Loading...
HomeMy WebLinkAbout04 - West Coast Highway Joint Manhole & Valve Adjustments (Project No. 24R09) — NOC for Contract No. 9417-1Q �EwPpRT CITY OF s NEWPORT BEACH `q44:09 City Council Staff Report January 28, 2025 Agenda Item No. 4 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Michael J. Sinacori, Assistant City Engineer - 949-644-3342, msinacori@newportbeachca.gov TITLE: West Coast Highway Joint Manhole & Valve Adjustments (Project No. 24R09) — Notice of Completion for Contract No. 9417-1 On January 9, 2024, the City Council awarded Contract No. 9417-1 for the West Coast Highway Joint Manhole & Valve Adjustments project to R.J. Noble Company. The project lowered and raised manholes and valve boxes for both the City of Newport Beach and the Orange County Sanitation District, and was performed in conjunction with the pavement rehabilitation by Caltrans along West Coast Highway between Jamboree Road and the Santa Ana River bridge. The work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project. DISCUSSION: Overall Contract Cost/Time Summary Awarded Contract Final Total Contract Total Contract Percent Contract Amount Amount Change Amount Cost Change $922,925.00 $1,020,426.22 +$97,501.22 10.6% Allowed Contract Time + Approved 45 Actual Time Used (Days) 45 Extensions (Days) = This project ensured that City and Orange County Sanitation District (OC San) facilities were properly lowered before the pavement rehabilitation and raised to final grade after the paving process. 4-1 West Coast Highway Joint Manhole & Valve Adjustments — Notice of Completion for Contract No. 9417-1 January 28, 2025 Page 2 The contracted work has been completed to the satisfaction of the Public Works Department. A summary of the construction cost is as follows: Original Bid Amount: $ 922,925.00 Actual Cost of Bid Items Constructed: $ 922,925.00 Total Change Orders: $ 97,501.22 Final Contract Cost: $1,020,426.22 The final total contract amount was $1,020,426.22, which was approximately 10.6% higher than the original bid amount. This cost increase was primarily due to a need to modify the construction trucks and equipment to reduce the back-up alarm noise because of the required night work next to residential areas; additional slip cans installed at City water valve boxes; further concrete improvements along West Coast Highway; as well as OC San and other outside agencies requesting additional facilities grade adjustments. A summary of the project schedule milestones is as follows: Estimated Start of Construction per Annual Baseline Schedule March 11, 2024 Actual Start of Construction Per Notice to Proceed March 18, 2024 Estimated Completion per Annual Baseline Schedule November 29, 2024 Substantial Completion Date Inclusive of Extra Work December 5, 2024 The long period between lowering manholes/valves at the start of the project and raising them again at the end of the project was due to the duration of the pavement rehabilitation work performed by Caltrans. Facilities were lowered in March and April of 2024 and raised in October through December of 2024. FISCAL IMPACT: The West Coast Highway Joint Manhole & Valve Adjustments project was included within the FY 2024-25 Capital Improvement Program (CIP) Budget. Funds for the construction contract were expended from the following account(s)- Account Description Account Number Amount Water Capital 70201-980000-24R09 $ 252,377.24 CMSD Contribution Account 13501-980000-24R09 $ 9,217.46 Mesa WD Contribution Account 13501-980000-24R09 $ 13,480.21 OCWD Contribution Account 13501-980000-24R09 $ 6,561.44 Concrete Replacement Program 01201927-980000-25R06 $ 39,660.90 (General Fund CIP) Wastewater Enterprise 71101-980000-24R09 $ 175,455.00 OC Sanitation Contributions 13501-980000-24R09 $ 523,673.97 Total: $ 1,020,426.22 4-2 West Coast Highway Joint Manhole & Valve Adjustments — Notice of Completion for Contract No. 9417-1 January 28, 2025 Page 3 Of the total project cost, $467,493.14 was funded by City accounts. Additional accounts were added to the project to recoup the $552,933.08 of costs associated with raising the facilities of outside agencies. The Water and Wastewater Enterprise Funds generate revenue primarily through water and wastewater rates collected by service users. ENVIRONMENTAL REVIEW: On January 9, 2024, the City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 (repair and maintenance of existing highways and streets, sidewalks, and gutters involving no expansion of use) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENT: Attachment A — Location Map 4-3 ATTACHMENT A NT; LIMITS OF WORK WEST COAST HIGHWAY JOINT MANHOLE & VALVE ADJUSTMENTS LOCATION MAP CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C-9417-1 24R09 1 /28/2025