CITY OF
z NEWPORT BEACH
c�<,FORN'P City Council Staff Report
October 22, 2024
Agenda Item No. 8
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Michael J. Sinacori, Assistant City Engineer - 949-644-3342,
msinacori@newportbeachca.gov
TITLE: Newport Boulevard Landscape Improvements (Industrial Way to
Pacific Coast Highway) and West Coast Highway Landscaping
Improvements (West City Limits to Highland St.) — Notice of
Completion for Contract No. 9226-1 (231-01)
ABSTRACT:
On January 9, 2024, the City Council awarded Contract No. 9226-1 for the Newport
Boulevard Landscape Improvements (Industrial Way to Pacific Coast Highway) and West
Coast Highway Landscaping Improvements (West City Limits to Highland St.) project to
Marina Landscape Inc. The project improved the landscaping and irrigation along the
northern city limit slopes and median of Newport Boulevard and near the western city limit
of West Coast Highway. The work is now complete and staff requests the City Council
accept the work and close out the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project.
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded Contract
Final Total Contract
Total Contract
Percent Contract
Amount
Amount
Change Amount
Cost Change
$1,026,120.96
$1,061,193.86
$35,072.90
3.42%
Allowed Contract Time + Approved
110
Actual Time Used (Days)
110
Extensions (Days) _
This project included median and slope landscape and irrigation work on Newport
Boulevard and landscape and irrigation work in the setback area of West Coast Highway.
RX
Newport Boulevard Landscape Improvements (Industrial Way to Pacific Coast Highway)
and West Coast Highway Landscaping Improvements (West City Limits to Highland St.)
— Notice of Completion for Contract No. 9226-1 (231_01)
October 22, 2024
Page 2
The contracted work has been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original Bid Amount:
Actual Cost of Bid Items Constructed:
Total Change Orders:
Final Contract Cost:
$ 1,026,120.96
$ 1,026,120.96
$ 35,072.90
$ 1,061,193.86
The final total contract amount was $1,061,193.86, which was approximately 3.42%
higher than the original bid amount. This cost increase was primarily due to change order
requests from City of Newport Beach staff for additional planting south of Hospital Road
and installing improved irrigation boxes, and dealing with unanticipated conditions during
construction, such as discovering asphalt underneath the soil in both areas of the project
and fixing vandalized irrigation boxes.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule February 12, 2024
Actual Start of Construction Per Notice to Proceed March 11,2024
Estimated Contract Completion Date per Annual Baseline August 30,2024
Schedule
Actual Substantial Construction Completion Date July 23, 2024
Due to rain impacts in the spring, the start of the construction was delayed, and additional
days were added due to increased grow/kill time and for the landscape work that was
added south of Hospital Road. The beginning of the maintenance period marks the start
of the substantially complete date, which was still ahead of the contract completion date.
FISCAL IMPACT:
The Newport Boulevard Landscape Improvements (Industrial Way to Pacific Coast
Highway) and West Coast Highway Landscaping Improvements (West City Limits to
Highland St.) project was included within the FY 2023-24 Capital Improvement Program
(CIP) Budget. Funds for the construction contract were expended from the following
accounts:
Account Description
General Fund — CIP
Neighborhood Enhancement
Neighborhood Enhancement
Account Number
/i u�"Tiwne
01201927-980000-24L01 $ 385,055.84
53601-980000-22L01 $ 64,113.12
53601-980000-23L01 $ 612,024.90
Total: $ 1,061,193.86
FIN
Newport Boulevard Landscape Improvements (Industrial Way to Pacific Coast Highway)
and West Coast Highway Landscaping Improvements (West City Limits to Highland St.)
— Notice of Completion for Contract No. 9226-1 (231-01)
October 22, 2024
Page 3
ENVIRONMENTAL REVIEW:
On January 9, 2024, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301 (h) (maintenance of
existing landscaping) of the CEQA Guidelines, California Code of Regulations, Title 14,
Chapter 3, because it has no potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
Iz
ATTACHMENT A
LIMITS OF WORK
NEWPORT BOULEVARD & WEST COAST
HIGHWAY LANDSCAPING IMPROVEMENTS
LOCATION MAP
J
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-9226-1 23 L01 10/22/2024