project was awarded,
the Utilities Department requested a closed loop system, which accounted for about 3%
of the contingency. Other change orders included changes to lighting, storm drain, fire
water supply systems, improved construction material for roofing, ceiling and
landscaping, and meeting added Southern California Edison requirements.
Following the construction of several of the concrete walls, staff inspected the finished
product and rejected walls that did not meet the requirements of the contract documents
or TELACU's own submittals and mockup. Many of the walls needed to be demolished
and replaced. Although the defects were caused solely by TELACU and its concrete
subcontractor, the City, in the spirit of cooperation, granted TELACU's request for an
additional 122 working days for the removal and replacement of the faulty walls. Despite
this City concession, TELACU was not able to follow the schedule it created and was
assessed 55 days of liquidated damages.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule September 6, 2022
Actual Start of Construction Per Notice to Proceed September 6, 2022
Extended Contract Completion Date Inclusive of Extra Work February 28, 2024
Actual Substantial Construction Completion Date June 28, 2024
The original construction schedule showed completing the project in May 2023, but due
to the defective concrete work, the project was not substantially complete until June 2024.
6-2
Newport Beach Junior Lifeguard Building Project —
Notice of Completion for Contract No. 7524-2 (19F13)
October 8, 2024
Page 3
TELACU demobilized, secured the site, and remobilized in September 2023, at which
time the contract working day clock was re-established. TELACU did not complete the
work within the approved contract time, even with the additional 122 days requested by
the contractor after the remobilization. The contractor was assessed liquidated damages
per the contract documents. As a result of TELACU's work quality and schedule
deficiencies, additional resources were required to finish the project. This included
providing additional oversight consisting of City staff and design consultants to ensure the
project was completed in accordance with the requirements of the contract.
It is important to note that TELACU disputes the City's position regarding the sufficiency
of the original concrete walls and has filed a claim against the City in the amount of
$1,259,028.96.1 Staff and the City Attorney's office are currently engaged in the statutory
dispute resolution process and will brief the City Council at a future meeting. The pending
claim does not impact the City's filing of the Notice of Completion.
FISCAL IMPACT:
Funds for the construction contract were expended from the following accounts:
Account Description
Account Number
Amount
American Rescue Plan Act (ARPA)
16601-980000-19F13
$
4,464,630.00
ARPA
16601-980000-221`13
$
450,000.00
NBJG Foundation Contributions
13501-980000-19F13
$
1,772,849.75
Junior Lifeguard Capital (FFP)
53101-980000-19F13
$
74,983.04
Total: $
6,762,462.79
ENVIRONMENTAL REVIEW:
On August 23, 2022, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15332 (In -Fill Development
Projects) of the CEQA Guidelines. This exemption applies to in -fill development projects
in urban areas that are consistent with the General Plan and applicable development
standards.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
TELACU has recently filed a second claim in the amount of $388,808.75 related to 18 separate alleged
change order events. Staff is currently evaluating these allegations.
6-3
ATTACHMENT A
/ / > Au <1„
A
�9 C/F/C
ocF�N
NEWPORT BEACH
JUNIOR LIFEGUARD BUILDING
NOT TO SCALE
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
mvzzz,, /mom
0
C-7261-02 9/24/2024
m.